INSP-Final Inspection | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been completed, final life fire safety inspection comlpete.
Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
INSP-Final Inspection | 3/6/2019 | 3/6/2019 | 3/6/2019 | P | PART |
Jim Page
|
|
|
Final fire alarm inspection for scope of work is complete. NAC panel is going to be changed per conversation with installing contractor. A follow up inspection will be required after NAC replacement is complete. TCO mis authorized per conversation with Ron Johnson for 45 days contingent on fire alarm completion, to include as-built submittal and approval.
Please call 1/2 hour ahead Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
INSP-Final Inspection | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | CANC |
Jim Page
|
|
|
Fire alarm system not ready for inspection per conversation with point of contact. Inspection request will be re-scheduled for a later date.
Please make last inspection for the day. Call 1/2 hour ahead Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
INSP-Final Inspection | 3/1/2019 | 3/4/2019 | 3/4/2019 | A | CANC |
Jim Page
|
|
|
Fire alarm system not ready for inspection per conversation with point of contact. Inspection request will be re-scheduled for a later date.
Please call 1/2 hour ahead Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
Staff review | 3/1/2019 | 3/1/2019 | 3/1/2019 | | DONE |
Lee G Meredith
|
|
|
|
Plan assigned to (Lee) | 3/1/2019 | | 3/1/2019 | | DONE |
Lee G Meredith
|
|
|
|
Plan Modification Accepted | | | 3/1/2019 | | DONE |
|
|
|
Plan Mod / As built drawings and calcs.
|
1st review completed | | | 3/1/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 3/1/2019 | | 3/1/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/1/2019 | | DONE |
|
|
|
Plan mod passed.
|
Permit Ready to Issue | | | 3/1/2019 | | DONE |
|
|
|
Plan Mod
|
Plan Modification Accepted | | | 3/1/2019 | | DONE |
|
|
|
plan mod changes made added relays - assigned to Lee M
|
Plan Modification Accepted | | | 3/1/2019 | | DONE |
|
|
|
plan mod changes added relays-assigned to Lee M
|
INSP-Conference | 2/8/2019 | 2/12/2019 | 2/12/2019 | P | DONE |
Jim Page
|
|
|
Fire conference complete.
Jim Phone #: ###-####
|
Application received | | | 1/31/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2019 11:50AM
|
Plan assigned to (Lee) | 1/31/2019 | | 1/31/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/31/2019 | | PASS |
|
|
|
As Noted.
|
Alarm Plan Check | 1/31/2019 | | 1/31/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/31/2019 | | DONE |
|
|
|
Plans passed as noted.
|
Permit Ready to Issue | | | 1/31/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 1/31/2019 | | DONE |
|
|
|
|