Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberBLD18-03245
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 2909 W ELDER ST
Project NameBoise Airport Hotel
Customer Number 
ePlanReviewYes
Description
(SIMPLE SUITES – NEW BUILDING) (DRH18-00305) (2-25-20 PLAN MODIFICATION TO RELOCATE THE GAS METER AND PIPING TO THE END OF THE BUILDING, ALTER THE WATER PIPE INSULATION AND HANGERS, AND TO RECONFIGURE THE GYPSUM BOARD MEMBRANE OF THE 1-HR FIRE-RESISTANCE-RATED FLOOR-CEILING ASSEMBLY BETWEEN THE 1ST STORY AND THE 2ND STORY ABOVE THE 1ST STORY SINGLE-USER TOILET ROOMS SO THAT THE REQUIRED EXHAUST DUCT OPENING PROTECTION CAN BE RELOCATED TO THE CEILING OF THE DROPPED CEILING. THE GAS LINE IS NOT ALLOWED TO PASS THROUGH THE 2-HR STAIRWAY ENCLOSURE. A 2-HR SHAFT WILL BE CONSTRUCTED AROUND THE GAS PIPE TO ISOLATE IT FROM THE STAIRWAY ENCLOSURE.) The fire sprinkler system is used for building area increase, for occupancy, and for code trade-offs. To construct a new 4 story wood framed hotel building having a total floor area of about of about 36,640 square feet (9,490 square feet 1st story, 9,050 square feet 2nd story, 9,050 square feet 3rd story, and 9,050 square feet 4th story) with 67 hotel sleeping units with 4 of those units accessible to the disabled (1 with an accessible roll-in type shower and 3 with accessible bathtubs). Work is to include concrete continuous footings, concrete spot footings, concrete spot footings with concrete piers for the steel canopy, concrete stem walls, concrete slab on grade with thickened areas for bearing and shear walls, steel columns with steel baseplates, wood stud bearing walls, wood stud shear walls with hold downs, steel beams, wood beams, floors constructed of TJI joists and wood floor sheathing, 1” gypcrete floor topping, flat wood roof trusses (design is a deferred submittal item) with wood roof sheathing, roof parapet braces, steel joists and a steel deck for the canopy, 2-hr stairway enclosures, 2-hr elevator shaft with a concrete pit, 24” diameter laundry chute within a 2-hr shaft with 90 minute automatic-closing access doors, 2-hr laundry chute termination room, 1-hr laundry chute access rooms with 45 minute doors, 1-hr corridors, exterior fixed windows, exterior doors, interior doors, steel exterior awnings with steel support rods, exterior wall fur-outs, EIFS, fiber cement siding, stacked stone veneer with precast concrete caps, exterior concrete steps with handrails to access the fire riser room and equipment rooms, millwork, and interior finishes. A trash enclosure with 8’- 8” masonry walls and steel gates will also be constructed. Special Inspection is required for soils, for concrete, for steel (including welding and bolting), for post-installed anchors in hardened concrete, for EIFS, and for intumescent fire-resistant coatings. Each hotel sleeping room will be served by its own PTAC unit and exhaust fan with a dedicated exhaust duct. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Class I standpipes are required. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 4/9/20205/5/2020 DONE
This permit finaled on the web by Samantha Tallman
Permanent Occupancy  3/30/2020 DONE
BLD-Final3/26/20203/27/20203/27/2020APASS
DetailsJim Storey
josh Phone #: ###-####
FIRE-Final Inspection3/26/20203/27/20203/27/2020APASS
DetailsTroy Cobbley
Life safety passed. Boise Fire is ok with emergency radio.

josh Phone #: ###-####
FIRE-Final Inspection3/26/20203/26/20203/26/2020PFAIL
DetailsTroy Cobbley
Repair east end exit discharge light, tidy up the wiring and install ceiling on both the 3rd and 4th floors, provide verification from the fire dept that the emergency radio coverage is acceptable, provide signage on the fire doors

