INSP-Final Inspection | 3/17/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection is complete.
Robert Chambers is the contact. Thanks Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed, no pressure loss observed.
Reashard Howard is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/26/2019 | 7/29/2019 | 7/29/2019 | A | FAIL |
Jim Page
|
|
|
Underground lost 6 psi during hydro
Reashard Howard is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/23/2019 | 7/26/2019 | 7/26/2019 | P | CANC |
Jim Page
|
|
|
Could not complete hydrostatic test due to time constraints, hydro will need to be rescheduled.
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 7/23/2019 | 7/26/2019 | 7/26/2019 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Robert Chambers is the contact. Stacey with Suez is aware of this flush, and will be there. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2019 | 7/18/2019 | 7/18/2019 | P | CANC |
Jim Page
|
|
|
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 7/17/2019 | 7/18/2019 | 7/18/2019 | P | CANC |
Jim Page
|
|
|
Robert Chambers is the contact. Stacey with Suez is aware of this inspection and will be there to perform the flush. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan Modification Accepted | | | 3/28/2019 | | DONE |
|
|
|
per cam hess
|
Plan assigned to (Stumbaugh) | 3/28/2019 | | 3/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/28/2019 | | 3/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 3/28/2019 | | DONE |
|
|
|
plan mod
|
CHANGE STATUS TO (ISS) | | | 3/28/2019 | | DONE |
|
|
|
plan mod no fees
|
INSP-Sprinkler Rough-in | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | FAIL |
Jim Page
|
|
|
Install does not match city approved drawings, piping is currently located under a future stairwell install.
The contact is Brian Collins. Thank you for your work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | FAIL |
Jim Page
|
|
|
Could not locate city approved drawings, piping is still covered, could not verify cover depth.
Cam Hess is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | FAIL |
Jim Page
|
|
|
Underground piping was covered before inspection was performed, all cover material needs to be removed from changes of direction as well as spot checked on longer runs of piping to verify proper depth of cover for what was installed. City approved drawings for undergorund supply need to be available at time of inspection.
Cam Hess is the contact. Thanks for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Issue and Print Permit | | | 11/28/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/27/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/27/2018 | | 11/27/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/27/2018 | | 11/27/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/27/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/27/2018 | | DONE |
|
|
|
all requirements met
|
Application received | | | 11/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2018 11:51AM
|