Information based on query as of Tuesday, May 14, 2024.
Permit Information
Permit NumberFIR18-00670
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 1330 E EXCHANGE ST
Project NameDMS Steel Sprinkler System
Customer Number 
ePlanReviewYes
Description
[Donahue McNamara Steel]
The fire sprinkler scope of work consists of a new show with office. There is a mezzanine used for mechanical equipment. The 6” underground piping supplies a 4” backflow preventer. The above system is designed as a 2½”x2½”x1¼” grid. The office area is designed as a side feed system with 4” main and 2 ½” branch lines.

[BLD18-00999]
Permit to construct a new 5,711 sq. ft. one story, pre-engineered metal office/warehouse building and related site improvements. Scope of work includes: construction of footing foundation, slab on grade concrete floor, electrical work and site work. This building will be fully Fire Sprinklered and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. Note: Special Inspections Required see form 310. **JG**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/18/20194/19/20194/19/2019PPASS
DetailsJim Page
Final fire sprinkler inspection complete, device testing/pass for fire alarm associated items completed on the 15APR2019 inspection.

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in/Hydro4/18/20194/19/20194/19/2019ADONE
DetailsJim Page
No pressure loss observed for overhead hydro.

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Final Inspection4/12/20194/15/20194/15/2019PCANC
DetailsTroy Cobbley
Not ready for final. See morning comments. A re-inspection fee has been added due to the overhead hydro test failing twice before.

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in/Hydro4/12/20194/15/20194/15/2019AFAIL
DetailsTroy Cobbley
Overhead hydro test failed due to visible loss at the guage, need as-builts per earlier correction note for flex heads and additional earthquake bracing. All device interconnect with the new fire alarm panel passed.

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in4/12/20194/15/20194/12/2019ACANC
DetailsJim Page
Phone #: ###-#### >> Inspection requested via web by Jessia Maxwell Inspection cancelled from web by: Jessia Maxwell
INSP-Final Inspection4/10/20194/12/20194/12/2019PFAIL
DetailsTroy Cobbley
Overhead hydro test failed due to visible loss on the guage.Separate inspection needs to be scheduled for a hydro test or rough-in.


Please call Chris ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in/Hydro4/12/20194/15/20194/12/2019PCANC
DetailsJim Page
Please call Chris Ford Phone #: ###-#### >> Inspection requested via web by Jessia Maxwell Inspection cancelled from web by: Jessia Maxwell
INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018APART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping approved for cover. Branch lines under mezzanine are 2 1/2 inch diameter pipe, top of piping is more than 6 inches down from point of attachment at the hangers, need to add sway bracing to branchlines under mezzanine. Will need to provide as-builts showing the addition of the sway bracing and addition of flex heads..

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in11/13/201811/14/201811/14/2018AFAIL
DetailsTroy Cobbley
Inspection was for the side sammys so that the cover could be repaired. The first side sammy I checked the retaining nut was bearly on.

Please call Chris Ford for above ground rough in Phone #: ###-#### Inspection requested via web by Jessia Maxwell