Second Notice | | 11/8/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | | 10/3/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1
|
Permanent Occupancy | | | 9/23/2019 | | DONE |
|
|
|
|
BLD-Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PASS |
Tell Riley
|
|
|
Russ Phone #: ###-####//final is complete//landscaping is done//public works signed off//no sign off sheet onsite//
|
PubWorks Occupancy Approval | 9/19/2019 | 9/19/2019 | 9/19/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 9/16/2019 | 9/16/2019 | 9/16/2019 | | PASS |
Tell Riley
|
|
|
working on landscaping
|
Temporary Occupancy | 8/12/2019 | 11/10/2019 | 8/12/2019 | | DONE |
Candy A. Nichols
|
|
|
|
PubWorks Temp Occupancy Appr | 8/12/2019 | 8/12/2019 | 8/12/2019 | | DONE |
Mike Sheppard
|
|
|
|
BLD-Final | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PART |
Tell Riley
|
|
|
Troy is here now. Phone #: ###-#### Inspection requested via web by Russell Valline//temp Occupancy ok//needs landscape complete and public works sign offs//
|
FIRE-Final Inspection | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety is passed.. Phone #: ###-#### Inspection requested via web by Russell Valline
|
CHANGE STATUS TO (ISS) | | | 7/12/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/2/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 6/18/2019 | 6/18/2019 | 7/2/2019 | | DONE |
Julie Romig
|
|
|
07/02 - Plan Mod 2 Fairmont High Gym
|
Routing - PLAN CHECK | 6/26/2019 | | 7/2/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - PUBLIC WORKS | 6/26/2019 | | 7/2/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 6/26/2019 | | 7/2/2019 | | PASS |
Tom Marshall
|
|
|
No review required per ePlanReview comments by TDM.
|
Permit Ready to Issue | | | 7/2/2019 | | DONE |
|
|
|
PLAN MOD
please do not re issue
|
Routing PW Drainage | 6/26/2019 | | 6/27/2019 | | PASS |
Brian Murphy
|
|
|
|
Telephone call | | | 6/27/2019 | | DONE |
|
|
|
Ed called me to see what fees were do for the plan mod-called him back- left message on his phone. We can't give him the amount because all the plan reviews have not be completed
|
Routing - FIRE | 6/26/2019 | 6/26/2019 | 6/26/2019 | | PASS |
Erika Akin
|
|
|
No impact to previous comments
|
Routing - Erosion and Sediment | 6/26/2019 | | 6/26/2019 | | PASS |
Michael Zawacki
|
|
|
Plan Mod Fairmont
|
Plan Modification Accepted | | | 6/18/2019 | | DONE |
|
|
|
2nd plan mod-Add light duty asphalt paving for basketball courts on East side of new cafereria building with 3 basketball standards and half-court striping. Modification to grading with added swale to East side of new basketball courts. Landscaping and irrigation are modified to accommodate new areas of paving.
|
BLD-Framing/Rough-in | 4/6/2019 | 4/8/2019 | 4/9/2019 | P | PART |
Jim Sly
|
|
|
enter on west side of the Building please see Russ thank you. Phone #: ###-#### Inspection requested via web by Russell Valline Framing....hard lid ceilings ....Locker rooms....plus......
|
BLD-Final | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Dave Hannah
|
|
|
come late morning we have fire in morning also thank you. Phone #: ###-#### Inspection requested via web by Russell Valline kitchen and lunch room area ok for temp occ
|
FIRE-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for Phase 1.
Inspection requested via web by Russell Valline
|
BLD-Final | 3/20/2019 | 3/21/2019 | 3/21/2019 | P | NR |
Jim Sly
|
|
|
Please come a little later Jim working on other inspections all day thanks Inspection requested via web by Russell Valline Need to have Ron Hills Letter for Phased Occupancy on site for next inspection. Need Fire Temp. Occ. approval.
|
FIRE-Final Inspection | 3/20/2019 | 3/21/2019 | 3/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm, fire sprinkler and hood suppression permits addressed. Need occupant load signs as discussed and fire dept access signage for the parking lot on the north side of the new building. Neeed determination of ADA requirements for the manual pull for the hood suppression system.
Please try to come early afternoon working on other inspections.
thanks s Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Ceiling Grid Inspection | 3/17/2019 | 3/18/2019 | 3/18/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline,, cloud in lunch room,, storage for kitchen, entry ok after trades are passed
|
FIRE-Conference | 3/17/2019 | 3/18/2019 | 3/18/2019 | A | DONE |
Troy Cobbley
|
|
|
I went over general life safety items with Russell. There were no small documents on site. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Ceiling Grid Inspection | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Conference | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | DONE |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline
|
FIRE-Conference | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | DONE |
Troy Cobbley
|
|
|
Russel and I spoke about temp. occupancy requirements and exit paths. I deferred him to Ron Hill in project management. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Framing/Rough-in | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline kitchen/caff.cooller/closets/restarmms/hall/mez surround framing ok ceillings ok
|
BLD-Concrete | 9/13/2018 | 9/14/2018 | 9/14/2018 | P | PASS |
Jim Storey
|
|
|
We are grouting our first lift tomorrow if you wanted to see. grout truck will be here at 2:00 All west will be here testing and inspecting. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Foundation | 8/20/2018 | 8/21/2018 | 8/21/2018 | P | PASS |
Jim Sly
|
|
|
All West is the Third party inspctor Phone #: ###-#### Inspection requested via web by Russell Valline OK pending Allwest special inspections,tests and approvals.
|
FIRE-Final Inspection | 8/14/2018 | 8/17/2018 | 8/17/2018 | P | PART |
Jim Page
|
|
|
Final life fire safety inspection for remodeled parking lot complete.
