Information based on query as of Thursday, May 16, 2024.
Permit Information
Permit NumberFIR19-00327
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 8743 W SHELLIE LN
Project NameSHELLIE RESIDENCE
Customer Number 
ePlanReviewYes
Description
SHILO SHALL INSTALL A FULL 13D SYSTEM IN THIS ONE STORY RESIDENTIAL HOUSE. 2" UG IS INSTALLED BY OTHERS WITH A 1" WATER METER. A PLUMBER SHALL INSTALL A 1ΒΌ" BACKFLOW PREVENTER. SHILO SHALL ATTACH TO THE BACKFLOW AND RUN PIPE AND HEADS TO PROTECT EACH OF THE NECESSARY ROOMS IN THE RESIDENCE. SHILO SHALL INSTALL 1 TY313 SSU IN THE RISER ROOM AND 18 SENJU 4.9K RESIDENTIAL CONCEALED HEADS THROUGHOUT.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/13/20198/14/20198/14/2019APASS
DetailsTroy Cobbley
permit finaled

Colton-wants at 10 Phone #: ###-####
INSP-Sprinkler Rough-in6/26/20196/27/20196/27/2019APASS
DetailsJim Page
Tenting has been corrected, all tenting in place at time of inspection. Overhead fire sprinkler piping/tenting approved for cover.

Colton Cox is the contact. This rough-in is for the tinting inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/25/20196/26/20196/26/2019AFAIL
DetailsJim Page
Tenting is not installed correctly in numerous areas.

Colton Cox is the contact. He would like this inspection to be for the tenting. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/24/20196/25/20196/25/2019AFAIL
DetailsJim Page
No tenting installed and no one working on tenting at time of inspection, cover is not approved.

Colton Cox is the contact for this inspection. The RTC and Hydro inspections were already passed. We are just needing inspection and approval for tinting insulation. Thank you for your help. Have a good day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/24/20196/24/20196/24/2019PDONE
DetailsJim Page
Hydrostatic test witnessed at city pressure (No FDC connection, static city pressure is required for a minimum), no pressure loss observed.
INSP-Sprinkler Rough-in6/24/20196/24/20196/24/2019PPART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping complete. Tenting was installed on the sprinkler heads only, all other piping still exposed to attice space. Remaining tenting will need to be installed, cover is no approved until all tenting is installed, inspected and passed.

Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/24/20196/25/20196/24/2019ACANC
DetailsTroy Cobbley
Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in6/17/20196/18/20196/18/2019AFAIL
DetailsTroy Cobbley
Plan needs to be mirror imaged, pipe routing and number of heads installed needs to match plans, will need to be tented prior to a cover inspection approval.

Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus