General Inspection | 8/3/2020 | 8/3/2020 | 8/3/2020 | | PASS |
Michael Zawacki
|
|
|
Landscapers working from sout tho nort. Sunroc on site repairing pavement. Peopl moving into south building, still interior work on northern building. BMPs still installed on maple grove.
|
General Inspection | 6/16/2020 | 6/16/2020 | 6/16/2020 | | PASS |
Michael Zawacki
|
|
|
Parking lot completed, all workers parked in lot. Road has been repaired and now open. Lot across street now closed, has been graded and berm and ditch added to prevent people from driving through. Landscaping scheduled to start next week. One more pad pour, ecopans still on site.
|
General Inspection | 5/1/2020 | 5/1/2020 | 5/5/2020 | | PASS |
Michael Zawacki
|
|
|
Crews finishing up concrete curb work on site, sidewalks have been completed. Scheduled to pave parking lot on tuesday the 12th. Susan drive is closed and is getting repaired. Irragation water is backing up into parking area on north side. Buildings framed and only interior work remains.
|
General Inspection | 3/16/2020 | 3/16/2020 | 3/16/2020 | | PASS |
Andy J. Long
|
|
|
BMPs installed - stabilzed staging area, concrete washout pans onstie. Fenced permeter and inlet protection on Maple Grove.
WIP. Not corrections requested at this time.
|
Tracking Control | 1/28/2020 | 1/28/2020 | 1/28/2020 | P | PASS |
Michael Zawacki
|
|
|
Rock has been brought in for entire area, no longer parked in mud. No tracking at time of inspection.
|
Tracking Control | 1/21/2020 | 1/23/2020 | 1/23/2020 | A | FAIL |
Michael Zawacki
|
|
|
No improvements made. Will start formal NOV
|
General Inspection | 1/20/2020 | 1/20/2020 | 1/21/2020 | | FAIL |
Michael Zawacki
|
|
|
Trackout. Road has been built through south lot, workers are parking in mud. North lot is stable, talked to foreman about forcing people to park on north, plenty of room. Follow up scheduled.
|
General Inspection | 11/29/2019 | 12/3/2019 | 12/4/2019 | P | FAIL |
Andy J. Long
|
|
|
No construction entrance of stabilized parking area for employees. No significant trackout to Maple Grove, some on Irving.
Request issued to RP Bob with Wright Brothers to get entrance installed and clean up.
Follow up scheduled.
|
General Inspection | 11/29/2019 | 11/29/2019 | 11/29/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with WB foreman at site. Concrete slabs being put in, trucks using washout and also ordered washout low enough for pump trucks. Framing has begun on southernmost units. Seepage bed dug. Crew was on site cleaning trash. Plan to have area paved before winter.
|
General Inspection | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP on foundations. Ecopans at site, no dust or trackout, site contained.
|
Site Preparation | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Michael Zawacki
|
|
|
Work began without site prep. Foreman was going off of temp occupancy card and not rough in, ESC is not listed as inspection and was overlooked. Water truck on site, no dust. Construction entrance made with round rock, contactors will sweep up trackout as needed. Site is below grade, no perimeter control needed for current phase. DIs around site have been protected. Gave them permit signs to put on site.
|