INSP-Final Inspection | 8/26/2015 | 8/27/2015 | 8/27/2015 | A | PASS |
Thomas Walsh
|
|
|
Final inspection and signoff for this permit.
|
INSP-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection for Tower 3 section of the building for all floors. Noted a couple of sprinklers that needed finish trim installed, and these were corrected before end of inspection. Tower 3 final passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2015 | 8/17/2015 | 8/17/2015 | P | PART |
Thomas Walsh
|
|
|
Hydrotest of new standpipe added in Tower 4 - 200 psi @ 2 hours - PASSED
|
INSP-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | PART |
Thomas Walsh
|
|
|
Inspection of fire sprinklers for units 514 and 515 to add to TCO for the 5th floor of Tower 3. - OK to occupy these units.
|
INSP-Alarm Testing | 7/9/2015 | 7/10/2015 | 7/10/2015 | A | PART |
Thomas Walsh
|
|
|
Inspection of A/S for Towers 1 # 2 sections of the building - all floors. TCO is requested for this section of the building, so this was a pre-final inspection for the units in this area of the building. A few escutcheon were missing, but were installed before the end of the inspection. Fire sprinklers for this portion of the building are finaled.
|
INSP-Sprinkler Rough-in/Hydro | 7/6/2015 | 7/6/2015 | 7/6/2015 | P | PART |
Thomas Walsh
|
|
|
Trip test of dry pipe valve supplying sprinklers in the fitness area, including the are below the pool/spa. Also tested fire alarm interface including water flow, tampers, and low-air test - All tested OK. Following these tests, the system was put on a 2 hour hydrotest, which also passed. NOTE: This completes the tests to all of the systems for the entire building. Final inspections are pending completion of Towers 3 and 4 areas.
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 7/2/2015 | 7/2/2015 | A | PART |
Thomas Walsh
|
|
|
Completion of the 24 hour air test of the the three dry pipe systems protecting the parking garage and fitness area. PASSED Conducted a trip test of the two dry systems protecting the parking garage. The system to the north flowed at 90 seconds, while the system to the south flowed at 50 seconds. Also hydrotested the wet system for the third floor and the wet system for the lobby area - 200 psi @ 2 hours - these both passed. NOTE: Could not trip test the dry system for the fitness center as this area was not accessible.
|
INSP-Alarm Testing | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | PART |
Thomas Walsh
|
|
|
Fire alarm interface tested, including all wet pipe waterflows (all floors), tampers, etc., including the exterior bell. All systems tested OK. Final inspection to follow.
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotests of floors 2 and 4 - 200 psi @ 2hrs, - PASSED. NOTE: Floor 3 had a leak and floor 5 is not ready for test.
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotests of floors 2 and 4 wet pipe systems - 200 psi @ 2hrs - PASSED NOTE: Floor 3 had a leak, and floor 5 is not ready for test.
|
INSP-Sprinkler Rough-in | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for under pool deck area - off of fitness room system. OK to cover.
|
INSP-Sprinkler Rough-in | 6/24/2015 | 6/25/2015 | 6/25/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for elevator lobbies on the 4th and 5th floors for Tower4, and unit inspections for hard lid soffits on the 2nd floor Tower 4, including units 200, 201, 202, 203, 204 and 205. OK to cover these areas.
|
INSP-Sprinkler Rough-in | 6/23/2015 | 6/24/2015 | 6/24/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for ist floor lobby rooms, including restrooms. Also fitness room sprinklers located above T-bar ceiling tilles. OK to cover the heads in these areas. NOTE: Inspection actually ocurred on 6/23.
|
INSP-Sprinkler Rough-in | 6/12/2015 | 6/15/2015 | 6/15/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for Tower 3 pod on the second floor, and the corridor for Tower 4 - also second floor.
|
INSP-Sprinkler Rough-in | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover unit soffits for 3rd floor tower 4 section, including units 300 thru 305. OK to cover the soffits in these units.
