BLD-Final | 4/30/2019 | 5/1/2019 | 5/1/2019 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need the fire alarm permit finaled. Kevin Phone #: ###-####
|
BLD-Final | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | CANC |
Mike Jordan
|
|
|
Kevin Phone #: ###-####
|
BLD-Conference | 4/3/2019 | 4/3/2019 | 4/3/2019 | A | PEND |
Jim Storey
|
|
|
open fire permit/ smokeseals verified ok on bld c/n
|
BLD-Final | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PART |
Jim Storey
|
|
|
Dave Phone #: ###-#### need s ratting for smoke leakage at doors.
|
BLD-Final | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | CANC |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PART |
Mike Jordan
|
|
|
Ok to occupy/use pedistrian walkway. Will be ok for final once fire signs off perm.
|
FIRE-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PART |
Troy Cobbley
|
|
|
Life safety for the Link is passed. Dave is going to place fire extinguishers at both ends of the Link. An additional stobe is needed at the Building 36 (LOBBY) end of the link. I spoke to Ron with Boise Fire about this. A separate permit will be needed for this work.
dave Phone #: ###-####
|
BLD-Final | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | CANC |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | FAIL |
Jim Page
|
|
|
Pedestrian link between 36 and 37 not ready for inspection.
Dave Phone #: ###-####
|
BLD-Final | 12/10/2018 | 12/14/2018 | 12/14/2018 | A | CANC |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Moved to pm.
|
BLD-Final | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | NR |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | PART |
Mike Jordan
|
|
|
Please call Chris - Phone #: ###-#### Inspection requested via web by Chris Fuhrman. Pending mech. inspection.
|
BLD-Framing/Rough-in | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PART |
Jim Storey
|
|
|
exterior walls ok to cover
|
BLD-Footing | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PART |
Jim Storey
|
|
|
concrete at noon // Dave Perkins Phone #: ###-#### placed with si/ ppending reports
|