INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Colton-wants at 10 Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | PASS |
Jim Page
|
|
|
Tenting has been corrected, all tenting in place at time of inspection. Overhead fire sprinkler piping/tenting approved for cover.
Colton Cox is the contact. This rough-in is for the tinting inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | FAIL |
Jim Page
|
|
|
Tenting is not installed correctly in numerous areas.
Colton Cox is the contact. He would like this inspection to be for the tenting. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | FAIL |
Jim Page
|
|
|
No tenting installed and no one working on tenting at time of inspection, cover is not approved.
Colton Cox is the contact for this inspection. The RTC and Hydro inspections were already passed. We are just needing inspection and approval for tinting insulation. Thank you for your help. Have a good day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed at city pressure (No FDC connection, static city pressure is required for a minimum), no pressure loss observed.
|
INSP-Sprinkler Rough-in | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete. Tenting was installed on the sprinkler heads only, all other piping still exposed to attice space. Remaining tenting will need to be installed, cover is no approved until all tenting is installed, inspected and passed.
Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/24/2019 | 6/25/2019 | 6/24/2019 | A | CANC |
Troy Cobbley
|
|
|
Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | FAIL |
Troy Cobbley
|
|
|
Plan needs to be mirror imaged, pipe routing and number of heads installed needs to match plans, will need to be tented prior to a cover inspection approval.
Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|