Permit Information
Permit NumberESC15-00019
StatusFinaled
Name OLIVIA WEICK
Site Address 625 N WHITEWATER PARK BLVD
Project NameFarmers Union Canal Intake
Customer Number 
ePlanReviewNo
Description
Intake Modifications: Part of the Esther Simplot Park/Whitewater Park Development.Intake and installation of 400ft of culvert in canal. Installation of a Reinforced concrete intake, large box culvert and cast-in-place concrete control gate.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/30/20166/30/20166/30/2016 DONE
DetailsEvan Jenkins
DOC - Permit Finaled6/30/20166/30/20166/30/2016PPASS
DetailsEvan Jenkins
Project Complete
ESC Conditions Satisfied
This portion to the project is complete. Main park is still under ESC conditions to reach 70% re-veg
General Inspection6/15/20166/15/20166/15/2016 PASS
DetailsAndy J. Long
WIP. Final landscaping and park feature installation & clean up occuring.
General Inspection5/31/20165/31/20165/31/2016 PEND
DetailsEvan Jenkins
construction complete.
pending perm re-veg.
No ESC issues observed
General Inspection5/16/20165/16/20165/16/2016 PASS
DetailsEvan Jenkins
Intake work complete
waiting for re-vegetation prior to finaling out ESC Permit
General Inspection4/29/20164/29/20164/29/2016 CANC
DetailsAndy J. Long
rescheduled for tuesday 5/3
General Inspection4/14/20164/14/20164/14/2016 PEND
DetailsEvan Jenkins
General Inspection3/30/20163/30/20163/30/2016 PEND
DetailsEvan Jenkins
Construction Complete
Pending re-veg
General Inspection3/15/20163/15/20163/16/2016 PASS
DetailsAndy J. Long
Canal intake structure is complete. Disturbed areas around intake have been hydroseeded. No corrections associated with this phase. See also ESC15-00306
General Inspection2/29/20162/29/20163/1/2016 PASS
DetailsEvan Jenkins
Conference2/12/20162/12/20162/12/2016PPASS
DetailsAndy J. Long
Met with Boise Public Works project manager Rob to view the recently completed canal intake. No turbidity source in the River observed. Bank and has been stabilized with large boulders.

Topsoil was applied this week. Hydroseeding and tacifier to be applied next week around the intake and in between the new Greenbelt path and Veteran's Pond.

Will come view the hydroseeding application next week. No corrections issued at this time.
General Inspection2/11/20162/11/20162/11/2016 PEND
DetailsEvan Jenkins
Coffer dam has been removed. Construction on new wier gates complete. Awaiting perm re-vegetation to take place this spring
General Inspection1/27/20161/27/20161/27/2016 PASS
DetailsEvan Jenkins
General Inspection1/12/20161/12/20161/12/2016 PASS
DetailsEvan Jenkins
No activity at time of inspection. No discharges leaving site at this time. no ESC issues observed
General Inspection12/28/201512/28/201512/28/2015 CANC
DetailsAndy J. Long
General Inspection12/11/201512/11/201512/11/2015 PASS
DetailsEvan Jenkins
WIP: No discharges entering boise river, or other esc issues observed
General Inspection11/26/201511/26/201511/27/2015 PASS
DetailsAndy J. Long
WIP on canal culvert installation at Esther Simplot Park. No activity at time of inspection. No trackout from site, no issues regarding coffer dam structure. No trackout or discharges offsite. No corrections.
General Inspection11/11/201511/11/201511/12/2015 PASS
DetailsEvan Jenkins
WIP on canal intake. No issues observed at this time
Complaint Inspection10/27/201510/27/201510/28/2015PPASS
DetailsAndy J. Long
Plume reported in Boise River Tuesday 10/27. Site inspection conducted at 4 PM. Investigated site with SWPPP coordinator for McMillen- Jacobs ACHD SWPPP Inspector.

Leak from river was going through cofferdam structure blocking off area of box culvert location, filling the area of work with water. To stop the leak the exterior lining on the dam was extended and more earth material added to the dam, which caused some turbid discharges of sediment down river during the activity. Turbidity was meaurred and is reported in the SWPPP daily report. SWPPP coordinator stated the turbidity did not reach reportable levels.


Inspection of the area of concern did not reveal any active plumes into Boise River and no BMP failures were identified. The rest of the site is in good condition, trackout and perimeter controls are working well. Dewatering system is still treating water passing through site and ground water being pumped.

No corrections. Site has fixed problem and has reported the corrective action.
General Inspection10/20/201510/20/201510/20/2015 PASS
DetailsEvan Jenkins
WIP: No ESC issues observed at this time. Inspection took place at 12:00pm
General Inspection10/5/201510/5/201510/5/2015 PASS
DetailsEvan Jenkins
WIP: BMP's in place. No ESC issues observed at this time
General Inspection9/18/20159/18/20159/18/2015 PEND
DetailsEvan Jenkins
Hasn't started yet
General Inspection9/3/20159/3/20159/3/2015 PEND
DetailsEvan Jenkins
Project has not begun yet
General Inspection8/19/20158/19/20158/19/2015 NR
DetailsEvan Jenkins
Olivia stated this portion of the project has been put on hold for approximately one more month. No work is occuring at this time.
General Inspection8/4/20158/4/20158/4/2015 PASS
DetailsEvan Jenkins
General Inspection7/20/20157/20/20157/20/2015 PASS
DetailsEvan Jenkins
General Inspection7/3/20157/3/20157/6/2015 PASS
DetailsAndy J. Long
No offhauling currently. Still in proecess of excavating old pond area to dig new pond. No dust issues or trackout observed. No activity directly next to River corridor. No corrections at this time. Full walk through needs to be scheduled.
Aging Inspection6/12/20156/12/20156/12/2015 PASS
DetailsEvan Jenkins
Random Inspection2/11/20152/11/20152/11/2015PPASS
DetailsAndy J. Long
Limited activity at time of inspection. Got report that there was a muddy discharge downstream from Farmer Union intake area.

After further investigation it is clear that the turbid flow is coming from Crane Creek, not from this project.
General Inspection2/6/20152/6/20152/6/2015PPASS
DetailsAndy J. Long
Staging areas and initial BMPs have been installed for Phase II of Esther Simplot. No excavation activity at site yet. No corrections needed at this time.
Site Preparation1/15/20151/16/20151/16/2015PPASS
DetailsEvan Jenkins
Silt Fence is installed correctly in two locations. McMillen placed large construction access rock throughout the entire haul road to minimize trackout as much as possible. Permit is posted w/ SWPPP onsite. As the project advances, they will install more BMP's as they go. No esc issues
Site Preparation1/12/20151/16/20151/15/2015ACANC
DetailsEvan Jenkins
Greg Phone #: ###-####
McMillen & Parks and Rec were not ready for initial schedualed Site prep for morning inspection. Reschedualed for PM. EEJ