Site Final | 8/11/2020 | 8/11/2020 | 8/11/2020 | P | PASS |
Andy J. Long
|
|
|
Project now covered by ESC19-01429 (building) and ESC20-00786 (carports).
|
General Inspection | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PASS |
Michael Zawacki
|
|
|
Landscapers on site. Most work is interior, area clean.
|
General Inspection | 7/3/2020 | 7/3/2020 | 7/7/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/18/2020 | 5/18/2020 | 5/18/2020 | | PASS |
Michael Zawacki
|
|
|
WIP on framing. All material on parking lot, trash contained. Area around building starting to regrow.
|
General Inspection | 4/2/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 3/2/2020 | 3/2/2020 | 3/2/2020 | | PASS |
Michael Zawacki
|
|
|
Parking lot is paved and being used as staging and storage for building materials. All inlets have DI protection and are clean. Roll pan washout on paved storage area, is about full. Vertical construction has begun, site clean, no workers at site at time of inspection.
|
General Inspection | 1/14/2020 | 1/14/2020 | 1/14/2020 | | PASS |
Michael Zawacki
|
|
|
Concrete crew and pump truck at site, no mud delivered yet. Roll pan washout with plenty of capacity on site.
|
General Inspection | 11/25/2019 | 11/26/2019 | 11/26/2019 | P | PASS |
Andy J. Long
|
|
|
Parking lot asphalt and utility installation complete. NO foundation work yet.
Notified RP to install sediment protection on new installed storm drains.
|
General Inspection | 10/28/2019 | 10/28/2019 | 10/28/2019 | P | PART |
Michael Zawacki
|
|
|
One grader operating on site. Pit run for road bed is being worked with water, some trackout. Sweeper on site. Area needs to be paves, section of road has been sawcut between road and sidewalk. Will need to monitor tracking, once paved should no longer be issue.
|
BMP Violation | 9/24/2019 | 9/27/2019 | 9/27/2019 | A | PASS |
Michael Zawacki
|
|
|
Street swept and inlet protection installed. Dirt on road will be an issue until the areas cut out for water and sewer are patched.
|
General Inspection | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | FAIL |
Michael Zawacki
|
|
|
To entrances with no rocks. Lot of trackout, inlets in parking lot no longer protected. Person listed on everything no longere with contractor.
|
General Inspection | 8/5/2019 | 8/20/2019 | 8/19/2019 | P | PART |
Michael Zawacki
|
|
|
Rough grading has begun. Stockpile height is higher than fence. No water truck or dust control on site. Spoke with pipe crew and they are pulling off, done with their work. Sweeper at site.
|
Site Preparation | 8/2/2019 | 8/5/2019 | 8/5/2019 | A | PASS |
Andy J. Long
|
|
|
9:30 AM Jeremy
Work to begin Wednesday, starting with pipework first.
Permit sign posted. RP onsite.
- construction entrance to be installed this week. - request to leave vegetative strip between and parking lot on south side - protect private storm drain in parking lot - dust control required - request that stockpile heights be kept lover than fence lines
|