General Inspection | 7/27/2020 | 7/27/2020 | 7/27/2020 | | PASS |
Michael Zawacki
|
|
|
Exterior building work completed. Landscapers on site. Contractor still parked and staged in parking lot. Area north of job no longer used for parking, materials, or offices.
|
General Inspection | 6/9/2020 | 6/9/2020 | 6/9/2020 | | PASS |
Michael Zawacki
|
|
|
Building exteriors completed and site paved. Still needs landscaping. Work on Susan still not completred, road is closed.
|
General Inspection | 4/24/2020 | 4/24/2020 | 4/24/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/9/2020 | 3/9/2020 | 3/9/2020 | | PASS |
Michael Zawacki
|
|
|
No trackout, pit run is starting to get compacted and mud may be an issue when wet weather returns. Two dumpsters on site, very little loose trash. All units fraed and current work is interiors.
|
Tracking Control | 1/21/2020 | 1/23/2020 | 1/23/2020 | A | FAIL |
Michael Zawacki
|
|
|
No improvements made. Will start formal NOV
|
General Inspection | 1/20/2020 | 1/20/2020 | 1/21/2020 | | FAIL |
Michael Zawacki
|
|
|
Trackout. Road has been built through south lot, workers are parking in mud. North lot is stable, talked to foreman about forcing people to park on north, plenty of room. Follow up scheduled.
|
General Inspection | 11/29/2019 | 12/3/2019 | 12/4/2019 | P | FAIL |
Andy J. Long
|
|
|
No construction entrance of stabilized parking area for employees. No significant trackout to Maple Grove, some on Irving.
Request issued to RP Bob with Wright Brothers to get entrance installed and clean up.
Follow up scheduled.
|
General Inspection | 11/28/2019 | 11/28/2019 | 11/29/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with WB foreman at site. Concrete slabs being put in, trucks using washout and also ordered washout low enough for pump trucks. Framing has begun on southernmost units. Seepage bed dug. Crew was on site cleaning trash. Plan to have area paved before winter.
|
General Inspection | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP on foundations. Ecopans at site, no dust or trackout, site contained.
|
General Inspection | 7/18/2019 | 7/30/2019 | 7/30/2019 | A | PASS |
Michael Zawacki
|
|
|
Site is clean and contained. Work begun on foundations. Eco pan and dumpster on site, no heavy equipment. No dust or trackout.
|
Site Preparation | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Michael Zawacki
|
|
|
Work began without site prep. Foreman was going off of temp occupancy card and not rough in, ESC is not listed as inspection and was overlooked. Water truck on site, no dust. Construction entrance made with round rock, contactors will sweep up trackout as needed. Site is below grade, no perimeter control needed for current phase. DIs around site have been protected. Gave them permit signs to put on site.
|