Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberFIR18-00789
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 2574 S BEVERLY ST
Project NameWest Airport shell Bldg A
Customer Number 
ePlanReviewYes
Description
[West Airport Shell Building A]
The fire sprinkler scope of work consists of a new one level shell bldg. 8”x250'± C-900 underground. A new 1250gpm @ 80psi fire pump and ESFR 16.8K @ 35psi wet system

• There is NO occupancy allowed under this permit. Shell and Corel ONLY.

Location on Plan - Warehouse
Commodity - Unknown – Shell and Core ONLY
Classification - Group A
Storage Type (rack, solid pile, etc.) - Rack
Pallet Type (wood or plastic) - Wood
Aisle Width - 8’
Height of Storage - 23’-3”
Ceiling Height - 26’-3”
Encapsulated - No
Solid Shelves - No
Smoke and Heat Vents - No
Draft Curtain - No
In Rack Sprinklers - No
Sprinkler Type - ESFR, K=16.8
High Temperature Sprinklers Required - No
Applicable NFPA Section - T-17.2.3.1
Hydraulic Design Criterion - 4 sprinklers on 3 line with 35 Psi
Hose Stream Requirements - 250 Gpm

[BLD18-02799]
The fire sprinkler system is used for building area increase and for fire area. To construct a new 28,416 square foot warehouse shell building (380’ x 75’ exterior dimensions). Work is to include concrete footings, concrete tilt-up wall panels, concrete floor sabs on grade, steel columns with steel baseplates and anchors, steel roof girder trusses, steel roof trusses, metal roof deck, insulation on top of the roof deck, single-ply TPO roof membrane, domed plastic skylights, wall insulation, exterior overhead doors, exterior storefront windows, exterior doors, exterior steel stairways with steel landings, two trash enclosures with steel gates, steel awnings with steel support tie-back rods, a keystone block retaining wall at the sloped grade, a 40 foot wide concrete apron at the loading dock area, and a 1-hr fire sprinkler riser room with an exterior door. Special inspection is required for soils, concrete, steel (including welding and bolting), and anchors post-installed in hardened concrete. Future roof top HVAC units weighing 750 pounds each were anticipated. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. This permit is not intended to establish a Certificate of Occupancy for any portion of this building. Separate permits are required to establish occupancy. A service sink and perhaps drinking fountains and two toilet rooms for each tenant space will be required. **JAR**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/10/20199/11/20199/11/2019APASS
DetailsTroy Cobbley
Permit finaled. Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Final Inspection9/6/20199/10/20199/10/2019PFAIL
DetailsTroy Cobbley
Project is not ready for final yet. Todays inspection was to witness the fire pump certification. Final on shell and pump run with capital pump Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Final Inspection9/6/20199/6/20199/6/2019PCANC
DetailsTroy Cobbley
Final on shell and pump run with capital pump. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in/Hydro7/25/20197/26/20197/26/2019APASS
DetailsTroy Cobbley
Overhead piping rough in and overhead piping hydro passed. Fire pump assembly has not been inspected or hydro tested.

Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Sprinkler Rough-in/Hydro5/24/20195/24/20195/24/2019PPASS
DetailsTroy Cobbley
Underground hydro test witnessed Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Sprinkler Rough-in5/21/20195/21/20195/21/2019PCANC
DetailsTroy Cobbley
2 nd floor apartments and 4th floor corridor. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Supply line flush5/13/20195/13/20195/13/2019PPASS
DetailsTroy Cobbley
Underground flush witnessed. Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Sprinkler Rough-in1/11/20191/14/20191/14/2019APASS
DetailsTroy Cobbley
Underground supply piping approved for cover.

Underground cover Phone #: ###-#### Inspection requested via web by Sam Ball