Final | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PART |
Tom Saunders
|
|
|
North tower 12 units House lights Phone #: ###-#### Inspection requested via web by Todd Hall.... North last 12 units ok 309-312,209-212, 109-112 exterior building a nd breezway lighting
for final: exterior site lighting complete carports access to service equipment..house panel masked off for painting
|
Final | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PART |
Tom Saunders
|
|
|
building 11 center tower units (12) Phone #: ###-#### Inspection requested via web by Todd Hall.... Units 101,102 D/W done 12 middle units ok 105-108, 205-208, 305-308
|
Final | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Rock A. Hudson
|
|
|
South tower 12 units Phone #: ###-#### Inspection requested via web by Todd Hall 101, 102 DW not hooked up, House circuits not complete. Rest of units only south tower TCO ok.
|
Electrical Rough-In | 6/9/2020 | 6/10/2020 | 6/10/2020 | A | PASS |
Tom Saunders
|
|
|
underground for bollard lights late morning if you can Tom Phone #: ###-#### Inspection requested via web by Todd Hall...GFCI protected feeder in PVC...ok to cover
|
Electrical Rough-In | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | NR |
Tom Saunders
|
|
|
underground inspection for bollard light conduits Phone #: ###-#### Inspection requested via web by Todd Hall....not ready
|
Electrical Rough-In | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PASS |
Tom Saunders
|
|
|
inspection for carport power riser conduits Phone #: ###-#### Inspection requested via web by Todd Hall...requiring GFCI protection for circuit of carports...risers got lifted by excavator...ok to pour
|
Electrical Rough-In | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | PASS |
Tom Saunders
|
|
|
underground for carports, pole lights, irrigation pump. see pics Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover...pics received per time constraints on getting covered for access to job site
|
Electrical Rough-In | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | PASS |
Tom Saunders
|
|
|
Bldg #11 North tower unit ceiling drops inspection (12) units Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover
|
Electrical Rough-In | 4/6/2020 | 4/6/2020 | 4/6/2020 | A | NR |
Tom Saunders
|
|
|
underground for carports, pole lights and irrigation pump. Please inspect late morning if possible Phone #: ###-#### Inspection requested via web by Todd Hall...not ready...contractor called...excavator behind
|
Electrical Rough-In | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Tom Saunders
|
|
|
Middle tower (12) units ceiling drops Phone #: ###-#### Inspection requested via web by Todd Hall...drops ok to cover
|
Electrical Rough-In | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | PASS |
Tom Saunders
|
|
|
rough in North tower first floor 4 units Phone #: ###-#### Inspection requested via web by Todd Hall...rough ok to cover...building complete
|
Electrical Rough-In | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | PASS |
Tom Saunders
|
|
|
South tower 12 units ceiling drops Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover
|
Electrical Rough-In | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | PASS |
Tom Saunders
|
|
|
North tower 2nd floor 4 units Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover above areas
|
Electrical Rough-In | 3/9/2020 | 3/9/2020 | 3/9/2020 | P | PASS |
Rock A. Hudson
|
|
|
3rd floor North tower 4 units Phone #: ###-#### Inspection requested via web by Todd Hall Units L- 309, 310, 311, 312 rough in ok cover
|
Electrical Rough-In | 2/27/2020 | 2/27/2020 | 2/27/2020 | P | PASS |
Tom Saunders
|
|
|
Middle tower first floor units and breezeway lights building 11 Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover areas requested
|
Electrical Rough-In | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | PASS |
Tom Saunders
|
|
|
2nd floor units in middle tower. North exterior wall for cover of unit feeders Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover areas requested
|
Electrical Rough-In | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PASS |
Tom Saunders
|
|
|
building 11 middle tower 3rd floor Phone #: ###-#### Inspection requested via web by Todd Hall... tower 2... 3rd floor units...ok to cover
|
Electrical Rough-In | 2/12/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Tom Saunders
|
|
|
South tower 2nd floor and 1st floor units (8 total) All stairwells and 3rd floor stairwell ceilings. Please call if any issues with pushing any of this to Thursday. 2nd floor and stairwells are priority. Phone #: ###-#### Inspection requested via web by Todd Hall.. ok to cover areas listed above
|
Electrical Rough-In | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | PASS |
Tom Saunders
|
|
|
Rough-In for BLDG 11, 3rd floor units, South Tower (4 units) Phone #: ###-#### Inspection requested via web by Todd Hall... ok to cover...3rd floor/Tower 1...4 units and breeze way
|
Electrical Rough-In | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | PASS |
Daryl DeGrange
|
|
|
rough in for unit feeders up South Wall and across attic area for South half of building. 18 units Phone #: ###-#### Inspection requested via web by Todd Hall r/i ok cover south wall 3 floors
|
Electrical Rough-In | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Tom Saunders
|
|
|
units 103,104,105,106,203,204,205,206,303,304,305,306 in bedrooms at firewall fro pre-rock Inspection requested via web by Todd Hall.. joining bedroom wall ok to cover...all units 3 stories
|