Description
[Rivers Edge Apartment]
The fire sprinkler scope of work consists of protecting four levels of a five level apartment building plus an attic (A complete total of 6 levels of fire protection in 3 permits). The first level and the underground are under two other separate permits. Extended cover residential sprinklers are being utilized throughout except for the attic, which has coin sprinklers. There is a class I standpipe throughout. The structure is divided into two building by the use of firewalls. The east portion is under building permit BLD13-02425 and the west portion is under permit BLD13-02424. There are two horizontal exits in the firewalls. CPVC piping is being used except for expose areas and the attic. Seismic sway braces are not required since the building is in a seismic category of B.

The first floor is under permit FIR14-00687
The underground is under permit FIR14-00638

The east wing consists of four floors of 32, 940 sq. ft. each, a total area of 131,760 sq. ft. with (91) dwelling units [(23)-2BR apartments (5 on 2nd floor / 6 on floors 3, 4 & 5 ) and (68) - 4BR apartments (17 per floor)]. All 2-BR units exceed 800 Sq. ft. in area and all 4-BR units exceed 1,100 sq. ft. in area. The east and west wings of the residential floors are divided by a 2-hour fire wall / horizontal exit assembly, extending from the top of 3-hour concrete floor to the underside of the roof deck sheathing, with fire retardant plywood deck extending 4 feet on each side of fire wall in place of a parapet. The dwelling units are separated from the parking area on the 1st level by a 3-hour fire-resistive horizontal floor/ceiling assembly. This allows the parking garage and the residential units above to each be considered as a separate building for code compliance. drs DRH12-00013 CUP11-00090 CFH11-00036
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/14/20159/15/20159/15/2015APASS
DetailsThomas Walsh
Test of new control valve for horizontal exit standpipes. Also signed off Certificate of completion forms.
INSP-Sprinkler Rough-in8/31/20158/31/20158/31/2015PPASS
DetailsThomas Walsh
Hydrostatic pressure test for the two new standpipes added on one sire of each (two) horizontal exits (south corridor and middle corridor)
200 psi @ 2 hours - PASSED
NOTE: Two new control valves supplying these new standpipes will have to be tied into the fire alarm system for monitoring purposes.
INSP-Final Inspection8/19/20158/20/20158/20/2015PCANC
DetailsThomas Walsh
Final inspection conducted through the 5th floor, on 8/19/15, however Records of Completion forms need to be submitted for all three (3) permits associated with this project. Contractor agreed to get paperwork together for signoff.
INSP-Sprinkler Rough-in8/18/20158/19/20158/19/2015APART
DetailsThomas Walsh
Rough to cover inspection for a sprinkler needing to be added to comm. closet # 360.
PASSED
NOTE: Also inspected 5th floor for sprinkler final. Several heads had to be cleaned due to mud on deflectors. Contractor agreed to call in for final signoff on all three (3) permits for this project.
INSP-Final Inspection8/17/20158/18/20158/18/2015PPART
DetailsThomas Walsh
Final walk through inspection of all fire sprinkler systems up to the 4th floor. The is one room (closet 360) that needs to have a sprinkler added, due to an extension of the room from the original plan. There are also some sprinklers (mostly patio heads) that are covered to protect from painting that is on-going on the south side of the building.
Fianl signoff is pending the completion and inspection of the 5th floor units and corridors.
INSP-Alarm Testing8/18/20158/18/20158/18/2015PPASS
DetailsThomas Walsh
Functional test of all fire sprinkler systems with fire alarm interface, including dry pie valve trip tests, low air alarms, wet system waterflows, all tampers, exterior bell activation, etc. All systems tested OK and were put into service at the end of the day. Inspection occurred 8/15.
INSP-Final Inspection8/13/20158/14/20158/14/2015PPART
DetailsThomas Walsh
Completed 24 hour air tests of the two dry pipe valves protecting the attics (North and South) - PASSED.
Also hydrotested the 5th floor wet pipe systems (200psi @ hours) - PASSED
INSP-Supply line flush8/12/20158/13/20158/13/2015APART
DetailsThomas Walsh
24 hour air tested started for all (four) dry=pipe valves. Will retest in 24 hours to ensure system is ait tight.
INSP-Sprinkler Rough-in8/12/20158/13/20158/13/2015ACANC
DetailsThomas Walsh
5th floor wet systems not ready for hydrotest. Canceled Appt.
INSP-Sprinkler Rough-in/Hydro8/12/20158/13/20158/13/2015APART
DetailsThomas Walsh
%th floor dry-pipe system hydrostatic test (North side). 200 psi @ 2hrs - PASSED
NOTE: South side DP system for 5th floor hydrotested this morning - also PASSED
INSP-Sprinkler Rough-in8/11/20158/13/20158/13/2015PPART
DetailsThomas Walsh
Rough to cover inspection for the entire 5th floor corridors, including elevator lobbies.
OK to cover pipe in these areas.
Actually inspected on 8/12 TW
INSP-Sprinkler Rough-in/Hydro8/11/20158/13/20158/13/2015PPART
