First Notice | | 4/9/2020 | 5/5/2020 | | DONE |
|
|
|
This permit finaled on the web by Samantha Tallman
|
Permanent Occupancy | | | 3/30/2020 | | DONE |
|
|
|
|
BLD-Final | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | PASS |
Jim Storey
|
|
|
josh Phone #: ###-####
|
FIRE-Final Inspection | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Boise Fire is ok with emergency radio.
josh Phone #: ###-####
|
FIRE-Final Inspection | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | FAIL |
Troy Cobbley
|
|
|
Repair east end exit discharge light, tidy up the wiring and install ceiling on both the 3rd and 4th floors, provide verification from the fire dept that the emergency radio coverage is acceptable, provide signage on the fire doors
josh Phone #: ###-####
|
BLD-Final | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | PART |
Jim Storey
|
|
|
Robbie Phone #: ###-#### temp occ ok
|
BLD-Ceiling Grid Inspection | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Jim Storey
|
|
|
Robbie Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/6/2020 | 3/9/2020 | 3/9/2020 | A | PASS |
Jim Storey
|
|
|
Robbie Phone #: ###-#### lobby and 2nd floor ok
|
Zoning Approval | 3/5/2020 | 3/5/2020 | 3/5/2020 | | PASS |
Katelyn Menuge
|
|
|
|
PubWorks Occupancy Approval | 3/3/2020 | 3/3/2020 | 3/3/2020 | | DONE |
Tiffany Lowery
|
|
|
|
OVERRIDE | | | 2/25/2020 | | |
|
|
|
|
Plan assigned to (CJW) | 2/5/2020 | 2/5/2020 | 2/25/2020 | | PASS |
Carl Westfall
|
|
|
plan mod (Simple Suites) (routed to staff)
|
CHANGE STATUS TO (ISS) | | | 2/25/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/25/2020 | | PASS |
|
|
|
Plan modification approved
|
Permit Ready to Issue | | | 2/25/2020 | | DONE |
|
|
|
plan mod approved - DO NOT RE ISSUE
|
Plan resubmittals requested | | | 2/24/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/24/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/24/2020 | | 2/24/2020 | | PASS |
Carl Westfall
|
|
|
|
Routing - MECHANICAL | 2/24/2020 | | 2/24/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/24/2020 | | 2/24/2020 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing - PLUMBING | 2/19/2020 | | 2/21/2020 | | FAIL |
Dan Ediger
|
|
|
Engineer stamp not signed and dated.
|
BLD-Framing/Rough-in | 2/19/2020 | 2/20/2020 | 2/20/2020 | P | PASS |
Jim Storey
|
|
|
late if possible - Robbie Phone #: ###-#### 1st floor ok
|
Routing - MECHANICAL | 2/19/2020 | | 2/20/2020 | | FAIL |
Troy James
|
|
|
Engineer stamp to be signed and dated.
|
BLD-Framing/Rough-in | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | PASS |
Jim Storey
|
|
|
Robbie Phone #: ###-#### rooms ceillings 1 st floor ok to cover.
|
Routing - PLAN CHECK | 2/18/2020 | | 2/19/2020 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 2/18/2020 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 2/13/2020 | | DONE |
|
|
|
|
Routing - PLUMBING | 2/10/2020 | | 2/12/2020 | | FAIL |
Dan Ediger
|
|
|
See eplan
|
Routing - MECHANICAL | 2/10/2020 | | 2/10/2020 | | FAIL |
Troy James
|
|
|
See eplan
|
Routing - PLAN CHECK | 2/5/2020 | | 2/10/2020 | | PASS |
Carl Westfall
|
|
|
The plan mod came in late on a Wednesday before the Plans Examiner was to be out of the office for 2 days. The project was routed on Monday after he returned to the office. A 2-hr shaft will isolate the gas line from the stairway enclosure.
|
Plan Modification Accepted | | | 2/5/2020 | | DONE |
|
|
|
plan mod submitted by Alex Dahl of The Richardson Design Partnership, llc. 1. relocating the Gas meter and piping to end of building.
