Permit Information
Permit NumberBLD19-01927
StatusFinaled
Name OKLAND CONSTRUCTION CO INC
Site Address 1290 W MYRTLE ST
Project NameUsao/Gsa
Customer Number 
ePlanReviewYes
Description
(USAO/GSA) Permit for a first time tenant on the 4th and fifth stories of the existing pioneer crossing building with work to include the build out of 1,647 sq, ft on the fourth story including a 1,313 sq. ft. conference room, a 97 sq. ft. storage room and 237 sq. ft. break room. Improvements on the 5th story include office, conference, break, storage and lobby areas. This building is fully fire sprinklerd with a one story type 1A podium and a 4 story type IIB building above the podium. The assembly use on the 3rd story of the upper building has not been required to be separated from the 5th story as it is considered accessory the story and is regulated as a B occupancy. This Building is fully fire sprinklered for height and area Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 7/14/20208/11/2020 DONE
MAILED 8-14-2020
Third Notice 5/12/20207/9/2020 DONE
mailed 7-9-2020
Second Notice 4/13/20205/7/2020 DONE
mailed 5-8-2020
First Notice 3/26/20204/3/2020 DONE
mailed 4-6-2020
Permanent Occupancy  3/16/2020 DONE
BLD-Final3/11/20203/12/20203/12/2020APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Sam Reading
FIRE-Final Inspection3/11/20203/12/20203/12/2020APASS
DetailsJim Page
Previously noted item has been corrected, final life fire safety inspection is complete.

Phone #: ###-#### Inspection requested via web by Sam Reading
FIRE-Final Inspection3/10/20203/11/20203/11/2020AFAIL
DetailsJim Page
Could not test release function on north stairwell door due to wiring issue, will need to retest release after repair is made.

Test remote unlock switch for L5 stairwell doors. Phone #: ###-#### Inspection requested via web by Sam Reading
FIRE-Final Inspection3/2/20203/3/20203/3/2020ACANC
DetailsJim Page
Code exceptions done. Need final ok for c of o Phone #: ###-#### >> Inspection requested via web by Sam Reading Inspection cancelled from web by: Sam Reading
BLD-Final3/2/20203/3/20203/3/2020ACANC
DetailsDave Hannah
Code exceptions done. Need final ok for c of o Phone #: ###-#### >> Inspection requested via web by Sam Reading Inspection cancelled from web by: Sam Reading
Plan Reviewer's activity  3/2/2020 DONE
DetailsJason Blais
Alternate on stairways doors locking hardware per 2018 code provisions approved by building official and fire marshal uploaded into ePlanReview case.
Plan Reviewer's activity  2/28/2020 DONE
DetailsJason Blais
Alternate on door hardware for two rooms approved by building official and fire marshal uploaded into ePlanReview case.
BLD-Final2/14/20202/18/20202/18/2020APART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Sam Reading ok for tco ok for co after fire gos perm
FIRE-Final Inspection2/14/20202/18/20202/18/2020APART
DetailsJim Page
Partial final inspection for life fire safety is complete for area of work. Fire sprinkler inspection is complete, fire alarm inspection is complete and NFPA72 compliant, waiting on as-builts to be submitted/approved for candella change in corner offices, fire alarm permit can be finaled after fire alarm permit is back in issued status. A formal letter of approveal to the building code official is required from the architect requesting the 2018 chapter 10 IFC exception for stairwell doors to be allowed locked and release on fire alarm activation as well as the combination tumbler look setup on the file room door and secure storage directly south of the file room. Combination looks do not meet IFC requirements for single action operation and will require approval from the building code official. 30 day TCO authorized by Joe Bruce, Fire Section Supervisor.

Phone #: ###-#### Inspection requested via web by Sam Reading
FIRE-Final Inspection2/13/20202/14/20202/14/2020PFAIL
DetailsTroy Cobbley
Provide all of the small documents, provide letter from the architect for compliance with the 2018 IFC 1010.1.9.11 exception #3, repair the exit sign in the 4th floor conference room.

Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Final2/13/20202/14/20202/14/2020PCANC
DetailsBrandon Shaw
Phone #: ###-#### >> Inspection requested via web by Sam Reading Inspection cancelled from web by: Sam Reading
FIRE-Conference2/7/20202/7/20202/7/2020ADONE
DetailsJim Page
Fire conference complete, discussed items for life fire safety inspection. All door hardware to include delayed egress needs to in place and functional. Stairwell card readers needs to comply with 2015 IFC section 1010.1.9.11 per conversation with Joe Bruce, Fire Section Supervisor.
FIRE-Final Inspection2/4/20202/7/20202/7/2020ACANC
DetailsJim Page
Was suppose to be scheduled as conference instead of final, this request is cancelled.

Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Final2/7/20202/7/20202/7/2020PCANC
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Sam Reading Inspection cancelled from web by: Sam Reading
BLD-Final2/4/20202/7/20202/7/2020ACANC
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Sam Reading Inspection cancelled from web by: Sam Reading
BLD-Ceiling Grid Inspection1/31/20201/31/20201/31/2020PPASS
DetailsDave Hannah
Cover inspection for 4th floor Conference and break room. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Ceiling Grid Inspection1/15/20201/16/20201/16/2020APASS
DetailsDave Hannah
Cover inspection for level 5, West and Northwest corridors and offices. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Ceiling Grid Inspection1/13/20201/13/20201/13/2020PPASS
DetailsDave Hannah
inspection for cover Level 5 from Gridline-C south Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Ceiling Grid Inspection1/7/20201/7/20201/8/2020PPART
DetailsDave Hannah
Grid inspection east of elevators. excepting corridors, admin storage room, and mail room. Phone #: ###-#### Inspection requested via web by Sam Reading offices and hallway east side ok
FIRE-Conference12/24/201912/30/201912/30/2019ADONE
DetailsJim Page
Fire conference complete.

Emergency light fixture layout, workstation furniture, additional signage requirements Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Wall cover12/5/201912/5/201912/11/2019PPASS
DetailsDave Hannah
L4 shaft wall. Fire-rated enclosure under stairs Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Wall cover11/18/201911/18/201911/21/2019PPASS
DetailsDave Hannah
Fire rating at 4th floor demising wall. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Framing/Rough-in11/19/201911/20/201911/20/2019APART
DetailsDave Hannah
Ceiling cover for hardlids on level 5 Phone #: ###-#### Inspection requested via web by Sam Reading hard lids ok to cover
BLD-Wall cover10/30/201910/30/201910/30/2019PPASS
DetailsDave Hannah
Fire Treated Plywood inspection for south stair interior wall and Secure store room West. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Wall cover10/11/201910/14/201910/14/2019PPASS
DetailsDave Hannah
Fire treated plywood walls L5 corridors and East Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Conference9/18/20199/19/20199/19/2019ADONE
DetailsDave Hannah
Inspector requirements for Tenant build-out Phone #: ###-#### Inspection requested via web by Sam Reading
Issue PAID IN FULL permit  8/19/2019 DONE
Print Occupancy Form  8/19/2019 DONE
Telephone call  8/16/2019 DONE
emailed brooke informing her that there are fees still due for issuance
Plan assigned to (CDM)6/11/20196/11/20197/15/2019 PASS
DetailsCarl D Madsen
07/04 USAO L-3
PLANS/APPL TAKEN TO FRONT DESK  7/15/2019 DONE
Override - Parcel Holds  7/15/2019  
Permit Ready to Issue  7/15/2019 DONE
all met-emailed brooke@bvadev.com the fees that are due

Need GC-met
Need Rev Val-met
Routing - MECHANICAL7/10/2019 7/11/2019 PASS
DetailsTroy James
Route to Impact Fee Review7/3/20197/6/20197/3/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - FIRE6/11/20196/11/20197/2/2019 PASS
DetailsMark Scharfen
07.02.2019-IFC review complete. Uploaded rev_fire 07.02.2019.pdf.
1st review completed  7/2/2019 DONE
Routing - PLAN CHECK6/11/2019 6/28/2019 PASS
DetailsCarl D Madsen
Routing - MECHANICAL6/11/2019 6/14/2019 FAIL
DetailsTroy James
see eplan
Routing - PLANNING6/11/2019 6/12/2019 PASS
DetailsNicolette Womack
Only interior work approved.
Routing - PUBLIC WORKS6/11/2019 6/12/2019 PASS
DetailsAngela Hardy
Routing - Addressing6/11/2019 6/11/2019 PASS
DetailsDoug Chausow
Routing - PLUMBING6/11/2019 6/11/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Intake Approval  6/7/2019 PASS
Intake Approval  6/3/2019 FAIL
DetailsJoe Bruce
Please provide the following to complete your prescreen:
1) The lighting compliance COMcheck is required to be printed on the plans. See checklist for requirement. A separate document is not permitted for the submittal.
2) Sheet G001 lists the incorrect mechanical and plumbing code adopted by the City of Boise. Please see the following link for currently adopted codes by the City of Boise: https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/general-building-information-300/301-current-codes/
3) Sheets A401-A404, A562, E100, E203, E402, E403, E501, S101, M503, are listed on the drawing index, but have not been uploaded into the drawings folder. Please provide drawings or remove from drawing index.
4) Sheet S001 lists the 2012 IBC in multiple locations for special inspections. The City of Boise has adopted the 2015 IBC. Please revise the sheets to reflect the adopted codes and revise drawings as necessary with current code.
5) Sheet E503 has been included in the drawing files, but not reflected in the sheet index. Update the drawings and sheet index to match.
6) Statement of special inspections is marked on the checklist, but could not be found in the documents folder. Upload this document as required by the checklist.
7) Plan sheets (See sheet Structural Drawings - S001) do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
Application received  5/29/2019 DONE
Application submitted via PDS Online on May 29 2019 9:21AM
Third Notice 8/16/2020