DetailsThomas Walsh
Hydrostatic test of two (2) wet pipe systems for the fourth floor - 200 psi @ 2hrs - PASSED. Actually tested on 8/12 TW.
INSP-Sprinkler Rough-in8/6/20158/7/20158/7/2015PPART
DetailsThomas Walsh
4th floor RTC inspection for the entire north and south corridors.
Exit signs near units, 412, 418, 426, and 429 are currently obstructing the sprinklers near these units, and will have to be relocated to provide proper clearance.
Otherwise - OK to cover the pipe in this corridor (4th level).
INSP-Sprinkler Rough-in/Hydro8/6/20158/7/20158/7/2015PPASS
DetailsThomas Walsh
Hydrostatic test of 2nd and 3rd floor wet systems - north and south sides.
200 psi @ 2 hours - all passed
INSP-Sprinkler Rough-in8/4/20158/4/20158/4/2015PPART
DetailsThomas Walsh
RTC inspection for 3rd floor corridors (all sides), including elevator lobbies. Need to add (1) A/S in center lobby, near east hallway. Otherwise OK to cover 3rd floor corridor pipe.
Also inspected 2nd floor elevator lobbies - center and south sides. OK to cover the pipe in these areas.
INSP-Sprinkler Rough-in7/29/20157/30/20157/30/2015APART
DetailsThomas Walsh
RTC 2nd floor corridors - all sections.
PASSED - OK to cover sprinkler pipe in this area.
INSP-Sprinkler Rough-in7/23/20157/24/20157/24/2015APART
DetailsJim Page
Inspected drop down ceiling area's in rooms 502, 525, 529, approved for cover. Verified with contractor list for the 5th floor apartment rooms, all rooms inspected for rough to cover.
INSP-Sprinkler Rough-in7/22/20157/23/20157/23/2015APART
DetailsJim Page
Inspected drop down ceiling area's in rooms 504, 508, 516, 531, 533, 538, 539, approved for cover
INSP-Sprinkler Rough-in7/21/20157/22/20157/22/2015APART
DetailsJim Page
Inspected drop down ceiling area's in rooms 501, 502, 503, 506, 514, 515, 522, 534, 535, 536, 537, 540, 541, 542, 543, approved for cover
INSP-Sprinkler Rough-in/Hydro7/8/20157/10/20157/10/2015PPART
DetailsThomas Walsh
5th floor drop lids unit inspection for the east side units, including unit 512, 513, 514, 515, 517, 518, 519, 522 and 521.
OK to cover drop lids in these rooms.
INSP-Sprinkler Rough-in7/8/20157/10/20157/10/2015PPART
DetailsThomas Walsh
5th floor corridor insulation (tenting) for the east side. All corridors on the 5th floor are OK to cover.
INSP-Sprinkler Rough-in7/1/20157/2/20157/2/2015PPART
DetailsThomas Walsh
Insulation (tenting) inspection of fire sprinkler piping for the 5th floor west units, 530, 532, 534, 535, 536, 538, and 539 - also corridors on the east side from unit 506 to 509.
OK to cover these areas,
INSP-Sprinkler Rough-in6/30/20157/1/20157/1/2015PPART
DetailsThomas Walsh
Insulation (tenting) inspection for 5th floor units, including unit 501, 506, 536, 537, 533, 531, 540, 541, 542, 543, and 544. A few more units still need to be done before the entire 5th floor is completed.
INSP-Sprinkler Rough-in6/29/20156/30/20156/30/2015ACANC
DetailsThomas Walsh
INSP-Sprinkler Rough-in6/26/20156/29/20156/29/2015PPART
DetailsThomas Walsh
This is a rough to cover inspection of the 4th floor west unit drop lids, including units 419 thru 442. A few discrepancies were noted in fire caulking that were addressed prior to the end of the inspection.
OK to cover pipe in these units (4th floor - entire west side).
INSP-Sprinkler Rough-in/Hydro6/25/20156/26/20156/26/2015APART
DetailsThomas Walsh
RTC inspection for dry and wet pipe system supplying the noth side of floor #5. Both passed inspection, while some repair work was needed for several draft stops, that were repaired before the end of the inspection. OK to cover for these two systems. Also tenting (insulation) inspection of units 509, 510, 512, 513, 514, 515, 516, 517 and 518.
INSP-Sprinkler Rough-in6/22/20156/23/20156/23/2015PPART
DetailsThomas Walsh
Tenting (insulation) inspection for 5th floor wet system, including units 526, 527, 528, and 529 on the west side, and units 519, and 520 on the east side. Also 5th floor corrdor on the southwest side to unit 529.
OK to cover pipe in these areas.
INSP-Sprinkler Rough-in/Hydro6/19/20156/22/20156/22/2015APART
DetailsThomas Walsh
Insulation (tenting) inspection for 5th floor wet pipe system - south side corridor from unit 527 to south stair lobby, also inuts 521, 522, 523, 524 and 525. All inspected OK after a few field adjustments were made to provide adequate protection of CPVC pipe.
INSP-Sprinkler Rough-in6/19/20156/22/20156/22/2015APASS
DetailsThomas Walsh
Reinspection of 5th floor units 517 and 518 to reinspect for dry pipe sprinkler obstructions. The changes inspected OK, and this completes the rough inspection for the south side dry pipe system.
NOTE: 24 hour air test and hydrotest of this system will be scheduled at a future date.
INSP-Sprinkler Rough-in6/19/20156/19/20156/19/2015PPART
DetailsThomas Walsh
Reinspection of 5th floor South dry pipe system for attic protection, including changes made to address numerous obstructions created by the installation of draft stops. All previous discrepancies corrected this visit, except for units 517, and 518, which will require further work. OK to cover all units except units 517 and 518, which will require reinspection prior to cover.
