Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberFIR18-00414
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 367 N ANCESTOR PL
Project NameEpisciences Manufacturing
Customer Number 
ePlanReviewYes
Description
[Episciences Manufacturing Facility]
The fire sprinkler scope of work consists of 18,446 ft² make-up manufacturing facility. A new wet grid system with 6”x4”x1½” pipe sizing. There are racks located within the 118 Warehouse Area and the 110 Storage area. ESFR sprinklers are being utilized. There are some small shelves with less than 8’ storage height. There is plastic storage at 19’ high.
There are flammable and combustible liquids; they are below MAQ. The flammable liquids will be in metal storage cabinets. The system is designed as a 6”x4”x2½”, 1½” Grid. The second floor is designed as a 4”x4”x 1½” grid. The 8” underground supplies a 8” backflow preventer and 8” header. There are floor control valves 8” and 4”.

• The underground piping is under permit FIR18-00130.

Location on Plan - Warehouse 118, Storage 110
Commodity - Makeup Ingredients
Classification - Group A Plastics and Class IV
Storage Type (rack, solid pile, etc.) - Rack
Pallet Type (wood or plastic) - Wood
Aisle Width - 8’
Height of Storage - 20’
Ceiling Height - 23’
Encapsulated - No
Solid Shelves - No
Smoke and Heat Vents - No
Draft Curtain - No
In Rack Sprinklers - No
Sprinkler Type - ESFR K=25.2
High Temperature Sprinklers Required - No
Applicable NFPA Section - T 17.2.3.1
Hydraulic Design Criterion - 15 Psi
Hose Stream Requirements - 250

[BLD17-03648]
This building is fire sprinklered for area increase and story increase. Permit for the construction of a new 18,446 sq. ft., 2-story concrete tilt-up building for a makeup manufacturing and office facility and associated site work. Scope of work includes: construction of slab on grade concrete foundation, concrete tilt up construction, second floor, interior non-bearing walls, restrooms, electrical, mechanical, plumbing, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. All work shall comply with the approved plans, DRH16-00360 and all applicable codes. Note: Special Inspections Required, see form 310. Note: complies with ANSI/ASHREA 90.1. **JAR

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/14/201811/15/201811/15/2018APASS
DetailsTroy Cobbley
permit finaled


Jordan Fuger Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection11/13/201811/14/201811/14/2018AFAIL
DetailsTroy Cobbley
Could not test the flow switch for the large system due to missing inspectors test orfice. All other devices worked and reported correctly.

Contact is Morgan. Phone #: ###-#### Inspection requested via web by Morgan Ahten

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection11/9/201811/13/201811/13/2018PCANC
DetailsTroy Cobbley
The fire alarm inspection failed. No sprinkler permit items tested.

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection11/6/201811/7/201811/7/2018PCANC
DetailsTroy Cobbley
Could not perform testing due to fire alarm communication issues. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection10/22/201810/23/201810/23/2018AFAIL
DetailsTroy Cobbley
The interconnections with the fire alarm system could not be tested, could not verify pressure relief vavles and the overhead doors have not been modified to remain less than 4' obstruction

Jordan Fuger is the contact for this final inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection10/16/201810/18/201810/18/2018PCANC
DetailsTroy Cobbley
Not ready for final

Jordan Fuger is the contact for this final inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in10/17/201810/18/201810/18/2018APASS
DetailsTroy Cobbley
Forward flush test passed, Second floor rough-in passed and piping can be re-covered. Need ball drip piped, need pressure relief vavles piped, need interconnection with the fire alarm system tested, need soffits for the ESFR heads finished installed, need the overhead door stops installed as discussed.

Jordan Fuger is the contact for this rough to cover inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in10/16/201810/17/201810/17/2018APART
DetailsTroy Cobbley
Main floor is complete except for the soffits at the ESFR heads. The second floor ceiling tile needs to be removed for a rough-in inspection.


Jordan Fuger is the contact for this RTC inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro10/1/201810/2/201810/3/2018PPASS
DetailsTroy Cobbley
The overhead hydro tests passed.
INSP-Sprinkler Rough-in9/26/20189/27/20189/27/2018APART
DetailsTroy Cobbley
See the city approved plans for locations marked "ok" in red where piping is ok to cover except where earth quake bracing is. All other areas can not be covered. The earth quake bracing material used is not what has been submitted/calculated and in some locations has not been installed in the spot as shown on plans. New calculations are required to be approved including new bracing locations. There are several overhead doors that exceed 4' when in the open position that will require sprinkler coverage beneath them. There are atleast two raisede metal work platforms that may require sprinkler coverage beneath. Earth quake bracing is missing from the 2 1/2" branchlines. Also one area the heads are overspaced.

I stopped the inspection after the above items had been noted so this list is not all inclusive of possible correction items.


Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro9/26/20189/27/20189/27/2018AFAIL
DetailsTroy Cobbley
Overhead hydro test on both systems failed due to a visible loss on both guages


Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in9/19/20189/20/20189/21/2018APART
DetailsTim Frost
Phone #: ###-#### >> Inspection requested via web by Stan Beus

______________
Barely got started before I ran out of time. There is problems with conduits in the storage area. ESFR can not have obstruction. Went over the problem with the fitter and GC. Sway branch line restraints were missing in the office area I checked.
INSP-Sprinkler Rough-in8/22/20188/23/20188/23/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above the hardlids in the restrooms on levels 1 and 2 complete, approved for cover.

Jeff Chaney is the contact for this inspection. He needs a RTC in the Office area and bathrooms. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus