Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberESC17-00847
StatusFinaled
Name JAMES WALSH
Site Address 2419 W FAIRVIEW AVE
Project NameAdare Manor Apartments
Customer Number 
ePlanReviewNo
Description
Building A: 166-Unit multi-family housing and accessory retail space. Jade Riley project manager 208-384-4422. SCE on 25th street.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final10/30/201911/1/201911/1/2019APASS
DetailsAndy J. Long
DI bags on Fairview have been pulled. DI bag onsite along 24th diagnol parking is parked up and will be removed by facility manager when possible. ESC permit conditions satisifed, permit finaled.
Site Final10/30/201910/30/201910/30/2019PNR
DetailsAndy J. Long
on site contact: Jeremy Smith ###-####

Need to pull 3 temporary DI bags (Fairview & 25th, Fairview and 24th, and on the 24th street diagnol parking area)

General Inspection9/17/20199/17/20199/17/2019PPASS
DetailsAndy J. Long
WIP on painting and interior finishing. Parking lot installed, storm water pond excavated. Some landscaping still in progress. Storm drains around site have sediment protection installed. No corrections requested.
General Inspection9/6/20199/6/20199/6/2019 CANC
DetailsMichael Zawacki
General Inspection7/22/20197/22/20197/25/2019 PASS
DetailsAndy J. Long
Complaint Inspection6/5/20196/5/20196/5/2019APASS
DetailsAndy J. Long
report of excavated soils smelling like hydrocarbons

Contractor worked with DEQ solid waste on 6/4 3:30 PM to resolve issue. Based on previous site testing, depth, and location under impervious road (24th), the soil is to be capped and paved over
General Inspection6/3/20196/3/20196/3/2019 PASS
DetailsMichael Zawacki
Roadwork on both 24th & 25th. Site is clean, work on curb islands. Eco pan washouts on site.
General Inspection4/17/20194/18/20194/19/2019APASS
DetailsMichael Zawacki
Site contained, roadwork along perimeter on fairview. Some trash and ci garette butts accumulates on road from neighboring business.
General Inspection3/15/20193/15/20193/19/2019 PASS
DetailsMichael Zawacki
No ESC issues. Most workers parking on street, entrance at each side. No loose trash, multiple dumpsters on site. Mortar mixer has secondar containment.
Tracking Control1/28/20191/28/20191/31/2019PPASS
DetailsAndy J. Long
Trackout cleaned up.
General Inspection1/21/20191/21/20191/23/2019 PASS
DetailsMichael Zawacki
No trackout. Site is contained, nothing leaving site.
General Inspection12/4/201812/4/201812/4/2018 PASS
DetailsMichael Zawacki
Road constructed through middle, only deliveries entering site, workers all parking on road. No ESC issues.
General Inspection10/19/201810/19/201810/19/2018 PASS
DetailsMichael Zawacki
Working on vertical. All work contained to fenced off block. Workers parking on street. No dust or trackout, no loose trash.
General Inspection9/3/20189/3/20189/4/2018 PASS
DetailsMichael Zawacki
WIP on vertical, using old climbing gym lot for storage. Some wind blown trash.
General Inspection7/17/20187/17/20187/17/2018PPASS
DetailsMichael Zawacki
WIP on framing. Only dirt work is sewer on south side of project. Site has a fine layer a silt that kicks up when driven on. Most workers parked on street, one truck and trailer came in while on site. Area is clean and trash free.
General Inspection6/12/20186/12/20186/12/2018PPASS
DetailsMichael Zawacki
Site contained, no trackout to 24th or 25th. Water wagon on site, area has been watered and is dust free, none observed blowing while at job. Multiple Eco pans on site. Site is free from trash.
General Inspection5/24/20185/24/20185/24/2018PPASS
DetailsMichael Zawacki
No dust at time of inspection, water wagon on site. Concrete is currently being poured, eco pan on site and driver was using it to wash out. Site is free from trash. No one was in job trailer at time of inspection, SWPPP was not in box, permit posted.
Complaint Inspection5/2/20185/3/20185/3/2018APEND
DetailsAndy J. Long
Dust occuring when using heavy equipment. No water truck observed operating at time of inspection but there is a water trailer onsite.


Notified project manager (Michael) to tell operators to drive slower than 5 mph. Use water trailer during high activity days, have water available to crust down haul routes.

New construction entrance was installed as requested during site prep.
General Inspection4/25/20184/25/20184/26/2018PPASS
DetailsAndy J. Long
WIP on foundation, initial grading complete. ESI construciton onsite(project super Tony). Walked site with project engineer.

SWPPP sign posted, binder stored in office trailer. ESI to conduct SWPPP inspections. Site is graded to retain stromwater and is surrounded by curbing and a vegetated strip. MS4 inlets on 24th, 25th, and Fairview

Discussed fugitive dust control and stockpile management, and noted that if inactive temporary stabilization is required.

Spill kit, dumpster, and ecopan concrete washout are on site and in use. Employee parking will be to the west of the site across 25th. Climbing gym to be demolished in late spring/summer.

Correction request:
- install new construction entrance on 24th.