Permit Information
Permit NumberESC18-00866
StatusFinaled
Name JOHN BROWN
Site Address 5510 W TARGEE ST
Project NameTargee Parcel B
Customer Number 
ePlanReviewNo
Description
Per Attached Conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final11/12/201911/13/201911/13/2019PPASS
DetailsAndy J. Long
send email to Mark to verify permit is closed

Temporary BMP storm drain sediment bag on Targee has been removed as requested. ESC permit finaled. Okay for BLD final when requested.
Aging Inspection10/29/201910/29/201910/29/2019 FAIL
DetailsAndy J. Long
project complete and stabilzed. Did not removed the temporary DI bag. Request sent to GC and excavator.
Site Final8/29/20198/29/20198/30/2019PNR
DetailsAndy J. Long
Site Final8/13/20198/13/20198/13/2019PNR
DetailsMichael Zawacki
DI bags still not removed, already notified GC.
Site Final6/21/20196/25/20196/25/2019PNR
DetailsMichael Zawacki
DI bag on Targee @ Eagleson not removed. Message sent to GC
Aging Inspection6/21/20196/21/20196/21/2019 CANC
DetailsAndy J. Long
General Inspection1/29/20191/29/20191/29/2019PPASS
DetailsMichael Zawacki
Home completed, still needs landscaping.
General Inspection8/21/20188/23/20188/24/2018APASS
DetailsAndy J. Long
follow up inspection



Corrections complete:

- sidewalk and gutter were swept. Most loose dirt was removed.
- DI bag installed for sediment protection on the receiving storm drain.
BMP Violation8/17/20188/20/20188/21/2018AFAIL
DetailsAndy J. Long
No clean up performed.

Verbal correction to RP to:
-sweep gutter and sidewalk
- install sediment protection on storm drain just west of site at Stop sign.

RP John stated they will do it tomorrow. Follow up scheduled for Thursday PM.
BMP Violation8/15/20188/16/20188/17/2018ACANC
DetailsAndy J. Long
General Inspection8/13/20188/13/20188/13/2018PPASS
DetailsAndy J. Long
Corrections needed:

- sweep up street, gutter and sidewalk in front of site
- clean up concrete slurry (dried) in the gutter
- install sediment protection on receiving storm drain just west of site