Print Occupancy Form | | | 5/14/2019 | | DONE |
|
|
|
|
Meeting | | | 5/14/2019 | | DONE |
|
|
|
Per Josh Wilson no zoning inspection required for occupancy.
|
Permanent Occupancy | | | 5/14/2019 | | DONE |
|
|
|
|
BLD-Final | 4/30/2019 | 5/1/2019 | 5/1/2019 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need the fire alarm permit finaled. Kevin Phone #: ###-####
|
BLD-Final | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | CANC |
Mike Jordan
|
|
|
Kevin Phone #: ###-####
|
BLD-Conference | 4/3/2019 | 4/3/2019 | 4/3/2019 | A | PEND |
Jim Storey
|
|
|
open fire permit/ smokeseals verified ok on bld c/n
|
BLD-Final | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PART |
Jim Storey
|
|
|
Dave Phone #: ###-#### need s ratting for smoke leakage at doors.
|
Print Occupancy Form | | | 1/30/2019 | | DONE |
|
|
|
|
BLD-Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | CANC |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PART |
Mike Jordan
|
|
|
Ok to occupy/use pedistrian walkway. Will be ok for final once fire signs off perm.
|
FIRE-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PART |
Troy Cobbley
|
|
|
Life safety for the Link is passed. Dave is going to place fire extinguishers at both ends of the Link. An additional stobe is needed at the Building 36 (LOBBY) end of the link. I spoke to Ron with Boise Fire about this. A separate permit will be needed for this work.
dave Phone #: ###-####
|
BLD-Final | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | CANC |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | FAIL |
Jim Page
|
|
|
Pedestrian link between 36 and 37 not ready for inspection.
Dave Phone #: ###-####
|
BLD-Final | 12/10/2018 | 12/14/2018 | 12/14/2018 | A | CANC |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Moved to pm.
|
BLD-Final | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | PART |
Mike Jordan
|
|
|
Please call Chris - Phone #: ###-#### Inspection requested via web by Chris Fuhrman. Pending mech. inspection.
|
BLD-Framing/Rough-in | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PART |
Jim Storey
|
|
|
exterior walls ok to cover
|
BLD-Footing | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PART |
Jim Storey
|
|
|
concrete at noon // Dave Perkins Phone #: ###-#### placed with si/ ppending reports
|
Fees Due Hold | 7/10/2018 | | 7/10/2018 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 5/14/2018 | 5/14/2018 | 7/9/2018 | | PASS |
Carl D Madsen
|
|
|
Micron Ped Link
|
Routing - PLANNING | 5/16/2018 | | 7/9/2018 | | PASS |
Carl D Madsen
|
|
|
Signed off per Eplan Susan Riggs
|
Routing - PLAN CHECK | 6/29/2018 | | 7/9/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 6/29/2018 | | 7/9/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/9/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED CERT
|
Issue PAID IN FULL permit | | | 7/9/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/9/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/23/2018 | 6/26/2018 | 6/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - STRUCTURAL | 5/16/2018 | | 6/23/2018 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/23/2018 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/16/2018 | | 6/23/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 5/16/2018 | 5/16/2018 | 6/5/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 5/16/2018 | | 5/23/2018 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 5/16/2018 | | 5/21/2018 | | PASS |
Sarah Schafer
|
|
|
|
Routing - Erosion and Sediment | 5/16/2018 | | 5/18/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan reviewed and ESC permit issued with GRD17-00087. See ESC18-00006. No duplicate ESC permit required.
|
Routing - Addressing | 5/16/2018 | | 5/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/16/2018 | | 5/17/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Drainage | 5/17/2018 | | 5/17/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 5/16/2018 | | 5/17/2018 | | PASS |
Bill VanDegrift
|
|
|
roof drainage
|
Recd Pcfee & Taken To Pln CK | | | 5/16/2018 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2018 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/14/2018 | | PASS |
Carl D Madsen
|
|
|
|
Intake Approval | | | 5/8/2018 | | FAIL |
Michael Hanson
|
|
|
Sending this back as 5 electrical files errored during upload. Please see drawing folder and re-upload the sheets effected.
|
Application received | | | 5/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2018 6:04AM
|