INSP-Sprinkler Rough-in6/18/20156/19/20156/19/2015APART
DetailsThomas Walsh
Retest of 5th fllor south dry pipe system to check for corrections needed from 6/18 inspection - many discrepancies were not adequately addressed, so plans to come back for another inspection are necessary.
Completed the 5th floor south wet system inspection, that were not ready on the 6/18 inspection. - OK to cover this area.
Also inspected 4th floor east side drop lids, including units 401, 402, 403, 404, 405, 406, 407, 409, 410, 411, 412, 413, 414, 415, 416, 417, 418, 420 and 443. All inspected OK - OK to cover the hard lids in these units.
INSP-Sprinkler Rough-in6/16/20156/18/20156/18/2015APART
DetailsThomas Walsh
RTC inspections of the 5th floor south wet and dry pipe systems - see plans for extent of inspection.
NOTE: Dry pipe system protecting the south attic space inspection failed as there are many obstructed sprinklers due to close proximity to draft stops. Many can be easily addressed as the draft stops were located on the wrong truss section. Some others will require adjustments in the sprinkler locations or adding some new heads to provide adequate coverage where heads cannot be moved. See plans were these discrepancies occur.
Wet pipe system inspected for all units on the southwest side of the building. Others missed will be inspected next visit.
INSP-Sprinkler Rough-in6/16/20156/17/20156/17/2015APART
DetailsThomas Walsh
RTC unit inspections for insulation for 4th floor west side units, including 421, 422, 423, and 440. This completes the 4th floor west for insulation inspections - OK to cover.
INSP-Sprinkler Rough-in6/12/20156/15/20156/15/2015APART
DetailsThomas Walsh
4th floor west unit insulation inspection, including units 424, 426, 427, 428, 429, 431, 432, 433, 434, 435, 436, 437, 438, and 439.
Units 427, 436 and 438 need touch up - will reinspect at tomorrow's inspection.
INSP-Sprinkler Rough-in6/11/20156/12/20156/12/2015PPART
DetailsThomas Walsh
RTC inspection for soffit lids for 3rd floor West units, including units 308, 319, 321, 322, 323, 324, 325, 326, 327, 328, 329, 330, 331, 333, 332, 335, 334, 337, 341, 340, 342, - Units 336, 339, and were already done. This should complete both wings of 3rd floor for unit soffit inspections.
INSP-Sprinkler Rough-in6/9/20156/10/20156/10/2015APART
DetailsThomas Walsh
Rough to cover inspection for unit soffits of 3rd floor west, including units 326, 327, 328, 329, 330, 332, 335, 339, 337, 336, 338, 339, 340 and 341.
OK to cover soffits for these units.
INSP-Sprinkler Rough-in6/4/20156/5/20156/5/2015APART
DetailsThomas Walsh
4th floor east side unit inspections for insulation prior to sheetrock, including all units from 401 thru 420, except 419, which was not ready.
INSP-Sprinkler Rough-in6/3/20156/4/20156/4/2015APART
DetailsThomas Walsh
Rough in inspection of unit soffits for 2nd floor west, including units 225 and 231 to complete this area, and 3rd floor east units, including 301, 302, 304, 305, 306, 307, 309, 311, 312, 313, 314, 315, 317, 318, 320, 343, and 344.
INSP-Sprinkler Rough-in5/28/20155/29/20155/29/2015APART
DetailsThomas Walsh
3rd fllor west units for insulation inspection - units # 321 thru 339, and unit 340 and 341.
Also stait lobbies at stait C & stair C - 3rd floor.
All passed after a few adjustments made during the inspection.
INSP-Sprinkler Rough-in/Hydro5/22/20155/26/20155/26/2015APART
DetailsThomas Walsh
3rd floor east wing insulation inspection, including units 301, 302, 303, 304, 305, 306, 307, 308,, 309, 310, 311, 312, 313, 314, 316, 343, and 344.
Rich - GC ###-####
INSP-Sprinkler Rough-in5/19/20155/20/20155/20/2015PPART
DetailsThomas Walsh
Rough-in inspection of 4th floor east side units (units 401 thru 420) and units 443 and 444 - all OK to cover.
Also 2nd floor west side unit soffit inspections - units 224, 226, 227, 228, 232, 234, 235, 236, 237 and 238. Unit 232 needs HT head in furnace room - OK to cover.
INSP-Sprinkler Rough-in5/12/20155/13/20155/16/2015APASS
DetailsThomas Walsh
Rough to cover for 3rd Floor West and visual insulation inspection on 2nd floor SW, including units 221-241, and units 319-339.
INSP-Sprinkler Rough-in/Hydro5/10/20155/10/20155/10/2015PPASS
DetailsThomas Walsh
INSP-Sprinkler Rough-in5/7/20155/8/20155/8/2015APASS
DetailsThomas Walsh
2nd floor, East drop lids.
INSP-Sprinkler Rough-in/Hydro5/8/20155/8/20155/8/2015APASS
DetailsThomas Walsh
2nd floor east wing unit hard lids/drops - unit 210 and 212 needs work
INSP-Sprinkler Rough-in5/6/20155/7/20155/7/2015ACANC
DetailsScott Arellano
Inspection on the insulation 2nd floor, west wing. Tyler is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/6/2015 5/6/2015ACANC
DetailsTroy Cobbley
Elevator lobby, all floors, tower 1. Nate is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in4/20/20154/21/20154/21/2015APASS
DetailsTim Frost
Passed cover inspection on Level 1 Lobby and adjoining bathrooms. Plans, have not been submitted and are required.