2. Altering Water Pipe insulation and hanger requirements.
3. moving floor assembly membrane rating location from floor to drop ceiling in rooms 136 & 135
Construction documents submitted: A006, A030, P101, Rated Section Drawing, Engineering alternative letterof approval for insulation change with updated hanger
specs, engineering alternative letter of approval for gas meter location change, RFI #30 Response Letter.
|
BLD-Framing/Rough-in | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | PART |
Jim Storey
|
|
|
Robbie Phone #: ###-#### east 1st floor ceillings abs and ele conduit collors and firestopping/
|
BLD-Framing/Rough-in | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Jim Storey
|
|
|
Robbie Phone #: ###-#### shaft and elavtor ok
|
BLD-Framing/Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | CANC |
Jim Storey
|
|
|
elevator shaft // Robbie Phone #: ###-####
|
BLD-Framing/Rough-in | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | CANC |
Jim Storey
|
|
|
Robbie Phone #: ###-####
|
BLD-Framing/Rough-in | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | DEFR |
Jim Storey
|
|
|
Robbie Phone #: ###-####
|
BLD-Framing/Rough-in | 11/14/2019 | 11/15/2019 | 11/15/2019 | P | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### 1st floor rms
|
BLD-Framing/Rough-in | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### c/n idems all complet ok to cover 3rd all of 4 th/ pending storage rms 1st 2nd and third.
|
BLD-Framing/Rough-in | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PART |
Jim Storey
|
|
|
josh Phone #: ###-#### shaft 4th floor ok to cover rm side// 2nd floor ok all but 3 inch hvac pvc collors required.
|
BLD-Framing/Rough-in | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-####//east 2nd floor/west 3rd floor ok to cover.
|
BLD-Energy code compliance | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### east 2nd floor/west 3rd floor ok to cover.
|
BLD-Energy code compliance | 11/4/2019 | 11/5/2019 | 11/5/2019 | P | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### 3thjird pass
|
BLD-Framing/Rough-in | 11/1/2019 | 11/4/2019 | 11/4/2019 | A | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### east 3dr ok
|
BLD-Wall cover | 11/1/2019 | 11/4/2019 | 11/4/2019 | A | PASS |
Jim Storey
|
|
|
rc channel // Josh Phone #: ###-#### all of 4th floor and east of shaft on third ok to cover
|
BLD-Energy code compliance | 11/1/2019 | 11/4/2019 | 11/4/2019 | A | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### all of 4th floor and east of shaft on third ok to cover
|
BLD-Energy code compliance | 10/30/2019 | 10/31/2019 | 10/31/2019 | A | PASS |
Jim Storey
|
|
|
Robbie Phone #: ###-#### east of shaft 4th floor ok
|
BLD-Energy code compliance | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PART |
Jim Storey
|
|
|
Robbie Phone #: ###-#### 3rd floor exrerior walls ok to cover to rm short of elavator.
|
BLD-Framing/Rough-in | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Jim Storey
|
|
|
Robie- 3rd 4th floor east side bulding Phone #: ###-#### mlb support.
|
BLD-Energy code compliance | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PART |
Jim Storey
|
|
|
Robie Phone #: ###-#### east end exterior walls and unit walls ok to insulate 4th and 3 rd floors// hold at 2 hr elavator and lundry shaft need to rock and firestop to roof deck/hangers firestoped membrane continuity.
|
BLD-Wall cover | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | PART |
Jim Storey
|
|
|
Robbie Phone #: ###-#### ok to insulate exterior and coridors// remove ceilling at elavator and lundry shaft/ plm void ceilling drain line/ check for collor spacing/ remove ceilling at water closet east cordor closet.
|
BLD-Framing/Rough-in | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Jim Storey
|
|
|
stair well.. r-c channel // Robbie Phone #: ###-#### // stairwells pending fire spk ok to cover// front canopy ok to cover// rc ceilling common area 1st floor ok to cover.
|
BLD-Framing/Rough-in | 10/2/2019 | 10/3/2019 | 10/3/2019 | P | PART |
Jim Storey
|
|
|
Robbie Phone #: ###-#### 1st floor common area ok to start ceillings and walls pending reinsp. 2hr shafts elavator and lurndry chase // plm water closet fire stop/ hvac ducts at ceilling/ pending fire stopping applacation listting.
|
Plan Reviewer's activity | | | 10/3/2019 | | DONE |
|
|
|
(10-3-19) Changed the name from "Boise Airport Hotel" to "Simple Suites" at the request of Dave Jeffs, Burgess Investment Group. CJW
|
BLD-Conference | 9/25/2019 | 9/26/2019 | 9/26/2019 | P | DONE |
Mike Jordan
|
|
|
Discuss plumbing penetrations in fire rated walls. if possible could we request a time window to have plumber on site. Phone #: ###-#### Inspection requested via web by Robbie Andrews. OK to insulate 2nd floor at common area only. Provide listings for 3m fire foam for use on pex.
|
BLD-Energy code compliance | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Mike Jordan
|
|
|
ROBBIE Phone #: ###-####. Insulation at elevator shaft. Ok to start sheet rock on interior side.
