BLD-Final | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Tell Riley
|
|
|
PAT Phone #: ###-####//all trades finals complete//signatures required complete//final complete//
|
BLD-Final | 10/14/2019 | 10/15/2019 | 10/15/2019 | P | CANC |
Tell Riley
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 10/8/2019 | 10/9/2019 | 10/9/2019 | A | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-####
|
BLD-Final | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//last six units complete//temp occupancy approved for entire building//final can be complete once all signatures are complete//
|
FIRE-Final Inspection | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Matt Phone #: ###-####
|
BLD-Final | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-####//cancel per Matt//
|
FIRE-Final Inspection | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | FAIL |
Troy Cobbley
|
|
|
Apartment 201 needs the ceiling patched in several locations and the smoke alarm re-mounted. Apartment 301 sprinkler pendant is missing canopy.
Matt Phone #: ###-####
|
BLD-Final | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//103,104,203,204,303,304/// finals complete on these units//
|
FIRE-Final Inspection | 9/30/2019 | 10/1/2019 | 10/1/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety complete for apartments 103, 104, 203, 204, 303 and 304. Matt Phone #: ###-####
|
BLD-Final | 9/25/2019 | 9/26/2019 | 9/26/2019 | P | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-#### cancel per matt
|
FIRE-Final Inspection | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | CANC |
Troy Cobbley
|
|
|
Matt Phone #: ###-#### cancel per matt
|
BLD-Final | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//units 105,106,205,206,305,306 are ok to occupy when door springs have been adjusted//
|
FIRE-Final Inspection | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | CANC |
Troy Cobbley
|
|
|
The rooms needing inspection have been looked at by me last week. Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 105, 106, 205, 206, 305, 306. Matt Phone #: ###-####
|
BLD-Final | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PART |
Tell Riley
|
|
|
Pat-1st 6 units Phone #: ###-####//north 6 units//final complete pending fire//
|
FIRE-Final Inspection | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PART |
Troy Cobbley
|
|
|
The six apartments, 1st through 3rd floors at the very north end of this building have the life safety passed. The FDC needs the required clearance as discussed prior to a final inspection. Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | CANC |
Troy Cobbley
|
|
|
Life safety will be a pass for the north most apartments when the project related fire alarm and fire sprinkler permits are passed. Matt- mid mornign Phone #: ###-####
|
BLD-Energy code compliance | 7/29/2019 | 7/30/2019 | 7/30/2019 | P | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//ok to cover units101,102,201,202,301,302, all units passed//
|
BLD-Framing/Rough-in | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//framinng corrections onsite//ok to insulate only// 101,102,201,202,301,303//
|
BLD-Energy code compliance | 7/19/2019 | 7/22/2019 | 7/22/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//corrections made//103,104, 203, 204, 303, 304// ok to cover//
|
BLD-Energy code compliance | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | NR |
Tell Riley
|
|
|
Matt Phone #: ###-####//add vapor barrier at bottom on first two floors//fix tenting 3rd floor//fix broken stud first floor//re inspect monday//103/104/203/204/303/304
|
BLD-Framing/Rough-in | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//framing corrections made//call for insulation on 103,104,203,204,303,304//
|
BLD-Framing/Rough-in | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PART |
Tell Riley
|
|
|
Bill Phone #: ###-####//see corrections onsite// ok to insulate--keep areas that need changes open//call for 7/17 pm inspection//103,104,203,204, 303, 304
|
BLD-Framing/Rough-in | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//corrections made//rough-ins passed//105,106,205,206,305,306//
|
BLD-Framing/Rough-in | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | NR |
Tell Riley
|
|
|
Matt Phone #: ###-####//hold downs need to be 18" max per manufacturer//clear up issues with interior wall hold downs//let me know......////
|
BLD-Energy code compliance | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | NR |
Tell Riley
|
|
|
Bill Phone #: ###-####//not ready//
|
BLD-Other | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | CANC |
Tell Riley
|
|
|
follow up on hold down installation....
|
BLD-Other | 6/26/2019 | 6/26/2019 | 6/26/2019 | A | CANC |
Tell Riley
|
|
|
follow up on hold down installation........
|
BLD-Framing/Rough-in | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PART |
Tell Riley
|
|
|
Bill Phone #: ###-####//framing corrections made//waiting for hold down extensions//will schedule follow up mid am 6/27//install trimmers on header second floor//ok to insulate top down//units 5's and 6's
|
BLD-Framing/Rough-in | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | FAIL |
Tell Riley
|
|
|
bill Phone #: ###-####//see corrections list onsite with Bill//call for re-inspection//
|
BLD-Energy code compliance | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PASS |
Mike Jordan
|
|
|
Bill- please late morning Phone #: ###-####. framing issues corrected.
|
BLD-Framing/Rough-in | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PART |
Tell Riley
|
|
|
bill Phone #: ###-####//install H2.5 on trusses//nail all truss hangers//add nuts to HDU's//caulk penetrations as discussed//ok to insulate only//
|
BLD-Wall Bracing | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | PART |
Jim Sly
|
|
|
Bill Phone #: ###-#### Exterior straps and nailing only.....OK..
|
BLD-Foundation | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Sly
|
|
|
Please go late morn and call Dean Phone #: ###-####
|
BLD-Foundation | 3/1/2019 | 3/4/2019 | 3/5/2019 | P | PASS |
Jim Sly
|
|
|
DAne Phone #: ###-####
|
BLD-Foundation | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 2/25/2019 | 2/26/2019 | 2/26/2019 | P | PART |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 2/20/2019 | 2/21/2019 | 2/22/2019 | P | CANC |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | PASS |
Brandon Shaw
|
|
|
Remove snow and/or ice before pouring... Frost protection is required...
|
BLD-Footing | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PART |
Jim Sly
|
|
|
Dane Phone #: ###-####
|