Permit Information
Permit NumberBLD17-02871
StatusFinaled
Name PETRA INC
Site Address 1300 S BIRD ST
Project NameIdaho Humane Society
Customer NumberBLD17-02474/GRD17-00030
ePlanReviewYes
Description
**Project Management- Ron Hill** (IDAHO HUMANE SOCIETY – OFFICE, ANIMAL SHELTER, ANIMAL HOSPITAL, AND RETAIL SALES) (DRH17-00219) (CUP17-00037) (10-5-18 PLAN MODIFICATION TO ADD 17 PARALLEL PARKING SPACES ALONG THE EAST DRIVEWAY/FIRE LANE, REMOVE A GATE ACROSS THE EAST DRIVEWAY/FIRE LANE, REMOVE THE CHAIN LINK FENCING AT THE NORTH AND EAST EDGES OF THE SITE, RECONFIGURE CHAIN LINK FENCING AT OUTDOOR KENNEL AREAS, REMOVE THE OUTDOOR PAVED PLAZA AND REPLACE IT WITH GRASS LANDSCAPING, REMOVE A TRELLIS STRUCTURE AT THAT LOCATION, PROVIDE A SIDEWALK AT THE NORTH ENTRANCE WHERE THE PLAZA HAS BEEN REMOVED, RELOCATE THE SANITARY SEWER CONNECTION AT BIRD STREET, ADD A SIDEWALK TRENCH DRAIN WITH COVER, REMOVE A SIDEWALK THAT LED FROM THE PUBLIC WAY TO THE MAIN ENTRANCE, AND TO CHANGE DECIDUOUS TREES TO CONIFERS.) The fire sprinkler system is used for unlimited area of the building. To construct a 40,175 square foot building (34,443 square feet 1st story and a 5,732 square feet 2nd story) to be used as an animal shelter, as an animal hospital, for supporting office, for retail sales, and as a pet training classroom. Work is to include concrete footings, concrete foundations, concrete slabs on grade, masonry exterior walls, exterior framed walls, steel columns, steel beams, glu-lam beams, bearing walls, roof trusses, EIFS, metal exterior wall panels, cement exterior wall panels, pre-cast concrete exterior wall panels, roof insulation installed on top of the roof deck, roof coverings, exterior windows, exterior awnings, exterior doors, a 2nd story floor constructed of concrete on a metal deck, an elevator to serve the 2nd story with an elevator pit and shaft, two stairways to serve the 2nd story, interior doors, interior windows, millwork, and finishes. Special Inspection is required for concrete, masonry, welding, bolting, and EIFS. A trash enclosure with masonry walls will also be constructed on site. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. This permit is intended to establish a Certificate of Occupancy for this tenant and for the entire building. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/30/201910/31/201910/31/2019APASS
DetailsMike Jordan
Jason Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection10/30/201910/30/201910/30/2019PPASS
DetailsTroy Cobbley
Life safety passed.

Jason Phone #: ###-####
BLD-Final9/16/20199/17/20199/17/2019PPEND
DetailsMike Jordan
John Phone #: ###-####. Insulation under lavs completed. Ok for final when the project related fire alarm permit has finaled.
FIRE-Final Inspection9/16/20199/17/20199/17/2019AFAIL
DetailsTroy Cobbley
The exit discharge light has been added as per the previous correction notice. Still need the project related fire alrm permit addressed.

John Phone #: ###-####
BLD-Conference9/13/20199/13/20199/13/2019PDONE
DetailsMike Jordan
John Phone #: ###-####. A correction notice was issued to provide insulation under sinks in all ADA bathrooms.
FIRE-Final Inspection8/13/20198/14/20198/14/2019APART
DetailsMark Scharfen
Fire life safety inspection so Humane Society can start to move equipment in. All extinguishers and exit lights in place. SE door in hospital to parking area is missing exit discharge lighting and will need to have exit discharge lighting installed. Any exit that has an exit sign on the inside will need to have exit discharge lighting outside. All other exits had it and emergency lighting in all area worked correctly. OK to move equipment in. Permit will not be finalled until corrections on fire alarm permit have been corrected, tested and passed.

