Third Notice | | 3/12/2019 | 3/8/2019 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Third Notice | | 2/11/2019 | 3/7/2019 | | DONE |
|
|
|
Sent email to Jack (jack@rrccontractors) informing him that RRC Contractors will be put on hold if final values are not sent in by 5pm 3/8/19. Have been trying to get since 5/27/18
|
Third Notice | | 12/18/2018 | 2/6/2019 | | DONE |
|
|
|
sent email to Jack (jack@rrccontractors.com) 2-6-19
|
Meeting | | | 1/8/2019 | | DONE |
|
|
|
sent email to Jack (jack@rrccontractors.com) to get final values
|
Third Notice | | 11/18/2018 | 12/13/2018 | | DONE |
|
|
|
mailed 12-14 with third follow up
|
Third Follow up | | | 12/13/2018 | | DONE |
|
|
|
|
Third Notice | | 10/17/2018 | 11/13/2018 | | DONE |
|
|
|
mailed 11-14
|
Second Follow up | | | 11/13/2018 | | DONE |
|
|
|
|
Third Notice | | 9/15/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
First Follow up | | | 10/12/2018 | | DONE |
|
|
|
|
Third Notice | | 8/12/2018 | 9/10/2018 | | DONE |
|
|
|
mailed 9-11-18
|
Third Notice | | 7/15/2018 | 8/7/2018 | | DONE |
|
|
|
mailed 8-10-18
|
Second Notice | | 6/21/2018 | 7/10/2018 | | DONE |
|
|
|
mailed 7-11-18
|
First Notice | | 5/27/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Print Occupancy Form | | | 5/17/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/17/2018 | | DONE |
|
|
|
|
BLD-Final | 5/16/2018 | 5/16/2018 | 5/16/2018 | P | PASS |
Mike Jordan
|
|
|
shell and core permit Bld17-01449 is finaled, modifiations are done // Bruce Rolfe Phone #: ###-####. Ok for perm occ. No card to sign.
|
BLD-Final | 5/14/2018 | 5/15/2018 | 5/15/2018 | A | CANC |
Mike Jordan
|
|
|
Derek Phone #: ###-####. Will reschedule.
|
FIRE-Final Inspection | 5/14/2018 | 5/14/2018 | 5/14/2018 | P | PASS |
Jim Page
|
|
|
Exit discharge light is installed at main entry, final life fire safety inspection complete.
Derek Phone #: ###-####
|
Telephone call | | | 5/14/2018 | | DONE |
|
|
|
called Derek to let know temp c of o expires soon-he scheduled the 2 finals needed to close permit out
|
BLD-Aging Inspection | 4/18/2018 | 4/18/2018 | 4/18/2018 | | PEND |
Mike Jordan
|
|
|
|
BLD-Final | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PART |
Jim Sly
|
|
|
Bruce Phone #: ###-#### OK for Temp Occ. OK for Perm Occ .When Architect submits drawing to the city which includes new double door installed in CMU wall East end. Installation appears to be typical of other new doorways installed in CMU wall per Architect/Engineer, Fire signs off for Perm Occ. and Building Exterior store front is completed.
|
FIRE-Final Inspection | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given until the exit discharge light is installed at the main exit.
Bruce Phone #: ###-####
|
Temporary Occupancy | 2/16/2018 | 5/17/2018 | 2/16/2018 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JG) | 2/14/2018 | 2/14/2018 | 2/16/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod Idaho Youth Ranch ePlan
|
Routing - PLAN CHECK | 2/15/2018 | | 2/16/2018 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 2/16/2018 | | DONE |
|
|
|
DO NOT REISSUE, plan mod fees due
|
CHANGE STATUS TO (ISS) | | | 2/16/2018 | | DONE |
|
|
|
|
BLD-Final | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | NR |
Mike Jordan
|
|
|
Late afternoon - Bruce Phone #: ###-####
|
FIRE-Final Inspection | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | CANC |
Troy Cobbley
|
|
|
Plans are still in review
Late afternoon - Bruce Phone #: ###-####
|
Routing - Design Review | 2/15/2018 | | 2/15/2018 | | PASS |
Sarah Schafer
|
|
|
|
Plan Modification Accepted | | | 2/14/2018 | | DONE |
|
|
|
Plan modification started for change in masonry door opening.
|
FIRE-Final Inspection | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | CANC |
Troy Cobbley
|
|
|
Hugo Phone #: ###-####
|
FIRE-Final Inspection | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguisher on the mezzanine, provide a exit discharge light at the main exit, provide double door with panic hardware at the rear exit as per the T.I. plans
Hugo Phone #: ###-####
|
BLD-Other | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | FAIL |
Mike Jordan
|
|
|
CMU // Hugo Phone #: ###-####. New openings in interior CMU walls not done per approved plans and engineering. engineer of record to accept in place work and provide letter or provide approved fix or have in place work removed and installed per the approved drawings. Correction notice issued.
|
Plan assigned to (JG) | 12/1/2017 | 12/1/2017 | 1/3/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, Plan Mod Idaho Youth Ranch ePlan
|
Routing - PLAN CHECK | 12/20/2017 | | 1/3/2018 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 1/3/2018 | | DONE |
|
|
|
Need - all met
GC Form
Revised Cert of Value
|
Issue PAID IN FULL permit | | | 1/3/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/3/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/8/2017 | | 12/12/2017 | | FAIL |
Javier Guzman
|
|
|
|
Plan Reviewer's activity | | | 12/7/2017 | | DONE |
Javier Guzman
|
|
|
Plan Modification not accepted due to a completed plan modification #522 application not uploaded
|
Plan resubmittals received | | | 12/1/2017 | | DONE |
|
|
|
started new workflow for plans in RDY status (never issued). Resubmittal to delete half wall at receiving and add three new egress doors at office/break room
|
Routing - FIRE | 8/31/2017 | 8/31/2017 | 9/12/2017 | | PASS |
Scott Arellano
|
|
|
Attached plan review to case.
|
Plan assigned to (JG) | 8/17/2017 | 8/17/2017 | 9/12/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 8/23 L1 Idaho Youth Ranch TI ePlan, pend fire
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/12/2017 | | DONE |
|
|
|
Need:
Revised Value
GC form
|
Route to Impact Fee Review | 8/30/2017 | 9/2/2017 | 8/31/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/31/2017 | | 8/31/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 8/17/2017 | 8/17/2017 | 8/30/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed plan review report to architect. Attached report to case.
|
1st review completed | | | 8/30/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Design Review | 8/17/2017 | | 8/24/2017 | | PASS |
Sarah Schafer
|
|
|
|
Routing - PLAN CHECK | 8/17/2017 | | 8/24/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 8/17/2017 | | 8/17/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/17/2017 | | 8/17/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 8/17/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen approved by Julie
|
Application received | | | 8/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2017 11:47PM
|