|
INSP-Sprinkler Rough-in | 6/3/2015 | 6/3/2015 | 6/3/2015 | P | PART |
Thomas Walsh
|
|
|
Rough inspection of unit soffits for Tower #4, 4th and 5th floors, including units 400, 401, 402, 403, 404, 405, 500, 501, 502, 503, 504 and 505. All inspected OK - unit 502 needs sprinkler installed. Also soffits in trash rooms - Tower 2 floors 2 thru 5. OK to cover pipe in these areas
|
INSP-Sprinkler Rough-in | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | PART |
Thomas Walsh
|
|
|
Tower 4 cooridor rough inspection for floors 4 and 5. Also several hard lid areas/rooms on the first and second floors - see plans for locations. PASSED - OK to cover.
|
INSP-Sprinkler Rough-in | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | PART |
Thomas Walsh
|
|
|
Rough-in inspection of 1sr floor hard lids near stair #1. Also stair 1 levels 3 and 4, and 4th floor POD area.
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2015 | 5/19/2015 | 5/19/2015 | P | PASS |
Thomas Walsh
|
|
|
Rough-in of fitness room dry system, elevator loobies for elevator #1 (floors 2 thru 5), and 3rd floor pod soffits for Tower 3. No discrpancies noted.
|
INSP-Sprinkler Rough-in | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | CANC |
Thomas Walsh
|
|
|
Rough-in inspection of fitness room dry system. Also elevator lobbies for elevator #1 (floors 2 thru 5) and 3rd fllor pod soffits located in tower 3. No discrepancies noted.
|
INSP-Sprinkler Rough-in | 5/6/2015 | 5/8/2015 | 5/16/2015 | A | PASS |
Thomas Walsh
|
|
|
Rough-in inspection of Elevator lobiesy, all floors, tower 1.
|
INSP-Sprinkler Rough-in | 5/14/2015 | 5/15/2015 | 5/16/2015 | A | PASS |
Thomas Walsh
|
|
|
Rough in inspection for tower 3 pod units, floors 1 thru 4, including units 206-209, 306-309, 406-409, and 506 -509
|
INSP-Sprinkler Rough-in | 5/1/2015 | 5/4/2015 | 5/4/2015 | P | PART |
Scott Arellano
|
|
|
Fire sprinkler rough inspection - Nate - Shilo FP 2nd floor corridors for towers 1 thru 3, and unit soffits sprinklers for all units in tower #3, floors 2 thru 5.
No discrepancies noted.
|
INSP-Sprinkler Rough-in | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | PART |
Katie Marron
|
|
|
3rd floor hallways OK to cover. See drawings for specific area of coverage.
|
INSP-Sprinkler Rough-in | 4/20/2015 | 4/20/2015 | 4/20/2015 | P | PART |
Katie Marron
|
|
|
5th and 4th Floor corridors, tower 3 to fire doors OK to cover. Noticed one area in pod with missing hangar.
|
INSP-Sprinkler Rough-in | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | PART |
Katie Marron
|
|
|
Floors 4, 3 and podium in tower 4 living quarters ok to cover, except room 204 with overspaced bedroom head and room 200 missing closet head. Soffits in tower 3 ok to cover.
|
INSP-Sprinkler Rough-in | 4/10/2015 | 4/14/2015 | 4/14/2015 | P | FAIL |
Katie Marron
|
|
|
Fail. Missing hangers at numerous locations and a branch line not connected to the main. Will verify corrections at next inspection scheduled for 4/15/15.
|
INSP-Sprinkler Rough-in | 4/8/2015 | 4/10/2015 | 4/10/2015 | A | DEFR |
Forrest France
|
|
|
This is 4th fl. Please call 1/2 hr prior to inspection. Nate is the contact. Thanks Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/6/2015 | 4/7/2015 | 4/7/2015 | P | PART |
Scott Arellano
|
|
|
Approved for rough cover within in rooms and corridors at 5th floor.
|
INSP-Sprinkler Rough-in | 4/2/2015 | 4/3/2015 | 4/3/2015 | A | PART |
Forrest France
|
|
|
4th and 5th floor tower 2 sprinkler coverage at soffits units only okayed- need to provide missing fire stop at some locations. Field modifications at the first floor lobby to be reflected on plan mod.