josh Phone #: ###-####
BLD-Final3/19/20203/20/20203/20/2020APART
DetailsJim Storey
Robbie Phone #: ###-#### temp occ ok
BLD-Ceiling Grid Inspection3/10/20203/11/20203/11/2020APASS
DetailsJim Storey
Robbie Phone #: ###-####
BLD-Ceiling Grid Inspection3/6/20203/9/20203/9/2020APASS
DetailsJim Storey
Robbie Phone #: ###-#### lobby and 2nd floor ok
Zoning Approval3/5/20203/5/20203/5/2020 PASS
DetailsKatelyn Menuge
PubWorks Occupancy Approval3/3/20203/3/20203/3/2020 DONE
DetailsTiffany Lowery
OVERRIDE  2/25/2020  
Plan assigned to (CJW)2/5/20202/5/20202/25/2020 PASS
DetailsCarl Westfall
plan mod (Simple Suites) (routed to staff)
CHANGE STATUS TO (ISS)  2/25/2020 DONE
Plan Reviewer's activity  2/25/2020 PASS
Plan modification approved
Permit Ready to Issue  2/25/2020 DONE
plan mod approved - DO NOT RE ISSUE
Plan resubmittals requested  2/24/2020 DONE
Plan resubmittals received  2/24/2020 DONE
Routing - PLAN CHECK2/24/2020 2/24/2020 PASS
DetailsCarl Westfall
Routing - MECHANICAL2/24/2020 2/24/2020 PASS
DetailsTroy James
Routing - PLUMBING2/24/2020 2/24/2020 PASS
DetailsDan Ediger
Per plans and ISPC
Routing - PLUMBING2/19/2020 2/21/2020 FAIL
DetailsDan Ediger
Engineer stamp not signed and dated.
BLD-Framing/Rough-in2/19/20202/20/20202/20/2020PPASS
DetailsJim Storey
late if possible - Robbie Phone #: ###-#### 1st floor ok
Routing - MECHANICAL2/19/2020 2/20/2020 FAIL
DetailsTroy James
Engineer stamp to be signed and dated.
BLD-Framing/Rough-in2/18/20202/19/20202/19/2020APASS
DetailsJim Storey
Robbie Phone #: ###-#### rooms ceillings 1 st floor ok to cover.
Routing - PLAN CHECK2/18/2020 2/19/2020 PASS
DetailsCarl Westfall
Plan resubmittals received  2/18/2020 DONE
Plan resubmittals requested  2/13/2020 DONE
Routing - PLUMBING2/10/2020 2/12/2020 FAIL
DetailsDan Ediger
See eplan
Routing - MECHANICAL2/10/2020 2/10/2020 FAIL
DetailsTroy James
See eplan
Routing - PLAN CHECK2/5/2020 2/10/2020 PASS
DetailsCarl Westfall
The plan mod came in late on a Wednesday before the Plans Examiner was to be out of the office for 2 days. The project was routed on Monday after he returned to the office. A 2-hr shaft will isolate the gas line from the stairway enclosure.
Plan Modification Accepted  2/5/2020 DONE
plan mod submitted by Alex Dahl of The Richardson Design Partnership, llc. 1. relocating the Gas meter and piping to end of building.
2. Altering Water Pipe insulation and hanger requirements.
3. moving floor assembly membrane rating location from floor to drop ceiling in rooms 136 & 135
Construction documents submitted: A006, A030, P101, Rated Section Drawing, Engineering alternative letterof approval for insulation change with updated hanger
specs, engineering alternative letter of approval for gas meter location change, RFI #30 Response Letter.
BLD-Framing/Rough-in1/2/20201/3/20201/3/2020APART
DetailsJim Storey
Robbie Phone #: ###-#### east 1st floor ceillings abs and ele conduit collors and firestopping/
BLD-Framing/Rough-in12/6/201912/9/201912/9/2019APASS
DetailsJim Storey
Robbie Phone #: ###-#### shaft and elavtor ok
BLD-Framing/Rough-in12/3/201912/4/201912/4/2019ACANC
DetailsJim Storey
elevator shaft // Robbie Phone #: ###-####
BLD-Framing/Rough-in12/3/201912/3/201912/3/2019PCANC
DetailsJim Storey
Robbie Phone #: ###-####
BLD-Framing/Rough-in12/2/201912/3/201912/3/2019ADEFR
DetailsJim Storey
Robbie Phone #: ###-####
BLD-Framing/Rough-in11/14/201911/15/201911/15/2019PPASS
DetailsJim Storey
Josh Phone #: ###-#### 1st floor rms
BLD-Framing/Rough-in11/12/201911/13/201911/13/2019APASS
DetailsJim Storey
Josh Phone #: ###-#### c/n idems all complet ok to cover 3rd all of 4 th/ pending storage rms 1st 2nd and third.
BLD-Framing/Rough-in11/8/201911/12/201911/12/2019APART
DetailsJim Storey
josh Phone #: ###-#### shaft 4th floor ok to cover rm side// 2nd floor ok all but 3 inch hvac pvc collors required.
BLD-Framing/Rough-in11/6/201911/7/201911/7/2019APASS
DetailsJim Storey
Josh Phone #: ###-####//east 2nd floor/west 3rd floor ok to cover.
BLD-Energy code compliance11/6/201911/7/201911/7/2019APASS
DetailsJim Storey
Josh Phone #: ###-#### east 2nd floor/west 3rd floor ok to cover.
BLD-Energy code compliance11/4/201911/5/201911/5/2019PPASS
DetailsJim Storey
Josh Phone #: ###-#### 3thjird pass
BLD-Framing/Rough-in11/1/201911/4/201911/4/2019APASS
DetailsJim Storey
Josh Phone #: ###-#### east 3dr ok
BLD-Wall cover11/1/201911/4/201911/4/2019APASS
DetailsJim Storey
rc channel // Josh Phone #: ###-#### all of 4th floor and east of shaft on third ok to cover
BLD-Energy code compliance11/1/201911/4/201911/4/2019APASS
DetailsJim Storey
Josh Phone #: ###-#### all of 4th floor and east of shaft on third ok to cover
BLD-Energy code compliance10/30/201910/31/201910/31/2019APASS
DetailsJim Storey
Robbie Phone #: ###-#### east of shaft 4th floor ok
BLD-Energy code compliance10/24/201910/25/201910/25/2019APART
DetailsJim Storey
Robbie Phone #: ###-#### 3rd floor exrerior walls ok to cover to rm short of elavator.
BLD-Framing/Rough-in10/22/201910/23/201910/23/2019APASS
DetailsJim Storey
Robie- 3rd 4th floor east side bulding Phone #: ###-#### mlb support.
BLD-Energy code compliance10/22/201910/23/201910/23/2019APART
DetailsJim Storey
Robie Phone #: ###-#### east end exterior walls and unit walls ok to insulate 4th and 3 rd floors// hold at 2 hr elavator and lundry shaft need to rock and firestop to roof deck/hangers firestoped membrane continuity.
BLD-Wall cover10/17/201910/18/201910/18/2019APART
DetailsJim Storey
Robbie Phone #: ###-#### ok to insulate exterior and coridors// remove ceilling at elavator and lundry shaft/ plm void ceilling drain line/ check for collor spacing/ remove ceilling at water closet east cordor closet.
BLD-Framing/Rough-in10/7/201910/7/201910/7/2019PPASS
DetailsJim Storey
stair well.. r-c channel // Robbie Phone #: ###-#### // stairwells pending fire spk ok to cover// front canopy ok to cover// rc ceilling common area 1st floor ok to cover.
BLD-Framing/Rough-in10/2/201910/3/201910/3/2019PPART
DetailsJim Storey
Robbie Phone #: ###-#### 1st floor common area ok to start ceillings and walls pending reinsp. 2hr shafts elavator and lurndry chase // plm water closet fire stop/ hvac ducts at ceilling/ pending fire stopping applacation listting.
Plan Reviewer's activity  10/3/2019 DONE
(10-3-19) Changed the name from "Boise Airport Hotel" to "Simple Suites" at the request of Dave Jeffs, Burgess Investment Group. CJW
BLD-Conference9/25/20199/26/20199/26/2019PDONE
DetailsMike Jordan
Discuss plumbing penetrations in fire rated walls. if possible could we request a time window to have plumber on site. Phone #: ###-#### Inspection requested via web by Robbie Andrews. OK to insulate 2nd floor at common area only. Provide listings for 3m fire foam for use on pex.
BLD-Energy code compliance8/19/20198/20/20198/20/2019APASS
DetailsMike Jordan
ROBBIE Phone #: ###-####. Insulation at elevator shaft. Ok to start sheet rock on interior side.
BLD-Energy code compliance8/7/20198/8/20198/8/2019APART
DetailsJim Storey
Robby Phone #: ###-#### roof deck exterior foam ok/ spray foam and r 19 glass pending interior/ hat track in corridors all floors ok to rock// pending steel fire protection.
BLD-Other8/1/20198/2/20198/2/2019APASS
DetailsJim Storey
Roof Framing // Robbie Andrews Phone #: ###-#### nailling ok/ truss bracing ok.
