INSP-Final Inspection | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Troy Cobbley
|
|
|
**PASS** Hydro papers and paperwork showing factory painted escutcheons uploaded to tidemark*MAS** Gabe is the contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
DOC - Permit Finaled | | | 12/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
INSP-Final Inspection | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | CANC |
Jim Page
|
|
|
Point of contact not available when inspection could be completed, inspection request will need to be rescheduled, this request is cancelled.
Gabe is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro witnessed with no pressure loss.
Gabe Garduno is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Jim Page
|
|
|
Plan mods have been accepted, all tenting is in place, cover is approved for overhead fire sprinkler piping.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | PART |
Jim Page
|
|
|
Previously noted items have been corrected, rough in inspection for overhead fire sprinkler piping is complete, plan mod still needs to be submitted as of this entry, cover is not approved until plan mod has been reviewed and accepted.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | FAIL |
Jim Page
|
|
|
** Failed. Plan Mod needed for piping changes. Head at entryway needs moved for proper coverage. Piping on 2nd floor in unheated concealed space needs rerouted out of concealed space to allow for proper freeze protection. GC to build wall in storage area under stair so head is no more than 10' away. Discussed insulation options, and requirements with GC.*MAS**
Gabe Garduno is the contact for this consultation. Thank you for your help. Have a great day. Phone #: ###-#### >> Inspection requested via web by Stan Beus
|