This is for the parking lot only Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Conference | 7/26/2018 | 7/27/2018 | 7/30/2018 | P | DONE |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Footing | 7/26/2018 | 7/27/2018 | 7/30/2018 | P | DONE |
Jim Sly
|
|
|
These are interior footings we do have Allwest 3rd party inspection also Inspection requested via web by Russell Valline OK pending Allwest special inspections, tests and approvals.
|
BLD-Foundation | 7/20/2018 | 7/23/2018 | 7/23/2018 | A | PASS |
Jim Sly
|
|
|
Jim just talk to you about this job and you explained as long Phone #: ###-#### Inspection requested via web by Russell Valline OK pending Allwest special inspections tests and approvals.
|
BLD-Footing | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline OK......pending Allwest special inspections, tests and approvals.
|
BLD-Footing | 7/11/2018 | 7/13/2018 | 7/12/2018 | A | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline Allwest will be special inspection.
|
OVERRIDE | | | 5/29/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 5/10/2018 | 5/10/2018 | 5/29/2018 | | DONE |
Julie Romig
|
|
|
*05/23 - Fairview Jr. High Plan Modification
|
Print Occupancy Form | | | 5/29/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/29/2018 | | DONE |
|
|
|
PLAN MOD
|
Routing Off Site - STRUCTURAL | 5/11/2018 | | 5/29/2018 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 5/29/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
Routing - Erosion and Sediment | 5/11/2018 | | 5/22/2018 | | PASS |
Michael Zawacki
|
|
|
RP needs valid Con # or to be registered in class before construction activities.
Site prep inspection required.
|
Routing - ELECTRICAL | 5/11/2018 | | 5/16/2018 | | PASS |
Daryl DeGrange
|
|
|
|
Routing - PLUMBING | 5/11/2018 | | 5/15/2018 | | PASS |
Bill VanDegrift
|
|
|
|
Routing PW Environmental | 5/14/2018 | | 5/15/2018 | | PASS |
Rick Christenson
|
|
|
No additional issues.
|
Routing - FIRE | 5/11/2018 | 5/11/2018 | 5/14/2018 | | PASS |
Erika Akin
|
|
|
|
Routing - PLANNING | 5/14/2018 | | 5/14/2018 | | PASS |
Celine Acord
|
|
|
per CUP18-00004 approved by NCW
|
Routing - PUBLIC WORKS | 5/11/2018 | | 5/14/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 5/11/2018 | | 5/14/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 5/11/2018 | | 5/14/2018 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 5/10/2018 | | DONE |
|
|
|
plan mod workflow started to update plans
|
Issue PAID IN FULL permit | | | 5/7/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/7/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/25/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 3/24/2018 | 3/24/2018 | 4/25/2018 | | DONE |
Julie Romig
|
|
|
*1st Rev Comp - 2nd Rec'd 04/16 - 502 Fairmont Junior High
|
Routing Off Site - STRUCTURAL | 4/16/2018 | | 4/25/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/25/2018 | | DONE |
|
|
|
met
Need
GC Form
Revised Cert of Value
RP
|
Routing - PLAN CHECK | 4/16/2018 | | 4/20/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing - FIRE | 4/16/2018 | 4/16/2018 | 4/18/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Routing - PLUMBING | 4/16/2018 | | 4/18/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Environmental | 4/16/2018 | | 4/17/2018 | | PASS |
Terry Alber
|
|
|
Kitchen plumbing rerouted per Pretreatment.
|
Route to Impact Fee Review | 4/5/2018 | 4/8/2018 | 4/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/5/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 3/24/2018 | | 4/5/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 3/24/2018 | | 4/4/2018 | | FAIL |
Julie Romig
|
|
|
Plan Review Report emailed to Architect.
|
Routing - PLUMBING | 3/24/2018 | | 3/30/2018 | | FAIL |
Bill VanDegrift
|
|
|
1) kitchen sink and dishwasher must be piped to the grease waste
2) vent required downstream of the interceptor
|
Routing - FIRE | 3/24/2018 | 3/24/2018 | 3/29/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments and emailed architect
|
Routing PW Environmental | 3/26/2018 | | 3/29/2018 | | FAIL |
Terry Alber
|
|
|
ALL drains in kitchen, including dishwasher, need to reroute through grease interceptor. Please resubmit corrected plumbing plans.
|
Routing PW Drainage | 3/26/2018 | | 3/28/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 3/24/2018 | | 3/28/2018 | | PASS |
Troy James
|
|
|
|
Routing - ELECTRICAL | 3/24/2018 | | 3/28/2018 | | PASS |
Daryl DeGrange
|
|
|
|
Routing PW Street Lights | 3/26/2018 | | 3/27/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PUBLIC WORKS | 3/24/2018 | | 3/27/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 3/24/2018 | | 3/26/2018 | | PASS |
Michael Zawacki
|
|
|
RP needs valid Con # or to be registered in class before construction activities.
Site prep inspection required.
|
Routing PW Sewer Design | 3/26/2018 | | 3/26/2018 | | PASS |
DeAnn Brown
|
|
|
Project is located in West Boise Sewer District. Comply with West Boise Sewer District requirements. The Boise City sewer notes on the plan are an outdated version. Find the update here: https://publicworks.cityofboise.org/development-permits-or-requirements/sanitary-sewer-notes/
|
Routing PW Solid Waste | 3/26/2018 | | 3/26/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLANNING | 3/24/2018 | | 3/26/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 3/24/2018 | | 3/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 3/24/2018 | | PASS |
|
|
|
|
Application received | | | 3/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 16 2018 1:11PM
|