BLD-Framing/Rough-in7/29/20197/29/20197/30/2019PPART
DetailsDave Hannah
ext sheeting and elevator shaft // Robbie Phone #: ###-#### ext shear nailing and fl/fl straping ok to cover also ok to rock elev shaft after addind strapes at plate lines were steel tubes go though plates
BLD-Wall cover6/25/20196/26/20196/26/2019APART
DetailsJim Storey
Rob Phone #: ###-#### west 1st floor 2 hr wall ok to place aganst sheer wall.gyp screws ok
BLD-Concrete5/15/20195/16/20195/16/2019APASS
DetailsJim Storey
rebar- Josh Phone #: ###-#### vapor barrior and rebar ok/pending si report
BLD-Foundation4/10/20194/11/20194/11/2019APASS
DetailsJim Storey
rebar and stem wall- Josh Phone #: ###-####
BLD-Footing4/3/20194/4/20194/4/2019PPART
DetailsJim Storey
Josh Phone #: ###-#### wip rebar ok/ si pending si contract needed/ grin g/ 1 thur 12/a
Telephone call  2/28/2019 DONE
left a message for tom andrews informing this permit is going to expire in 5 days and recommended to send in a request for an extension, review went a bit longer.
Meeting  2/28/2019 DONE
wright brothers came in to pick up permit saying they got a call it was ready. informed there are still fees due and i called to recommend sending in a request for an extension if they don't believe the fees will be paid by 3/4/19
Issue PAID IN FULL permit  2/28/2019 DONE
Print Occupancy Form  2/28/2019 DONE
Meeting  2/25/2019 DONE
sent email to peter informing permit is going to expire in 7 days. see documents
Meeting  2/25/2019 DONE
emailed aaron informing the fee amount w/achd and that a letter from achd is still needed
OVERRIDE  2/13/2019  
Plan assigned to (CJW)9/13/20189/13/20182/13/2019 PASS
DetailsCarl Westfall
(3rd done) 10/17/18 (new - 25 days) (ePlan - 145 sheets) Boise Airport Hotel (passed and routed to staff)
Routing - PLUMBING2/12/2019 2/13/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
PLANS/APPL TAKEN TO FRONT DESK  2/13/2019 DONE
Permit Ready to Issue  2/13/2019 DONE
met
NEED
ACHD
MET
RP
GC FORM
REVISED VALUE
Plan resubmittals received  2/12/2019 DONE
Routing - PLAN CHECK2/12/2019 2/12/2019 PASS
DetailsCarl Westfall
Plan resubmittals requested  2/6/2019 DONE
Routing - Design Review1/30/2019 2/5/2019 PASS
DetailsAndrea Tuning
Routing PW Drainage1/30/2019 1/30/2019 PASS
DetailsBrian Murphy
Move approval stamp to latest version of C2.0
Routing - PLAN CHECK1/29/2019 1/30/2019 PASS
DetailsCarl Westfall
Completed the 3rd review. Drawings approved.
Routing - MECHANICAL1/30/2019 1/30/2019 PASS
DetailsTroy James
Routing - PLUMBING1/30/2019 1/30/2019 FAIL
DetailsDaryl Spivey
Waste and vent plumbing does not meet requirements of ISPC.
Plan resubmittals received  1/29/2019 DONE
DetailsCarl Westfall
Plan resubmittals requested  12/24/2018 DONE
Routing Off Site - STRUCTURAL12/14/2018 12/24/2018 PASS
DetailsCarl Westfall
Jordan Terry (KPFF)
Routing - MECHANICAL12/14/2018 12/19/2018 FAIL
DetailsTroy James
Routing - PLAN CHECK12/10/2018 12/14/2018 FAIL
DetailsCarl Westfall
Revised drawings required
Routing PW Solid Waste12/14/2018 12/14/2018 PASS
DetailsEvan Carpenter
Routing PW Drainage12/14/2018 12/14/2018 PASS
DetailsBrian Murphy
Routing Off Site - C.D.H12/14/2018 12/14/2018 PASS
DetailsCarl Westfall
Routed to Dinko at CDHD for review. He determined that no review was required.
Routing PW Sewer Design12/14/2018 12/14/2018 PASS
DetailsDeAnn Brown
Routing - PLUMBING12/14/2018 12/14/2018 FAIL
DetailsDaryl Spivey
Plumbing not approved. Not shown on plans as required by ISPC.
Routing - Design Review12/14/2018 12/14/2018 FAIL
DetailsAndrea Tuning
All pole lighting shall be located outside of the required setbacks.

