General Inspection | 8/6/2020 | 8/6/2020 | 8/7/2020 | | PASS |
Michael Zawacki
|
|
|
Site is being watered for dust control multiple times a week. No blowing dust at time of inspection. Southern area is further along, more units getting close to being finished and turned over. Plan to be paved before winter. No issues at time of inspection
|
General Inspection | 7/6/2020 | 7/6/2020 | 7/7/2020 | | PASS |
Michael Zawacki
|
|
|
WIP on multiple buildings. Teneants are expected to move into a few buildings end of the month. Site is clean, areas are being watered to keep dust down, sweeper comes twice a week.
|
General Inspection | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PASS |
Michael Zawacki
|
|
|
Southern section of lot is paved, crews working on sidewalk. Rumble strips are full of dirt, no longer forcing drivers over them. Site is still bare, has potential for dust or mud. Trash is clean, site is clean, no current major issues.
|
General Inspection | 5/4/2020 | 5/4/2020 | 5/5/2020 | | PASS |
Michael Zawacki
|
|
|
Site is dry, no blowing dust. No loose trash on site. Crew is doing curbing islands on south parking lot, washout used. Track pads need to be cleaned before it rains again, lots of dirt in employee parking area.
|
General Inspection | 4/3/2020 | 4/3/2020 | 4/6/2020 | | PASS |
Michael Zawacki
|
|
|
Work on Fairview exit completed, gate is closed. Waiting for site to dry, won't pass compaction for road beds. Pump truck on site doing pours for balconies. Concrete trucks using washout. Crew was cleaning track pads, lots of tracking from genie lift.
|
General Inspection | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PASS |
Andy J. Long
|
|
|
Minor trackout to Cloverdale, receiving storm drain has sediment bag installed. Regular sweeper scheduled for Tuesday and Thursday.
Requested that some muddy holes/spots in the parking area have pit run placed on top, which was completed during inspection.
Concrete washout pans onsite, trash contained. Site interior is extremely muddy, but the trackout offsite has been managed. Site has restrictions on access to muddy area and has desigated vehicles that do not exit the muddy areas.
|
Tracking Control | 9/20/2019 | 9/23/2019 | 9/23/2019 | A | PASS |
Andy J. Long
|
|
|
Trackout to Cloverdale has been cleaned up. Receiving storm drains north of site have sediment protection installed.
Controls include rumble bar plates and long preserved asphalt access.
Recommend installation of rock entrance/exit from dirt to paved area. Install extra row of rumble bars to get more wheel rotations.
|
General Inspection | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Michael Zawacki
|
|
|
Old paved parking lot for school has been left in place, some material staged on lot. Most of exposed area has good crust, water truck on site, multiple drivers available. Work area has been watered, some dust from wheels. Large stockpiles on site. Additional work will be needed at sewer easment for installaion, school had a septic and drain field. Foreman will watch for dust and water as needed.
|
General Inspection | 7/23/2019 | 8/6/2019 | 8/5/2019 | A | PASS |
Andy J. Long
|
|
|
Grading and infrastructure in progress. No trackout. Permit posted.
Fugitive dust control water truck doing a good job keeping dust down.
|
Site Preparation | 7/18/2019 | 7/22/2019 | 7/22/2019 | A | PASS |
Andy J. Long
|
|
|
Scott ###-####
Site BMPs are installed, stormwater team (Scott, Tyler, John w/ ESI) onsite for inspections, SWPPP plan available. ESI to do SWPPP inspections and mantain binder.
- Site access and ESC permit sign posting is on Cloverdale. No access along Fairview at this time. Screened fence installed, Fairview along the south is above grade of the site. - Construction entrance on Cloverdale is the preserved asphalt from previous development. Area will also be used for employee parking and staging. This surface must be kept clean to prevent any turbid runoff to Cloverdale MS4. Sheet flow from this area flows north to low lying grassy-vegetated area. A watlle has been installed as a sediment control to treat runoff to this area.
- Clearing limits have been estabished. Entire perimeter except along Fairview has sediment control wattle installed properly.
- Leakproof concrete washout facility with sign must be provided prior to placement of any concrete.
- Rough grading and site grubbing is in progress, water truck in use to control dust and refill hydrant is onsite. No dust isssues observed.
- Large stockpiles inactive for 7 days must have stabilization measure implemented to prevent wind blown dust and sediment runoff. Current stockpile in NW corner is active. To prevent wind blown dust, top should be leveled and water truck should spray to form crust on top.
Approved for construction.
|
Site Preparation | 7/18/2019 | 7/19/2019 | 7/18/2019 | A | CANC |
Andy J. Long
|
|
|
rescheduled
|