INSP-Final Inspection | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
Gerardo Arce is the contact. This inspection has already been done, reach out to the contact for more information. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/26/2019 | 3/26/2019 | 3/26/2019 | P | DONE |
Jim Page
|
|
|
Hydrstatic test for underground supply witnessed, no pressure loss observed.
Gerardo Arce is the contact. This inspection is for a Hydro only. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | DONE |
Mark Scharfen
|
|
|
Flush witnessed by Troy C. and Mark Scharfen on 3/20/2019 and passed.
Gerardo Arce is the contact for this underground flush on BLD D. We have talked to Stacey with Suez Water. He can help us in the PM with the flush. Please give Gerardo a little notice so he can let Stacey know what time to show up to help. Thank you for your help. Have a nice day. Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 2/1/2019 | 2/4/2019 | 2/4/2019 | P | FAIL |
Jim Page
|
|
|
Could not complete flush, underground valves were not accessable at time that flush could be completed due to dirt cover/bent valve box.
Underground hydro/flush Gabriel Garduno is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 1/24/2019 | 1/29/2019 | 1/29/2019 | A | FAIL |
Jim Page
|
|
|
Point of contact could not be reached.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 | P | CANC |
Troy Cobbley
|
|
|
Problem with hydro pump.
|
INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 | P | FAIL |
Troy Cobbley
|
|
|
Underground supply was not at the minimum starting pressure for a hydro test.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for undergorund supply, stub up and approximately 12 feet of pipie approved for cover, remaining underground to be inspected at a later date.
Underground rough to cover Phone #: ###-#### Inspection requested via web by Stan Beus
|