INSP-Final Inspection | 3/23/2020 | 3/25/2020 | 3/25/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Contact is Zach Grasmick Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need fees paid, need service tag on risers, need sticker on bell, need interconnect with the facp tested. Need above ground and underground test papers.
Contact is Zach Grasmick Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 3/19/2020 | 3/19/2020 | 3/19/2020 | A | FAIL |
Jim Page
|
|
|
Texted point of contact at 11:06AM with no response, attempted to call point of contact at 11:30AM with no answer, could not leave a message because voicemail was full. Final fire sprinkler inspection needs to be coordinated with the alarm vendor, this request will need to be rescheduled, procceeded to next inspection. Due to the second fail a reinspection fee has been added to the permit.
Raul is the contact Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | FAIL |
Jim Page
|
|
|
Exterior sidewall heads are to close to deck, minimum of 4 inches, not more than 6 inches from deck is the requirement for sidewalls per NFPA13.
Raul is contact Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in/Hydro | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | DONE |
Jim Page
|
|
|
Temporary heat was removed before temp heat was established. As discussed, if temp heat was removed and building reached below 40 degrees then a re-hydro will be required, re-hydor has been witnessed with no observed pressure loss at riser provided gauges.
Raul is contact Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 3/4/2020 | 3/6/2020 | 3/5/2020 | A | CANC |
Jim Page
|
|
|
Raul is the Contact Phone #: ###-#### >> Inspection requested via web by Chris Green Inspection cancelled from web by: Chris Green
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PART |
Jim Page
|
|
|
Was informed that permenant heat was established to builindg, temporary heat is what is keeping the building at 40 degrees and above. Hydrostsic test is unofficial, no pressure loss observed. Periodic check ins will be done, if building is below 40 degrees then a re-hydro will be required.
Contact is Raul Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in/Hydro | 1/16/2020 | 1/17/2020 | 1/17/2020 | A | FAIL |
Jim Page
|
|
|
Hydrostatic test is not accepted, no rough in inspection has been performed and plans onsite are not city approved drawings. Replace couplings with T's and plugs on dry heads, couplings are not acceptable as shown on manufactures specifications.
Contact is Raul Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Supply line flush | 1/10/2020 | 1/10/2020 | 1/10/2020 | P | CANC |
Jim Page
|
|
|
Wrong permit number for flush, underground permit is FIR19-00655
Contact is Raul Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in | 1/6/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
This is for Underground Rough In trying to aim for 3:00 ish. Contact is Raul Phone #: ###-#### Inspection requested via web by Chris Green
|