The interior planter islands adjacent to the buildings main entrance shall contain a Class II tree. The proposed Columnar Sweetgum is not an approved species. Please consult the Boise Parks and Recreation Tree Planting Guide for an approved species.

The landscape plan is proposing to remove two large trees from the property to teh south. This is not approved. If the applicant would like to pursue this possibility, a separate Design Review application will be required. The request will then be reviewed through the Design Review process for appropriateness and mitigation. This proposal should be removed from this site.

The fire hydrant is also proposed to be located at the main entrance driveway. The fire hydrant location should be located outside of the area where the required tree is proposed to be planted.

All Mechanical units are required to be screened. The mechanical area along the south property line should include a screening proposal.
Routing - FIRE  12/13/2018 PASS
DetailsErika Akin
Attached revised comments to case
Plan resubmittals requested  12/10/2018 DONE
All uploaded "A" sheets were the wrong size. All uploaded "P" and "M" sheets were not signed. All uploaded "E" sheets were not stamped or signed. Resubmittal rejected. The above revised sheets deleted. Work flow sent back to the applicant to try again.
Plan resubmittals received  12/10/2018 DONE
Routing - PLAN CHECK12/6/2018 12/10/2018 FAIL
DetailsCarl Westfall
All uploaded "A" sheets were the wrong size. All uploaded "P" and "M" sheets were not signed. All uploaded "E" sheets were not stamped or signed. Resubmittal rejected. The above revised sheets deleted. Work flow sent back to the applicant to try again.
Plan resubmittals received  12/6/2018 DONE
Route to Impact Fee Review11/5/201811/8/201811/6/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE9/13/20189/13/201811/5/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
1st review completed  11/5/2018 DONE
Plan resubmittals requested  11/5/2018 DONE
Routing - PLAN CHECK9/13/2018 10/3/2018 FAIL
DetailsCarl Westfall
Revised drawings required
Routing Off Site - STRUCTURAL9/13/2018 10/1/2018 FAIL
DetailsCarl Westfall
Jordan Terry (KPFF)
Routing PW Drainage9/14/2018 9/25/2018 PASS
DetailsBrian Murphy
Routing - MECHANICAL9/13/2018 9/24/2018 FAIL
DetailsTroy James
Routing PW Environmental9/14/2018 9/20/2018 PASS
DetailsRick Christenson
Routing - Erosion and Sediment9/13/2018 9/17/2018 PASS
DetailsMichael Zawacki
RP needed prior to any ground disturbance. Site prep inspection required.
Routing - PLANNING9/13/2018 9/17/2018 PASS
DetailsDavid Moser
Routing - Addressing9/13/2018 9/17/2018 PASS
DetailsDoug Chausow
Routing PW Street Lights9/14/2018 9/17/2018 PASS
DetailsTom Marshall
Routing - Design Review9/13/2018 9/17/2018 FAIL
DetailsAndrea Tuning
DRH18-00305
All pole lighting shall be located outside of the required setbacks.

Provide a continuous pedstrian pathway to the bicycle parking. (You should not haev to carry your bike up a cur, through a landscape planter,etc.)

The interior planter islands adjacent to the buildings main entrance shall contain a Class II tree.

Install a second tree within the “double terminal planter” located in the northwest corner of the site.

The sidewalks on Elder Street shall be 7-feet wide the entire leghth of the property if they are attached. This will need to be unimpeded walkway. If this cannot be attained, the sidewalk shall be 5-feet in width and detached from the curb line by a minimum of 8-feet.

All interior sidewalks shall be 5-feet in width.

Recess the upper story windows a minimum of two inches from the façade. Cut sheets identifying this depth will be required prior to issuance of a building permit.

Provide full height screening for the mechanical units located on the site side of the building. The proposed screening method shall be reviewed and approved by the Design Review Division prior to issuance of a building permit.


Routing PW Sewer Design9/14/2018 9/14/2018 FAIL
DetailsDeAnn Brown
Add to note 10 on utility sheet and label manhole as shown in changemarks in eplanreview.
Routing PW Solid Waste9/14/2018 9/14/2018 FAIL
DetailsEvan Carpenter
The solid waste enclosure must have at least 18 feet of unobstructed clearance between gate posts (measured from the innermost points) for two dumpsters. A single 6- or 8-yard dumpster could be placed in the enclosure with no required changes.
Routing - PUBLIC WORKS9/13/2018 9/14/2018 PASS
DetailsMorgan Webb
Routing - PLUMBING9/13/2018 9/14/2018 FAIL
DetailsDaryl Spivey
Plumbing not installed per ISPC. All plumbing shall be installed as required by the Idaho State Plumbing Code.
Routing PW Sewer Rating9/14/2018 9/14/2018 PASS
DetailsMorgan Webb
Intake Approval  9/13/2018 PASS
Plans ACCEPTED BY PLAN TECH  9/13/2018 DONE
Recd Pcfee & Taken To Pln CK  9/13/2018 DONE
Intake Approval  9/7/2018 FAIL
DetailsMichael Hanson
This permit has failed prescreen due to the following:
1. Architectural sheets are missing signature and date on stamp.
2. City stamp space is missing from MEP and S drawings.
Application received  9/5/2018 DONE
Application submitted via PDS Online on Sep 5 2018 11:21AM