Site Final | 1/4/2019 | 1/9/2019 | 1/9/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 12/28/2018 | 1/2/2019 | 1/4/2019 | P | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 12/28/2018 | 12/28/2018 | 12/28/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/12/2018 | 11/12/2018 | 11/13/2018 | | PASS |
Michael Zawacki
|
|
|
Work complete, parking lot and landscaping done. All materials from next door lot removed. OK to final when building permit closed.
|
General Inspection | 9/26/2018 | 9/26/2018 | 9/27/2018 | | PASS |
Michael Zawacki
|
|
|
Parking lot is paved and landscaping completed. All work is now in building, dumpster in parking lot. Most material removed from adjacent lot where job trailer is parked.
|
General Inspection | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Michael Zawacki
|
|
|
Building is up, curbing in place, parking area prepped for paving. Some landscaping in place. All material storage contained on site. Old washout can be cleaned.
|
General Inspection | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Michael Zawacki
|
|
|
Tilt up walls done. Site is clean, trusses and materials all stored on site. All trash is going into garbage trailer. Some spilled washout still in area of washout. Nothing is leaving site.
|
General Inspection | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | PASS |
Michael Zawacki
|
|
|
Slab was poured yesterday. Pump truck washed out in vicinity of washout area, foreman will get it cleaned up. Sweeper comes through and keeps parking lots clean. Track utilities is on site and has a saw cut area of pavement, they plan on patching when work completed.
|
General Inspection | 1/30/2018 | 2/20/2018 | 2/21/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on grading and excavation for foundation. No concrete work yet. Construction entrance installed, no trackout. Recieving storm drains have sediment inlet filters. Permit sign posted on job trailer.
Approved
|
Site Preparation | 1/30/2018 | 1/30/2018 | 1/30/2018 | P | PASS |
Andy J. Long
|
|
|
Jose ###-####
RP Jose Bautista on site for inspection. BMPs installed include:
5 storm drain inlets (3 in private parking lot) and two on Ancestor Place culdesac installed.
- construction entrance with geotextile lining and angular rock.
- construction limits have been fenced off with orange fence. Perimter vegetation outside of limits to be preserved.
- no surface waters or ditches adjacent or on site.
Approved for excavation.
|