Final | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | PASS |
Jack Reynolds
|
|
|
Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - final ok area B - occ card signed
|
Final | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | FAIL |
Jack Reynolds
|
|
|
Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - need dryer tags installed on 104, 207 and 304
|
Final | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | FAIL |
Chad Schwendiman
|
|
|
Air balance will be sent to you hopefully before the inspection. Antonio will be the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - Boilers need to terminate per the manufacures listing, Need dryer vent lenght tags in units 104, 207 and 304
|
Final | 1/29/2020 | 1/30/2020 | 1/30/2020 | A | FAIL |
Chad Schwendiman
|
|
|
Temp Occupancy of Area B. Please inspect mid-morning as we are waiting for as air balance report gets typed up. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - Approved TCO plan does not include a TCO for area B, only area A. Need accurate dryer vent lenght tags installed in all units. Clearance around boiler flue's from sheeting okay.
|
Final | 1/16/2020 | 1/17/2020 | 1/17/2020 | A | PART |
Jack Reynolds
|
|
|
Can you come around 11am? Temp occupancy Area A and Garage level. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist Temp final ok on area A units 103,104,105,106, lobby 203, 204, 205, 302 and parking garage
|
Final | 1/15/2020 | 1/15/2020 | 1/15/2020 | P | NR |
Jack Reynolds
|
|
|
Temp occupancy of Area A and parking garage. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - outside terminations need finished - 1st floor grilles in common area need finished - wine cellar 2nd floor needs finshed and running - need documents from 3rd party on parking garage sensors and exhaust system showing system has been tested
|
Conference | 1/13/2020 | 1/13/2020 | 1/13/2020 | A | DONE |
Jack Reynolds
|
|
|
Walk through of area A and parking garage. - Parking garage needs smoke dampers installed on east side per approved City prints. Talked with contractor and general about topic. Parking garage needs to be completed fully for TCO - need to seal around penetrations on supply fan and exhaust fan - condensate for elevator equipment room needs installed by others
|
Conference | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | DONE |
Jack Reynolds
|
|
|
Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - talked with Antonio about finals on area A - wine cellar on 2nd floor needs finished still
|
Rough-in | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Jack Reynolds
|
|
|
2nd floor corridor. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - 2nd floor corridor R/I ok
|
Rough-in | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PASS |
Ben Livingston
|
|
|
1st floor corridor. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - 1st floor corridor duct seal, breezway duct insulation -
|
Rough-in | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | FAIL |
Jack Reynolds
|
|
|
2nd floor corridor. Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - missing F/S damper on 8" duct 2nd floor
|
Rough-in | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Jack Reynolds
|
|
|
3rd floor corridor. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - 3rd floor fire/smoke damper clearances ok for angles - duct seal R/I ok
|
Rough-in | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | CANC |
Jack Reynolds
|
|
|
3rd floor corridor. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - need fire damper installation instructions for rec and round fire dampers on 3rd floor for inspections
|
Rough-in | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | PASS |
Jack Reynolds
|
|
|
Condo 101, Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 101 R/I duct seal ok - breeze way supply and return ducting R/I duct seal ok for insulation
|
Rough-in | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | PASS |
Jack Reynolds
|
|
|
Soffit rough in condo 102. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist -unit 102 R/I duct seal ok
|
Rough-in | 10/14/2019 | 10/14/2019 | 10/14/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit inspection in condo 107 and fire damper openings. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 107 duct seal R/I ok - F/S dampers not ready for clearance inspection - boiler flues need 6" enclosed clearances to combustibles
|
Rough-in | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit rough in condo 207. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 207 duct seal R/I ok
|
Rough-in | 9/30/2019 | 10/1/2019 | 10/1/2019 | A | PASS |
Jack Reynolds
|
|
|
Condo 201 rough in. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 201 duct seal R/I ok
|
Rough-in | 9/26/2019 | 9/26/2019 | 9/26/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit rough in condo 208. Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - unit 208 R/I duct seal ok
|
Rough-in | 9/20/2019 | 9/20/2019 | 9/20/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit rough in on condos 202 and 206, Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 202 R/I duct seal ok/ dryer is well over 60' in length with fittings and straight pipe -unit 206 R/I duct seal ok
|
Rough-in | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Jack Reynolds
|
|
|
Soffit inspection in 304. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 304 R/I ok duct seal soffit cover ok
|
Rough-in | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Ben Livingston
|
|
|
Soffits inspection in 303, Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - 303 soffits, 205 condensate conection wine room cooler okay -
|
Rough-in | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffits in condo 301, Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - unit 301 R/I and duct seal ok
|
Rough-in | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit rough in for condos 103 ; 106. Contact Antonio ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - 103,106 R/I duct seal ok
|
Rough-in | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Jack Reynolds
|
|
|
Rough in for Condo''s 104 ; 105. Contact Antonio ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - unit 104, 105 R/I duct seal ok
|
Rough-in | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit inspection in condo 203. Tyson is the contact Phone #: ###-#### Inspection requested via web by stan lillquist -R/I duct seal 203 ok
|
Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Jack Reynolds
|
|
|
Soffit rough in on condo 204 ; 205, exclude wine room rough in 205. Tyson is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - 204 and 205 duct seal ok - wine room in 205 will be at a later date
|
Rough-in | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | FAIL |
Jack Reynolds
|
|
|
Soffit cover in condos 204 and 205, Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - duct seal is not finished - line set insulation for wine cellar needs insulation fixed - condensate line for wine cellar need to be min 3/4 and approved materials. use pump to achieve grade then gravity drain to approved location
|
Rough-in | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PART |
Jack Reynolds
|
|
|
South end dryer vent, Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - dryers units on south side 101,102,107 ok 201 needs two seams in the wall sealed 202,206,207 and 5th unit on the 2nd floor that wasn't labeled ok 301,303,304 ok
|
Rough-in | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Ben Livingston
|
|
|
Soffit rough in on condo 302. Antonio is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist 302 soffit duct okay
|
Rough-in | 6/7/2019 | 6/10/2019 | 6/10/2019 | A | PASS |
Jack Reynolds
|
|
|
3rd floor north dryer vents. Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - 1st and 2nd floor north side dryer vents ok
|
Rough-in | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Jack Reynolds
|
|
|
inspect dryer vent in condo 302, Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - unit 302 dryer vent of 8' ok - talked with Antonio about the rest of the dryer vents being longer than 35'. Prints show labels being installed near dryer stating dryers being capable of exhausting at least 60'.
|