Re inspection of the insulation on the 2nd floor, eastwing. Also RTC 1st floor south end Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/17/20154/20/20154/20/2015APASS
DetailsTim Frost
Everything passed except for two sprinklers. One was missing and one was slightly overspaced. The corridors were not inspected. The laundry rooms were not installed. The horizontal sidewall protecting the patios were not installed.

_______

I also looke at the insulation on the second floor. The installation of the insulate was NOT acceptable. The insulation was NOT flush with the ceiling. I spoke with Shawn (Superintendent) and told him I would look at it again when the insulation was flushed.

_______

3rd floor east wing. Tyler is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Conference4/10/20154/10/20154/10/2015PPEND
DetailsForrest France
INSP-Sprinkler Rough-in4/6/20154/7/20154/7/2015APEND
DetailsTim Frost
Inspected all of second floor except for east wing which was inspected by Troy Cobbley. Second floor has passed rough in. Did not inspect the corridors.
______________
Apparently, there has been a change in the design. The drywall is not going to the deck. This leaves the entire space between the second floor ceiling and the third floor an open combustible concealed space. This space will require fire protection. Until this matter has been resolved the cover on the second floor is on hold.
INSP-Sprinkler Rough-in3/26/20153/27/20153/31/2015PPART
DetailsForrest France
Ref. to inspection notes dated 3/30
INSP-Sprinkler Rough-in3/27/20153/30/20153/30/2015APART
DetailsTroy Cobbley
Inspection was for east wing of the 2nd floor. See the city approved plans for locations marked in red and dated with todays date. I noted one overspaced head that can be verified at final and two locations where the cpvc piping may be exceeding maximum flex. Many dummy drops are installed and no actual rc's or pendants and in these locations the dummy drop is very close to a wall.Rooms are ok to cover as marked (noted above). I spoke to the General Contractor about the fire stopping in the vertical chases and needing access to verifiy the fire stopping. He is going to try for a variance due to the fact he is building the vertical chases to meet 2 Hour construction.