John Phone #: ###-####
BLD-Conference8/7/20198/8/20198/8/2019ADONE
DetailsMike Jordan
call 10 mins ahead- John Phone #: ###-####
FIRE-Conference7/12/20197/12/20197/12/2019PDONE
DetailsTroy Cobbley
I went over the exit sign/emergency lights as shown on the city approved plans that are missing. We also went over the requirements for the one hour fire sprinkler riser room.
BLD-Ceiling Grid Inspection5/22/20195/22/20195/22/2019PPASS
DetailsMike Jordan
John Phone #: ###-####. 2nd floor and remainder of 1st. floor ok.
BLD-Ceiling Grid Inspection5/20/20195/21/20195/21/2019AFAIL
DetailsMike Jordan
John Phone #: ###-####. All main runners and cross ties shall be tied to prevent spreading. Needs to install clips or spreader bars.
BLD-Conference5/13/20195/14/20195/14/2019ADONE
DetailsMike Jordan
John Phone #: ###-####
BLD-Ceiling Grid Inspection5/7/20195/7/20195/7/2019PPASS
DetailsMike Jordan
hosptail side -John Phone #: ###-####
BLD-Ceiling Grid Inspection4/30/20194/30/20194/30/2019PPASS
DetailsJim Sly
John Phone #: ###-####
BLD-Energy code compliance3/7/20193/7/20193/7/2019PPASS
DetailsMike Jordan
John Phone #: ###-####
BLD-Framing/Rough-in3/1/20193/1/20193/1/2019PPASS
DetailsMike Jordan
John Phone #: ###-####. fireblocking in donor hall.
BLD-Energy code compliance3/1/20193/1/20193/1/2019PPASS
DetailsMike Jordan
John Phone #: ###-####
BLD-Framing/Rough-in2/22/20192/25/20192/25/2019APART
DetailsMike Jordan
John Phone #: ###-####. Donor hall and catery. Needs to complete fireblocking.
BLD-Energy code compliance1/31/20191/31/20191/31/2019PPASS
DetailsMike Jordan
John Phone #: ###-####. fireblocking at top plate fiurred perimeter walls, 2nd. floor ok.
BLD-Energy code compliance1/29/20191/30/20191/30/2019APART
DetailsMike Jordan
John Phone #: ###-####. Airseal at 2nd floor and 1st floor central area completed. Went over fireblocking issues with contractor.
BLD-Framing/Rough-in1/25/20191/28/20191/28/2019APASS
DetailsMike Jordan
evan Phone #: ###-####. !st and 2nd floors, central area only.
BLD-Framing/Rough-in1/23/20191/24/20191/24/2019ACANC
DetailsJim Sly
John Phone #: ###-####
Cancelled by Contractor......
BLD-Wall cover1/17/20191/17/20191/17/2019PPASS
DetailsMike Jordan
John Phone #: ###-####. New envelope compliance with the R30 at vaulted ceilings will be ok, 4% better than code. Spray foam insulation also ok per the ICC ESR report.
BLD-Energy code compliance1/15/20191/15/20191/15/2019PPART
DetailsMike Jordan
John Phone #: ###-####. A correction notice was issued to have architect recalculate the comm check using the R30 value at the vaulted roof areas in lieu of the R38.
FIRE-Final Inspection1/14/20191/15/20191/15/2019AFAIL
DetailsTroy Cobbley
Inspection was just for a conference for the hospital side of the building. I'm ok for covering on the walls and columns as discussed.

John Phone #: ###-####
BLD-Energy code compliance1/10/20191/10/20191/10/2019PPASS
DetailsMike Jordan
John Phone #: ###-####. Ok to cover walls in hospital wing only. Need ICC ESR report for spray foam insulation in attic area ans also needs to provide an attic access as well.
FIRE-Conference12/5/201812/5/201812/5/2018PDONE
DetailsTroy Cobbley
I stopped at the job site and spoke the the project superintendant about the need to contact the building inspector and the building plan reviewer about changes driven by the sprinkler system such as adding elements to the building that have not been included on the city approved plans. The items would include filling combustible concealed spaces with insulation and/or adding sheet rock. Prior to a cover inspection being given I would need approval from the building inspector and/or plan reviewer.
BLD-Framing/Rough-in11/29/201811/29/201811/29/2018PPASS
DetailsMike Jordan
John Phone #: ###-####. Interior wood framed walls ok in hospital wing only. Ok to insulate.
BLD-Wall Bracing7/17/20187/18/20187/18/2018APASS
DetailsMike Jordan
John Phone #: ###-####. All exterior shear walls ok for cover.
BLD-Other6/29/20187/2/20187/2/2018APASS
DetailsMike Jordan
John-- the 2 gable ends--roof sheeting inspection Phone #: ###-####. roof sheathing nailing on pitched roofs ok.
BLD-Framing/Rough-in6/14/20186/15/20186/15/2018APASS
DetailsMike Jordan
John Phone #: ###-####. Flat roof and sloped roof over donor only ok to cover.
BLD-Framing/Rough-in6/14/20186/14/20186/14/2018PPASS
DetailsMike Jordan
John Phone #: ###-####. Roof over animal shelter only ok to cover.
BLD-Framing/Rough-in5/31/20186/1/20186/1/2018APASS
DetailsMike Jordan
John--pre roofing Phone #: ###-####. Roofs over garage and upper mezz ok to cover only.
BLD-Wall Bracing5/29/20185/29/20185/29/2018ANR
DetailsMike Jordan
roofs at garage and 2nd story not ready. Also needs to proveide city approved set of structural plans. Roof at hospital allready covered ,no inspection. Contractor accepts all liability in this area. Will try and verify blocking underneath once contractor has city approved plans.
BLD-Conference4/12/20184/12/20184/13/2018PDONE
DetailsMike Jordan
BLD-Other3/9/20183/12/20183/13/2018APEND
DetailsMike Jordan
John-grout and rebar Phone #: ###-####. Pending special inspection.
BLD-Foundation2/14/20182/15/20182/15/2018APASS
DetailsJim Storey
rebar // John Phone #: ###-#### mti/si pending report to 450