BLD-Final | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Mike Jordan
|
|
|
Can we please final our life fire safety now that the FA permit FIR19-00585 is finaled (revised drawings approved). Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
|
DOC - Permit Finaled | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
|
FIRE-Final Inspection | 10/11/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given until the as-builts/plan mods are approved.
Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
|
FIRE-Alarm Testing | 10/11/2019 | 10/15/2019 | 10/15/2019 | A | DONE |
Troy Cobbley
|
|
|
See the project related fire alarm permit for specifics for the fire alarm testing.
|
BLD-Final | 10/11/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Mike Jordan
|
|
|
Fire Alarm / Final inspections scheduled for 7 am Tuesday. Please come afterward. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps. OK for temp occ. Will be ok for perm occ. once fire signs perm.
|
BLD-Final | 10/11/2019 | 10/16/2019 | 10/11/2019 | A | CANC |
Mike Jordan
|
|
|
Fire Alarm / Fire Final inspection scheduled for 7 AM Tuesday. Please come afterward. Thank you. Phone #: ###-#### >> Inspection requested via web by Jackie Phelps Inspection cancelled from web by: Jackie Phelps
|
FIRE-Final Inspection | 10/11/2019 | 10/16/2019 | 10/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Please come first thing (7 am) so we can get done before school starts. We cant sound alarm when school in session. Thank you. Phone #: ###-#### >> Inspection requested via web by Jackie Phelps Inspection cancelled from web by: Jackie Phelps
|
FIRE-Alarm Testing | 10/11/2019 | 10/14/2019 | 10/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Preferably before school opens if plan review is completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jackie Phelps
|
BLD-Final | 10/11/2019 | 10/14/2019 | 10/11/2019 | P | CANC |
Mike Jordan
|
|
|
Preferably before school opens if plan review is completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jackie Phelps
|
FIRE-Final Inspection | 10/11/2019 | 10/14/2019 | 10/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Preferably before school opens if plan review is completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jackie Phelps
|
BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 | P | CANC |
Brandon Shaw
|
|
|
Preferably right after final life safety. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
FIRE-Final Inspection | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | NR |
Troy Cobbley
|
|
|
No ready for life safety due to fire alarm resubmittal. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
BLD-Framing/Rough-in | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PASS |
Tell Riley
|
|
|
jimmie//SSC clips installed per RFI 027 for connection of box header//correction made per Mikes notes//
|
BLD-Framing/Rough-in | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PART |
Mike Jordan
|
|
|
Early as possible please. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Steel stud framing and box headers for new openings. Needs to install SSC clips from bottom track to each stud. Contractor to fllow up with RFI approving the angle clips in leiu of HUC hangars for box header to jamb conections.
|
BLD-Framing/Rough-in | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | NR |
Jim Storey
|
|
|
Jimmy Phone #: ###-#### no one on site.
|
BLD-Wall cover | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | CANC |
Mike Jordan
|
|
|
Ross is on site contact through 8/27. ###-####. We are scheduled to sheetrock the ceiling tomorrow, insulation has been removed and replaced with new. RFI mentioned in early inspection comment has been sent. Please confirm If we need a re-inspection prior to cover. Thank you! Jackie Phelps ###-#### Phone #: ###-#### >> Inspection requested via web by Jackie Phelps Inspection cancelled from web by: Jackie Phelps
|
BLD-Framing/Rough-in | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Mike Jordan
|
|
|
Jimmy Phone #: ###-####. Interior steel stud furred walls for equipment chases. Also reviewed RFI for use of A35's.
|
BLD-Framing/Rough-in | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PART |
Mike Jordan
|
|
|
Jimmie Phone #: ###-####. Additional 2x12 joist sistering to support new mech. equpment in kitchen. Need RFI for alternate attacment of A35 in lieu of the 2 inch bearing.
|