Permit Information
Permit NumberBLD18-00943
StatusFinaled
Name SLETTEN CONSTRUCTION
Site Address 2121 N COLE RD
Project NameFairmont Jr High Gymnasium
Customer Number 
ePlanReviewYes
Description
**(FAIRMONT JR HIGH – GYMNASIUM)** // 07/02/19 PLAN MOD TO LANDSCAPING AND GRADING. JAR // 05/29/18 PLAN MODIFICATION TO REMOVE BID ALTERNATES FROM DRAWING SET. JAR // Permit to construct a new 28,750 square foot gymnasium, locker rooms, and cafeteria with associated support areas including restrooms, kitchen associated office, storage, and mechanical rooms on the existing Fairmont Jr. High campus. Work also includes general site work. Special inspections required per attached Form 310. All work per the approved plans and notations. This building is fully fire sprinklered for area increase and is fully alarmed. JAR
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/18/20199/19/20199/19/2019APASS
DetailsTell Riley
Russ Phone #: ###-####//final is complete//landscaping is done//public works signed off//no sign off sheet onsite//
BLD-Aging Inspection9/16/20199/16/20199/16/2019 PASS
DetailsTell Riley
working on landscaping
BLD-Final7/15/20197/15/20197/15/2019PPART
DetailsTell Riley
Troy is here now. Phone #: ###-#### Inspection requested via web by Russell Valline//temp Occupancy ok//needs landscape complete and public works sign offs//
FIRE-Final Inspection7/15/20197/15/20197/15/2019PPASS
DetailsTroy Cobbley
Life safety is passed.. Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Framing/Rough-in4/6/20194/8/20194/9/2019PPART
DetailsJim Sly
enter on west side of the Building please see Russ thank you. Phone #: ###-#### Inspection requested via web by Russell Valline
Framing....hard lid ceilings ....Locker rooms....plus......
BLD-Final3/21/20193/22/20193/22/2019APART
DetailsDave Hannah
come late morning we have fire in morning also thank you. Phone #: ###-#### Inspection requested via web by Russell Valline kitchen and lunch room area ok for temp occ
FIRE-Final Inspection3/21/20193/22/20193/22/2019APART
DetailsTroy Cobbley
Life safety passed for Phase 1.


Inspection requested via web by Russell Valline
BLD-Final3/20/20193/21/20193/21/2019PNR
DetailsJim Sly
Please come a little later Jim working on other inspections all day thanks Inspection requested via web by Russell Valline
Need to have Ron Hills Letter for Phased Occupancy on site for next inspection. Need Fire Temp. Occ. approval.
FIRE-Final Inspection3/20/20193/21/20193/21/2019PFAIL
DetailsTroy Cobbley
Need the project related fire alarm, fire sprinkler and hood suppression permits addressed. Need occupant load signs as discussed and fire dept access signage for the parking lot on the north side of the new building. Neeed determination of ADA requirements for the manual pull for the hood suppression system.

Please try to come early afternoon working on other inspections.

thanks s Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Ceiling Grid Inspection3/17/20193/18/20193/18/2019PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Russell Valline,, cloud in lunch room,, storage for kitchen, entry ok after trades are passed
FIRE-Conference3/17/20193/18/20193/18/2019ADONE
DetailsTroy Cobbley
I went over general life safety items with Russell. There were no small documents on site. Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Ceiling Grid Inspection3/4/20193/5/20193/5/2019APASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Conference2/25/20192/26/20192/26/2019ADONE
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Russell Valline
FIRE-Conference2/25/20192/26/20192/26/2019ADONE
DetailsTroy Cobbley
Russel and I spoke about temp. occupancy requirements and exit paths. I deferred him to Ron Hill in project management.
Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Framing/Rough-in2/11/20192/12/20192/12/2019APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Russell Valline kitchen/caff.cooller/closets/restarmms/hall/mez surround framing ok ceillings ok
BLD-Concrete9/13/20189/14/20189/14/2018PPASS
DetailsJim Storey
We are grouting our first lift tomorrow if you wanted to see. grout truck will be here at 2:00 All west will be here testing and inspecting. Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Foundation8/20/20188/21/20188/21/2018PPASS
DetailsJim Sly
All West is the Third party inspctor Phone #: ###-#### Inspection requested via web by Russell Valline
OK pending Allwest special inspections,tests and approvals.
FIRE-Final Inspection8/14/20188/17/20188/17/2018PPART
DetailsJim Page
Final life fire safety inspection for remodeled parking lot complete.

This is for the parking lot only Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Conference7/26/20187/27/20187/30/2018PDONE
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Russell Valline
BLD-Footing7/26/20187/27/20187/30/2018PDONE
DetailsJim Sly
These are interior footings we do have Allwest 3rd party inspection also Inspection requested via web by Russell Valline
OK pending Allwest special inspections, tests and approvals.
BLD-Foundation7/20/20187/23/20187/23/2018APASS
DetailsJim Sly
Jim just talk to you about this job and you explained as long Phone #: ###-#### Inspection requested via web by Russell Valline
OK pending Allwest special inspections tests and approvals.
BLD-Footing7/12/20187/13/20187/13/2018APASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Russell Valline
OK......pending Allwest special inspections, tests and approvals.
BLD-Footing7/11/20187/13/20187/12/2018ANR
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Russell Valline
Allwest will be special inspection.