|
BLD-Energy code compliance | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | PART |
Jim Storey
|
|
|
Robby Phone #: ###-#### roof deck exterior foam ok/ spray foam and r 19 glass pending interior/ hat track in corridors all floors ok to rock// pending steel fire protection.
|
BLD-Other | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | PASS |
Jim Storey
|
|
|
Roof Framing // Robbie Andrews Phone #: ###-#### nailling ok/ truss bracing ok.
|
BLD-Framing/Rough-in | 7/29/2019 | 7/29/2019 | 7/30/2019 | P | PART |
Dave Hannah
|
|
|
ext sheeting and elevator shaft // Robbie Phone #: ###-#### ext shear nailing and fl/fl straping ok to cover also ok to rock elev shaft after addind strapes at plate lines were steel tubes go though plates
|
BLD-Wall cover | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | PART |
Jim Storey
|
|
|
Rob Phone #: ###-#### west 1st floor 2 hr wall ok to place aganst sheer wall.gyp screws ok
|
BLD-Concrete | 5/15/2019 | 5/16/2019 | 5/16/2019 | A | PASS |
Jim Storey
|
|
|
rebar- Josh Phone #: ###-#### vapor barrior and rebar ok/pending si report
|
BLD-Foundation | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Jim Storey
|
|
|
rebar and stem wall- Josh Phone #: ###-####
|
BLD-Footing | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | PART |
Jim Storey
|
|
|
Josh Phone #: ###-#### wip rebar ok/ si pending si contract needed/ grin g/ 1 thur 12/a
|
Telephone call | | | 2/28/2019 | | DONE |
|
|
|
left a message for tom andrews informing this permit is going to expire in 5 days and recommended to send in a request for an extension, review went a bit longer.
|
Meeting | | | 2/28/2019 | | DONE |
|
|
|
wright brothers came in to pick up permit saying they got a call it was ready. informed there are still fees due and i called to recommend sending in a request for an extension if they don't believe the fees will be paid by 3/4/19
|
Issue PAID IN FULL permit | | | 2/28/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/28/2019 | | DONE |
|
|
|
|
Meeting | | | 2/25/2019 | | DONE |
|
|
|
sent email to peter informing permit is going to expire in 7 days. see documents
|
Meeting | | | 2/25/2019 | | DONE |
|
|
|
emailed aaron informing the fee amount w/achd and that a letter from achd is still needed
|
OVERRIDE | | | 2/13/2019 | | |
|
|
|
|
Plan assigned to (CJW) | 9/13/2018 | 9/13/2018 | 2/13/2019 | | PASS |
Carl Westfall
|
|
|
(3rd done) 10/17/18 (new - 25 days) (ePlan - 145 sheets) Boise Airport Hotel (passed and routed to staff)
|
Routing - PLUMBING | 2/12/2019 | | 2/13/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/13/2019 | | DONE |
|
|
|
met
NEED
ACHD
MET
RP
GC FORM
REVISED VALUE
|
Plan resubmittals received | | | 2/12/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/12/2019 | | 2/12/2019 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 2/6/2019 | | DONE |
|
|
|
|
Routing - Design Review | 1/30/2019 | | 2/5/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing PW Drainage | 1/30/2019 | | 1/30/2019 | | PASS |
Brian Murphy
|
|
|
Move approval stamp to latest version of C2.0
|
Routing - PLAN CHECK | 1/29/2019 | | 1/30/2019 | | PASS |
Carl Westfall
|
|
|
Completed the 3rd review. Drawings approved.
|
Routing - MECHANICAL | 1/30/2019 | | 1/30/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/30/2019 | | 1/30/2019 | | FAIL |
Daryl Spivey
|
|
|
Waste and vent plumbing does not meet requirements of ISPC.
|
Plan resubmittals received | | | 1/29/2019 | | DONE |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 12/24/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 12/14/2018 | | 12/24/2018 | | PASS |
Carl Westfall
|
|
|
Jordan Terry (KPFF)
|
Routing - MECHANICAL | 12/14/2018 | | 12/19/2018 | | FAIL |
Troy James
|
|
|
|
Routing - PLAN CHECK | 12/10/2018 | | 12/14/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing PW Solid Waste | 12/14/2018 | | 12/14/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 12/14/2018 | | 12/14/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - C.D.H | 12/14/2018 | | 12/14/2018 | | PASS |
Carl Westfall
|
|
|
Routed to Dinko at CDHD for review. He determined that no review was required.
|
Routing PW Sewer Design | 12/14/2018 | | 12/14/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLUMBING | 12/14/2018 | | 12/14/2018 | | FAIL |
Daryl Spivey
|
|
|
Plumbing not approved. Not shown on plans as required by ISPC.
|
Routing - Design Review | 12/14/2018 | | 12/14/2018 | | FAIL |
Andrea Tuning
|
|
|
All pole lighting shall be located outside of the required setbacks.
