Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD19-00534
StatusIssued
Name ESI
Site Address 11964 W FAIRVIEW AVE
Project NameVillage East - Building K
Customer NumberBLD19-00526-00536, 538-539
ePlanReviewNo
Description
(13 PERMITS IN EPLAN UNDER BLD19-00526) (BUILDING K – VILLAGE EAST APARTMENTS – RESIDENTIAL) (PUD18-00042) (DRH18-00528) The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 22,793 square foot, 4 story apartment building (5,959 square foot 1st story, 5,959 square foot 2nd story, 5,959 square foot 3rd story, and 4,916 square foot 4th story) with a total of 16 dwelling units (4 on each story). All dwelling units on the 1st story are required to comply as Type B dwelling units (one is also required to comply as Type A in Building G and in Building K). Since there is no elevator in this building, the dwelling units located on the 2nd, 3rd and 4th stories are not regulated for accessibility to the disabled. Work is to include concrete footings, concrete stem walls between conditioned and unconditioned spaces, concrete pedestals, concrete slab on grade with thickened slab at interior bearing walls and R-10 perimeter slab edge insulation between conditioned and unconditioned spaces, 2x6 walls between conditioned and unconditioned spaces with R-20 cavity insulation and R-3.8 continuous insulation, wood columns, shear walls with gypsum panels or structural wood panels and hold downs, an unconditioned 1-hr fire-resistance-rated corridor on each story, two unconditioned 2-hr fire-resistance-rated exterior stairways, 1-hr dwelling unit separation walls between dwelling units, draftstops in the attic, 1-hr dwelling unit separation floors between dwelling units, engineered wood truss roof system with a structural wood panel roof deck and R-49 insulation installed on top of the ceiling with the attic vented to the outside, roof overbuilds, ladder and roof hatch to access roof top heat pumps, exterior windows, interior doors between conditioned and unconditioned spaces, exterior cementitious lap siding, exterior brick veneer, exterior stucco, guards, handrails, asphalt shingles, 3-ply roofing membrane at flat roof areas, roof drains and overflow drains, interior millwork, and interior finishes. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The design for the engineered wood trusses is a deferred submittal item. The fire sprinkler system is required to comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/12/20208/13/20208/13/2020PFAIL
DetailsGreg Ruxton
Pavement required for TCO not complete.

Paving operations for fire truck access should wrap up in the morning.Other small items addressed from Troy Cobbley''s visit on Wednesday. Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Final8/12/20208/13/20208/13/2020ANR
DetailsTell Riley
Need a couple hours in the morning. After 10 am inspection preferred Phone #: ###-#### Inspection requested via web by Travis Blackburn
FIRE-Final Inspection8/11/20208/12/20208/12/2020PFAIL
DetailsTroy Cobbley
Life safety will be ok for a temp when the additional pavement has been layed as agreed. For a final the permanant address and heaters will need to be provided and veriifed.

Lee *screened Phone #: ###-####
BLD-Wall cover6/2/20206/2/20206/2/2020PPART
DetailsTell Riley
Drop ceiling on 1st and 2nd floors for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//soffits ok to cover when fire caulk is fixed as discussed//areas will be framed down in laundry//fire tape areas as discussed 2nd floor//Jeremy will send photos to confirm//
BLD-Wall Bracing5/22/20205/22/20205/22/2020PPART
DetailsTell Riley
Reinspect for gyp shear on all floors Phone #: ###-#### Inspection requested via web by Travis Blackburn//4th and 3rd floor ok//fix shear wall in 2nd floor, block edges//add screws at first floor//
BLD-Wall Bracing5/21/20205/22/20205/22/2020ACANC
DetailsTell Riley
Re inspect of gypsum board shear on all floors Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Wall cover5/21/20205/21/20205/21/2020PPART
DetailsTell Riley
3rd and 4th floor drop ceiling inspection for cover along with gyp shear in the entire building Phone #: ###-#### Inspection requested via web by Travis Blackburn//drops ok, third floor pending fire sprinkler approval//shear walls will need to be re-inspected after more screws are added//
BLD-Wall cover5/20/20205/20/20205/21/2020PCANC
DetailsTell Riley
Inspect drop ceilings on bldg K 4th floor, possibly 3rd also Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Framing/Rough-in5/11/20205/11/20205/11/2020PPART
DetailsTell Riley
Corridor inspection to cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//add lags in areas marked//fire caulk penetrations where marked//
BLD-Energy code compliance5/6/20205/7/20205/7/2020PPASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Framing/Rough-in5/4/20205/5/20205/5/2020APART
DetailsTell Riley
Inspection to insulate 1st floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//add bolts as noted on floor//fix holddown that is not installed//fire caulk areas noted//photos of repairs will be sent//
BLD-Wall cover4/27/20204/28/20204/28/2020APART
DetailsTell Riley
Cover inspection for 2nd floor only Phone #: ###-#### Inspection requested via web by Travis Blackburn//2nd floor cover ok, add insulation around vent exhausts at exterior wall and at rims where needed//
BLD-Wall cover4/23/20204/24/20204/24/2020APASS
DetailsDave Hannah
Insulation inspection to cover 3rd floor only Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Conference4/21/20204/22/20204/22/2020ADONE
DetailsTell Riley
