Site Final | 5/16/2018 | 5/17/2018 | 5/17/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 5/16/2018 | 5/16/2018 | 5/16/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/1/2018 | 5/1/2018 | 5/1/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/16/2018 | 4/16/2018 | 4/16/2018 | | PASS |
Michael Zawacki
|
|
|
One vacant lot remaining in development. Every other home is complete and stable,.
|
General Inspection | 3/30/2018 | 3/30/2018 | 3/30/2018 | | PASS |
Michael Zawacki
|
|
|
Landscapers on site.
|
General Inspection | 3/15/2018 | 3/15/2018 | 3/15/2018 | | PEND |
Michael Zawacki
|
|
|
Rilling on hill behind house and through side of lot. Talked to landscaper on site.
|
General Inspection | 2/28/2018 | 2/28/2018 | 2/28/2018 | | PASS |
Michael Zawacki
|
|
|
Yard is still all exposed.
|
General Inspection | 2/13/2018 | 2/13/2018 | 2/15/2018 | | PASS |
Michael Zawacki
|
|
|
Home complete, yard needs stabalization.
|
General Inspection | 1/29/2018 | 1/29/2018 | 1/29/2018 | | PASS |
Michael Zawacki
|
|
|
Home complete, no landscaping in place. Perimeter BMPs installed. Some rilling in back yard.
|
General Inspection | 1/12/2018 | 1/12/2018 | 1/12/2018 | | PASS |
Michael Zawacki
|
|
|
WIP. Perimeter has been protected with gator guard. Runoff has been swept off.
|
General Inspection | 12/28/2017 | 12/28/2017 | 12/28/2017 | | PASS |
Michael Zawacki
|
|
|
WIP on interior.
|
General Inspection | 12/13/2017 | 12/13/2017 | 12/13/2017 | | PASS |
Michael Zawacki
|
|
|
Exterior appears complete. Rock wall and front steps complete. Yard still needs landscaping and stabalization. Gator guard in use on slope.
|
General Inspection | 11/28/2017 | 11/28/2017 | 11/28/2017 | | PASS |
Michael Zawacki
|
|
|
WIP on interior. Yard is getting rock wall. Still needs stabalization.
|
General Inspection | 11/13/2017 | 11/13/2017 | 11/13/2017 | | PASS |
Michael Zawacki
|
|
|
Neighborhood BMPs maintained. Yard still exposed, needs landscaping. One area where gator guard blew out but looks like it was repaired today, still some runoff on road.
|
General Inspection | 10/27/2017 | 10/27/2017 | 10/27/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/12/2017 | 10/12/2017 | 10/13/2017 | | FAIL |
Michael Zawacki
|
|
|
Someone removed and piled gator guard. Sediment runoff going down the hill. Light rain during inspection. Attempted to call RP but getting bust signal.
|
General Inspection | 9/27/2017 | 9/27/2017 | 10/2/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/8/2017 | 9/8/2017 | 9/8/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/23/2017 | 8/23/2017 | 8/25/2017 | | PASS |
Andy J. Long
|
|
|
No sediment runoff or trackout. This phase of Hackberry Ranch in good condition.
|
General Inspection | 5/15/2017 | 5/15/2017 | 5/15/2017 | P | PASS |
Andy J. Long
|
|
|
WIP. Trash contained. Perimeter wattles installed to keep dirt from running off to Horse Trail and onsite storm water pond. All SFHs in progress are in compliance, workers parking on paved areas instead of open lots & dirt.
|
Site Preparation | 3/7/2017 | 3/7/2017 | 3/8/2017 | P | PASS |
Melissa Jannusch
|
|
|
Subdivision is clean. No corrections requested.
|