The interior planter islands adjacent to the buildings main entrance shall contain a Class II tree. The proposed Columnar Sweetgum is not an approved species. Please consult the Boise Parks and Recreation Tree Planting Guide for an approved species.
The landscape plan is proposing to remove two large trees from the property to teh south. This is not approved. If the applicant would like to pursue this possibility, a separate Design Review application will be required. The request will then be reviewed through the Design Review process for appropriateness and mitigation. This proposal should be removed from this site.
The fire hydrant is also proposed to be located at the main entrance driveway. The fire hydrant location should be located outside of the area where the required tree is proposed to be planted.
All Mechanical units are required to be screened. The mechanical area along the south property line should include a screening proposal.
|
Routing - FIRE | | | 12/13/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Plan resubmittals requested | | | 12/10/2018 | | DONE |
|
|
|
All uploaded "A" sheets were the wrong size. All uploaded "P" and "M" sheets were not signed. All uploaded "E" sheets were not stamped or signed. Resubmittal rejected. The above revised sheets deleted. Work flow sent back to the applicant to try again.
|
Plan resubmittals received | | | 12/10/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/6/2018 | | 12/10/2018 | | FAIL |
Carl Westfall
|
|
|
All uploaded "A" sheets were the wrong size. All uploaded "P" and "M" sheets were not signed. All uploaded "E" sheets were not stamped or signed. Resubmittal rejected. The above revised sheets deleted. Work flow sent back to the applicant to try again.
|
Plan resubmittals received | | | 12/6/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 11/5/2018 | 11/8/2018 | 11/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/13/2018 | 9/13/2018 | 11/5/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 11/5/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 11/5/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/13/2018 | | 10/3/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 9/13/2018 | | 10/1/2018 | | FAIL |
Carl Westfall
|
|
|
Jordan Terry (KPFF)
|
Routing PW Drainage | 9/14/2018 | | 9/25/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 9/13/2018 | | 9/24/2018 | | FAIL |
Troy James
|
|
|
|
Routing PW Environmental | 9/14/2018 | | 9/20/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - Erosion and Sediment | 9/13/2018 | | 9/17/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed prior to any ground disturbance. Site prep inspection required.
|
Routing - PLANNING | 9/13/2018 | | 9/17/2018 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 9/13/2018 | | 9/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Street Lights | 9/14/2018 | | 9/17/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 9/13/2018 | | 9/17/2018 | | FAIL |
Andrea Tuning
|
|
|
DRH18-00305
All pole lighting shall be located outside of the required setbacks.
Provide a continuous pedstrian pathway to the bicycle parking. (You should not haev to carry your bike up a cur, through a landscape planter,etc.)
The interior planter islands adjacent to the buildings main entrance shall contain a Class II tree.
Install a second tree within the “double terminal planter” located in the northwest corner of the site.
The sidewalks on Elder Street shall be 7-feet wide the entire leghth of the property if they are attached. This will need to be unimpeded walkway. If this cannot be attained, the sidewalk shall be 5-feet in width and detached from the curb line by a minimum of 8-feet.
All interior sidewalks shall be 5-feet in width.
Recess the upper story windows a minimum of two inches from the façade. Cut sheets identifying this depth will be required prior to issuance of a building permit.
Provide full height screening for the mechanical units located on the site side of the building. The proposed screening method shall be reviewed and approved by the Design Review Division prior to issuance of a building permit.
|
Routing PW Sewer Design | 9/14/2018 | | 9/14/2018 | | FAIL |
DeAnn Brown
|
|
|
Add to note 10 on utility sheet and label manhole as shown in changemarks in eplanreview.
|
Routing PW Solid Waste | 9/14/2018 | | 9/14/2018 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure must have at least 18 feet of unobstructed clearance between gate posts (measured from the innermost points) for two dumpsters. A single 6- or 8-yard dumpster could be placed in the enclosure with no required changes.
|
Routing - PUBLIC WORKS | 9/13/2018 | | 9/14/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 9/13/2018 | | 9/14/2018 | | FAIL |
Daryl Spivey
|
|
|
Plumbing not installed per ISPC. All plumbing shall be installed as required by the Idaho State Plumbing Code.
|
Routing PW Sewer Rating | 9/14/2018 | | 9/14/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 9/13/2018 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/13/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/7/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Architectural sheets are missing signature and date on stamp.
2. City stamp space is missing from MEP and S drawings.
|
Application received | | | 9/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2018 11:21AM
|