Permit Information
Permit NumberESC18-00863
StatusFinaled
Name JOHN BROWN
Site Address 5512 W TARGEE ST
Project NameTargee Parcel A
Customer Number 
ePlanReviewNo
Description
Per Attached Conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled11/5/201911/5/201911/5/2019PPASS
DetailsAndy J. Long
Site Final10/23/201910/24/201910/29/2019ANR
DetailsAndy J. Long
need to remove DI bag
Aging Inspection10/23/201910/23/201910/23/2019 CANC
DetailsAndy J. Long
Site Final8/23/20198/28/20198/30/2019PNR
DetailsAndy J. Long
tell John Brown to have the DI bag removed on Targee @ Eagleson
Site Final8/13/20198/13/20198/13/2019PNR
DetailsMichael Zawacki
DI bags still not removed, already notified GC.
Site Final6/25/20196/25/20196/25/2019PNR
DetailsMichael Zawacki
DI bag on Targee @ Eagleson not removed. Message sent to GC
General Inspection1/29/20191/29/20191/29/2019PPASS
DetailsMichael Zawacki
Home completed, still needs landscaping.
Random Inspection9/7/20189/7/20189/7/2018PPASS
DetailsAndy J. Long
WIP on foundation. Permit posted, BMPs installed. No violations
General Inspection8/21/20188/23/20188/24/2018APASS
DetailsAndy J. Long
follow up inspection



Corrections complete:

- sidewalk and gutter were swept. Most loose dirt was removed.
- DI bag installed for sediment protection on the receiving storm drain.
BMP Violation8/17/20188/20/20188/21/2018AFAIL
DetailsAndy J. Long
No clean up performed.

Verbal correction to RP to:
-sweep gutter and sidewalk
- install sediment protection on storm drain just west of site at Stop sign.

RP John stated they will do it tomorrow. Follow up scheduled for Thursday PM.
BMP Violation8/15/20188/16/20188/17/2018ACANC
DetailsAndy J. Long
General Inspection8/13/20188/13/20188/13/2018PFAIL
DetailsAndy J. Long
Corrections needed:

- sweep up street, gutter and sidewalk in front of site
- clean up concrete slurry (dried) in the gutter
- install sediment protection on receiving storm drain just west of site