FIRE-Final Inspection | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | CANC |
Troy Cobbley
|
|
|
Permit already finaled.
Chad Phone #: ###-####
|
BLD-Final | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Jim Sly
|
|
|
Chad Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Chad Phone #: ###-####
|
FIRE-Final Inspection | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | FAIL |
Troy Cobbley
|
|
|
The storage racks have been modified so that they do not exceed 8'. I let chad know that they can not exceed 12' in height for storage without a High Pile Storage permit. I am still waiting for fire dept approval for the calculations for the bollards at the nitrogen tank. Also the electrical dept has requested that life safety not be signed off until the required electrical permits are issued for the work that has been performed.
Chad Phone #: ###-####
|
FIRE-Final Inspection | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | PART |
Troy Cobbley
|
|
|
A temporary is being given with Adele's permission until the bollards have been installed at the Nitrogen tank and a racking permit is provided for the new storage racks.
Please call ahead for access, 30min - Jedera Phone #: ###-####
|
BLD-Final | 6/18/2018 | 6/19/2018 | 6/19/2018 | P | CANC |
Mike Jordan
|
|
|
Chad Phone #: ###-####. Needs fire/life/safety final.
|
FIRE-Final Inspection | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | CANC |
Troy Cobbley
|
|
|
Not ready per Chad Phone #: ###-####
|
BLD-Final | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | NR |
Jim Storey
|
|
|
Chad Phone #: ###-#### failled fire/no inspection by bld
|
BLD-Final | 6/14/2018 | 6/18/2018 | 6/18/2018 | P | NR |
Jim Storey
|
|
|
Chad Phone #: ###-#### failled fire/no inspection by bld
|
FIRE-Final Inspection | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | FAIL |
Troy Cobbley
|
|
|
See list on approved plans for items needing corrected such as repairing exit signs/emergency lights, adding emergency lights, providing address, repairing fire alarm panel, removing deadbolts, providing permit for the paint booth and permit for the opening enlargement in the CMU wall at the paint booth.
|
FIRE-Final Inspection | 6/14/2018 | 6/18/2018 | 6/18/2018 | A | CANC |
Troy Cobbley
|
|
|
No plans on site yet. Chad was going to go to the city and get copy.
Chad Phone #: ###-####
|
BLD-Final | 6/13/2018 | 6/15/2018 | 6/15/2018 | P | NR |
Jim Sly
|
|
|
Chad Phone #: ###-#### Need Fire Final 1st.
|
FIRE-Final Inspection | 6/13/2018 | 6/15/2018 | 6/15/2018 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Chad Phone #: ###-####
|
BLD-Conference | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | DONE |
Dave Hannah
|
|
|
Call half hour before to meet // Chad Phone #: ###-####
|
FIRE-Final Inspection | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for inspection yet. No plans or small documents on site, fire extinguishers expired, a paint booth is being installed, it appears a large portion of a CMU wall has been removed, fire alarm panel is non-functional, need verification of fire sprinkler one year and five year inspections....ect.
Chad-- please call 30 mins before Phone #: ###-####
|