Information based on query as of Tuesday, May 21, 2024.
Permit Information
Permit NumberFIR14-00875
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 1011 W ROYAL BLVD
Project NameBoise Heights Apartments
Customer Number 
ePlanReviewYes
Description
Boise Heights apartments to provide a code compliant fire alarm. This is a 5 story multi person dormitory. To include all fire alarm for entire building. Associated with building permit BLD13-03405
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/26/20158/27/20158/27/2015APASS
DetailsThomas Walsh
Final inspection/test of fire alarm system for Tower 4 area - all floors, including elevator 2 recal/alt. recall functions, area SD for elevator lobbies, unit smoke detection, etc.
All devices tested satisfactorily.. System is being monitored off site - correct address was confirmed.
INSP-Final Inspection8/27/20158/27/20158/27/2015PPASS
DetailsThomas Walsh
Final inspection/test of fire alarm system for Tower 4 - all floors, including elevator# 2 recall/alt. recall functions, SDs for elevator lobbies, unit SDs, etc. All devices tested satisfactorily. Offsite monitoring and correct address confirmed.
INSP-Final Inspection8/26/20158/27/20158/26/2015ACANC
DetailsJim Page
>> Inspection requested via mobile web by Nathan Proce Inspection cancelled via mobile web on Wednesday, August 26, 2015.
INSP-Alarm Testing8/19/20158/20/20158/20/2015PPART
DetailsThomas Walsh
Fire alarm inspection/test for Towers 3 & 4 corridors only - no unit inspections were conducted.
Test of MPs. SDs for FSDs, SDs for DH, etc, just within the corridors. Elevator for Tower 4 not ready for test. All devices tested satisfactorily within the corridors, and checked many units under general alarm.
INSP-Alarm Testing8/18/20158/18/20158/18/2015PPART
DetailsThomas Walsh
Fire alarm testing is completed for the building up to and including the 4th floor (5th floor is not completed yet). All fire sprinkler systems are in service and all fire alarm devices are also in service. I did find some units on the 4th floor that still had their protective cap on their room SDs, and these should be removed before releasing the unit to the resident. The FACP is fully monitored and is being put into service at the end of each day.
INSP-Final Inspection8/13/20158/14/20158/14/2015APART
DetailsThomas Walsh
Fire alarm system testing of portions of Tower 3 5th floor (units 514 &515)) to add to TCO. Alarms for these units, and area of the corridor serving these units, are OK
INSP-Alarm Testing7/9/20157/10/20157/10/2015APART
DetailsThomas Walsh
Tower 2 fire alarm testing, including elevator # 1 recall functions, MP, SDs, unit smoke detection, SFDs, general notification and rooftop HVAC units serving tower 2.
All devices staisfactorily.
GC is requesting TCO of Tower 1 and 2 (all floors). Fire alarm system has been tested and is functonal for these areas.
INSP-Alarm Testing7/1/20157/2/20157/2/2015APART
DetailsThomas Walsh
Testing of fire alarm system for the 5th floor (Tower 1) and the rooftop HVAC units for shutdown. Also confirmed test of fire sprinkler dry pipe systems with FACP.
NOTE: Many of the descriptions and locations of the various devices will have to be updated to clarify the device locations and purpose/function. Will retest some of the devices alraedy tested to confirm proper addressing.
NOTE: Tower 3 and Tower 4 areas - all floors not tested todate.
INSP-Alarm Testing6/30/20157/1/20157/1/2015APART
DetailsThomas Walsh
Partial fire alarm test for the entire apartment building, including all fire sprinkler interface devices, including waterflows, tampers, etc., and then all fire alarm devices, including SDs, FSDs, MPs, elevator recall functions (Elevator # 1 only). More testing is required to complete the process, mostly on the upper floors.
NOTE: Fire alarm installation work is still on-going in Towers 3 & 4, while they are looking for partial TCO for Towers 1 and possible 2. Therfore, this is just a partial test of the system that is completed today.