General Inspection | 4/30/2018 | 4/30/2018 | 4/30/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 4/13/2018 | 4/13/2018 | 4/13/2018 | | PASS |
Michael Zawacki
|
|
|
Home complete. Seeding in process.
|
General Inspection | 3/29/2018 | 3/29/2018 | 3/29/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/14/2018 | 3/14/2018 | 3/14/2018 | | PASS |
Michael Zawacki
|
|
|
Exterior construction and driveway complete. Working on landscaping. Talked to builder and he will remove witches hat across street.
|
General Inspection | 2/22/2018 | 2/27/2018 | 2/27/2018 | A | PASS |
Michael Zawacki
|
|
|
Driveway is done, landscapers on site. Lot is frozen and snow covered, no issues observed.
|
General Inspection | 2/21/2018 | 2/21/2018 | 2/22/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 2/6/2018 | 2/6/2018 | 2/6/2018 | | PART |
Michael Zawacki
|
|
|
DI across street needs to be cleaned. Stockpile is mostly removed. Exposed area is slightlt lower than street level. Trash is thrown away and site kept clean.
|
General Inspection | 1/16/2018 | 1/19/2018 | 1/19/2018 | P | PART |
Andy J. Long
|
|
|
Need to change out DI bag in front of house. No new erosion or evidence of muddy runoff observed
|
General Inspection | 1/16/2018 | 1/16/2018 | 1/16/2018 | | PART |
Andy J. Long
|
|
|
Need perimeter controls on upper side of driveway. Conduct DI maintenance.
|
General Inspection | 1/1/2018 | 1/1/2018 | 1/2/2018 | | PASS |
Michael Zawacki
|
|
|
WIP on stucco and interior. Some light track out. Trash being put in dumpster. Giant pile of backfill on lot next door.
|
General Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | | PASS |
Michael Zawacki
|
|
|
No trackout. Doing some trench work in front. Lots of backfill still stored on site.
|
General Inspection | 11/29/2017 | 11/29/2017 | 11/29/2017 | | PASS |
Andy J. Long
|
|
|
Preparing to pave driveway. No trackout observed. Should be done before end of year.
|
Random Inspection | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PEND |
Michael Zawacki
|
|
|
Talked to general contractor and said they will get it cleaned up. Concrete was washed out onto dirt, framers left waste laying around. Dumpster scheduled to be picked up Tuesday the 14th.
|
General Inspection | 10/31/2017 | 10/31/2017 | 10/31/2017 | | CANC |
Michael Zawacki
|
|
|
WIP on SFH. Currently framing. Wattles protecting swale on bottom.
|
General Inspection | 10/12/2017 | 10/12/2017 | 10/12/2017 | | PASS |
Andy J. Long
|
|
|
Townhome complete. WIP on other units. Temp BMPs to be removed upon final completion. ESC permit finaled.
|
Tracking Control | 9/25/2017 | 9/25/2017 | 10/2/2017 | P | PEND |
Andy J. Long
|
|
|
|
General Inspection | 9/21/2017 | 9/21/2017 | 9/26/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/5/2017 | 9/5/2017 | 9/8/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Melissa Jannusch
|
|
|
No trackout or run off onto street or sidewalk. Trash is contained. No corrections.
|
General Inspection | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | PASS |
Melissa Jannusch
|
|
|
Corrections have been addressed. A wattle has been added to the end of the silt fence to prevent run off. Sidewalk has been swept.
|
General Inspection | 5/22/2017 | 5/22/2017 | 5/22/2017 | P | FAIL |
Melissa Jannusch
|
|
|
Run off issues causing sediment to deposit on sidewalk. Silt fence is channeling runoff causing the problem. Left message with RP suggesting the addition of a wattle or other BMP to stop flow onto sidewalk. Correction request for RP to clean sediment of sidewalk follow up for next week.
|