Discuss phased turnover and clubhouse firestopping. Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Framing/Rough-in4/21/20204/22/20204/22/2020APART
DetailsTell Riley
Framing inspection to insulate 2nd floor only. Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate 2nd floor//collars on 3rd and 4th floor installed, and joist repairs were made//
BLD-Framing/Rough-in4/20/20204/21/20204/21/2020PPART
DetailsTell Riley
Inspection on 3rd floor for approval to insulate and cover inspection on 4th floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//4th floor ok to cover when fire collars are on drain pipe//3rd floor ok to insulate, fix sprinkler tenting, add fire collar to drain pipe, fix hole in joist in furnace room on two of the 4 units//
BLD-Conference4/1/20204/1/20204/1/2020PDONE
DetailsTell Riley
met onsite with Matt, plumbing inspector, discussed with Travis need for plumbing plans to be revised for building and all other buildings prior to any passed plumbing inspections//
BLD-Wall cover3/31/20204/1/20204/1/2020APEND
DetailsTell Riley
4th floor only approval to cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//insulation ok---still need trades inspections completed--need them prior to insulation and cover//
BLD-Framing/Rough-in3/26/20203/27/20203/27/2020APEND
DetailsTell Riley
Shaftliner cover and 4th floor ok to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok when firecaulk has been done at shaftliner//ok to insualate 4th floor pending other trades inspections//
BLD-Framing/Rough-in3/24/20203/25/20203/25/2020PNR
DetailsTell Riley
2ND and 3RD Floor preliminary inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//discussed framing corrections for cut joists, will need fixed//some fire caulking, need plumbing and fire alarm finished//
BLD-Framing/Rough-in3/19/20203/20/20203/20/2020APART
DetailsTell Riley
3rd and 4th floor//truss bracing fixed//framing appears to be ok//need mechanical, electrical, and plumbing roughs passed//will need to do walk through before insulation//
BLD-Framing/Rough-in3/18/20203/19/20203/19/2020ACANC
DetailsTell Riley
3rd and 4th floor preliminary walk to check structural aspects. Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Framing/Rough-in3/11/20203/12/20203/12/2020APART
DetailsTell Riley
Preliminary inspection for trusses and structural as time allows Phone #: ###-#### Inspection requested via web by Travis Blackburn//northside 4th floor units trusses ok//south side 4th floor units trusses need bracing//shear straps 4th floor ok//
BLD-Other2/17/20202/18/20202/18/2020APART
DetailsTell Riley
Exterior sheetrock inspection to install weather barrier Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok per pla ns//
BLD-Framing/Rough-in2/3/20202/3/20202/3/2020PPART
DetailsTell Riley
Walk prerock areas in K for insulation Phone #: ###-#### Inspection requested via web by Travis Blackburn//will be ok after hold downs installed//
BLD-Wall Bracing1/14/20201/14/20201/14/2020PPART
DetailsTell Riley
Shear inspection on last wall and h2.5''s to be covered at eves Phone #: ###-#### Inspection requested via web by Travis Blackburn//shear area on exterior south wall ok//see CN for other areas requested to look at//
BLD-Wall Bracing1/8/20201/10/20201/10/2020APART
DetailsTell Riley
Exterior shear and hardware for cover. Interior at a later date Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to cover exterior with wrap--DO NOT COVER south wall until approved for straps and fixed sheathing//
BLD-Conference1/7/20201/8/20201/8/2020PDONE
DetailsTell Riley
Discuss 2hr walls Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Wall Bracing1/7/20201/8/20201/8/2020PNR
DetailsTell Riley
Shear inspection for hardware for exterior cover Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Wall Bracing1/7/20201/7/20201/8/2020PCANC
DetailsTell Riley
BLD-Wall Bracing1/3/20201/6/20201/6/2020APART
DetailsTell Riley
Shear inspection and hardware inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//nailing ok//need to finish straps//provide documentation on nails in pressure treat or use hot dipped galvanized//will need to check hold downs//
BLD-Concrete10/14/201910/14/201910/14/2019PPASS
DetailsTell Riley
Concrete pour at 1pm. Inspection on reinforcing steel at edges of corridor Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//
BLD-Concrete10/9/201910/10/201910/10/2019PPART
DetailsTell Riley
We are pouring the slab for building K at 6:30 on Friday morning. Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//
BLD-Concrete10/3/201910/4/201910/4/2019PCANC
DetailsTell Riley
Pouring slab on grade for this building early Monday morning so late inspection should work Phone #: ###-#### Inspection requested via web by Travis Blackburn//cancel per Matt//
BLD-Foundation9/18/20199/19/20199/19/2019PPART
DetailsTell Riley
Concrete pour scheduled for 3:30 Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to pour//pending special inspections///
BLD-Footing9/16/20199/16/20199/16/2019PPART
DetailsTell Riley
Second half of this building will need inspected for reinforcement.Pour time is after the walls on the clubhouse walls this afternoon Phone #: ###-#### Inspection requested via web by Travis Blackburn//bar fixed while onsite// ok pending specials//
BLD-Footing9/10/20199/12/20199/12/2019PFAIL
DetailsMike Jordan
Concrete pour is at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn. Clearance issues fromm bottom of footing. Needs to install verts in corner, rebar needs to be tied as to resist movement when concrete is placed.
BLD-Final8/13/20208/14/2020 A 
DetailsTell Riley
Phone #: ###-#### >> Inspection requested via web by Travis Blackburn