|
INSP-Sprinkler Rough-in | 3/31/2015 | 4/1/2015 | 4/1/2015 | A | PART |
Forrest France
|
|
|
Inspection completed for connection of trash chute sprinkler heads at towers one and three- floor levels 5th, 3rd and podium.
|
INSP-Sprinkler Rough-in | 3/13/2015 | 3/16/2015 | 3/16/2015 | P | PART |
Forrest France
|
|
|
Verified C/N item at the 5th floor unit 511 tower 2. Rough-in for coverage at soffits 1st floor tower 1.
|
INSP-Sprinkler Rough-in | 2/27/2015 | 3/2/2015 | 3/6/2015 | A | PART |
Forrest France
|
|
|
Requesting inspection on the 3rd ; 4th floor. Nate M is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/26/2015 | 2/27/2015 | 3/6/2015 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/26/2015 | 2/26/2015 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | PART |
Forrest France
|
|
|
Requesting RTC 3rd floor tower 2. Nate is your is your contact. Please Call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 2/12/2015 | 2/13/2015 | 2/13/2015 | A | DONE |
Forrest France
|
|
|
On site conferecne regarding NFPA 13 2013 sec. 8.5.5.4
|
INSP-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 | A | PART |
Forrest France
|
|
|
Verified added coverage at the 3rd and 4th floor tower two riser room concealed spaces.
|
INSP-Sprinkler Rough-in | 2/5/2015 | 2/6/2015 | 2/6/2015 | A | PART |
Forrest France
|
|
|
Rough-in inspection completed for living units only at tower 2 podium level. Install incomplete at the common area room 241. Also okayed prior C/N items at the 3rd and 4th floors tower 2. Note: * Damaged main and branchlines due to overheating by proximity to temporary jobsite heating appliances on the 2nd thru 5th floor corridors tower one to be replaced as discussed.*
|
INSP-Sprinkler Rough-in | 2/4/2015 | 2/4/2015 | 2/4/2015 | A | PART |
Forrest France
|
|
|
Completed rough-in inspection for the 5th floor tower 2 living units and common corridor. Also okayed for cover drops at lower soffits 4th floor tower 1.
|
INSP-Sprinkler Rough-in | 2/2/2015 | 2/3/2015 | 2/4/2015 | P | PART |
Forrest France
|
|
|
Completed rough-in inspection of the 3rd and 4th floors tower 2 living units with the exception of NE end and corner rooms not yet piped. DSW heads at some units not yet installed, need to provide coverage at the riser room chases per plan, noted missing coverage at bedroom in unit 322. Rough-in inspections to be done prior to ceiling insulation, discussed distances to be maintained from light fixtures, ceiling fans, and heat sources per NFPA guidelines.
|
INSP-Sprinkler Rough-in | 1/26/2015 | 1/27/2015 | 1/27/2015 | A | PART |
Forrest France
|
|
|
Center pendent head and branch at the pods tower one podium level thru 4th floor okay for sheetrock ceiling cover.
|
INSP-Sprinkler Rough-in | 11/20/2014 | 11/21/2014 | 11/21/2014 | A | PART |
Forrest France
|
|
|
Rough-in inspection completed at "tower one" 5th floor room units 530,531,532,533,535,536, and 537, and common corridor including the elevator lobby. Noted items include; overspaced and obstructed head at unit 531 bedroom, relocate one sprinkler too close to a wall in unit 530, furnace rooms to be provided with intermediate temp heads, verify coverage at the elevator hoistway.
|
INSP-Conference | 10/17/2014 | 10/17/2014 | 10/17/2014 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 9/15/2014 | 9/16/2014 | 9/16/2014 | A | PART |
Forrest France
|
|
|
Intended for an UG fire supply line hydrostatic test- Hydro passed.
|
INSP-Conference | 11/26/2014 | 11/26/2014 | | P | |
Forrest France
|
|
|
Nate is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|