Permit Information
Permit NumberESC16-01651
StatusFinaled
Name JIM CONGER
Site Address 6211 W HILL RD
Project NameBelmar Estates # 2
Customer Number 
ePlanReviewNo
Description
(BELMAR SUBDIVISION) Subdivision site development including grading, road & sewer, installation , and stormwater facilities. SWPPP submitted with site map and narrative. CGP tracking IDR12AV03 & IDR12AV84. Silt fence perimeter sediment control along Farmer Union Canal and low elevation of the subdivision to be installed prior to earth disturbance. No GRD permit issued with ESC permit. Construction entrance required for access onto Hill Road. Leak proof concrete washout required for cement curb work. Need to protect new storm drain inlets once installed. ESC site preparation inspection required, call 608-7070 to schedule.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection4/1/20194/1/20194/1/2019 CANC
DetailsMichael Zawacki
DOC - Permit Finaled4/1/20194/1/20194/1/2019PPASS
DetailsMichael Zawacki
All homes completed, neighborhood BMPs removed.
Aging Inspection1/30/20191/30/20191/30/2019 PASS
DetailsMichael Zawacki
Homes are complete. Road needs to be swept in rear.
General Inspection11/30/201811/30/201811/30/2018PPEND
DetailsMichael Zawacki
Landscapers skid steer has tracked mud into cul-de-sac. Will need to be cleaned at end of work.
General Inspection11/14/201811/14/201811/14/2018PPASS
DetailsMichael Zawacki
Almost all exterior work on homes complete. Concrete work is complete, washout removed. Some trash boxes full and need to be removed. Load of landscaping rock is stored on road.
Aging Inspection10/1/201810/1/201810/1/2018 PASS
DetailsMichael Zawacki
Neighborhhod is crowded but clean. No dirt leaving homesites, trash is mostly contained. Large pile of landscaping gravel dumped on street.
Aging Inspection8/1/20188/1/20188/2/2018 PASS
DetailsMichael Zawacki
Neighborhood around 1/3rd completed and occupied. Site is clean, lots have trash boxes. Concrete work is complete.
General Inspection6/1/20186/1/20186/1/2018APASS
DetailsAndy J. Long
A foundations have been poured. Concrete washout area has been cleaned up. Permit signs posted on active projects, storm drains have sediment protection. No loose trash or other violations observed.
General Inspection5/3/20185/3/20185/3/2018PPART
DetailsMichael Zawacki
Drain inlet protection is getting full and needs to be maintained. All foundations have been poured, concrete washout has been removed. Paint and/or stucco is being washed onto ground.
General Inspection4/3/20184/3/20184/3/2018PPART
DetailsMichael Zawacki
Most foundations and driveways complete. Lots of loose dirt in rear of projects. Some trash boxes are overfilled and waste is being piled on ground.
General Inspection3/7/20183/7/20183/7/2018PPART
DetailsMichael Zawacki
Lots of trackout on roads and sidewalks. Homesites are clean of building waste. Concrete washout has been relocated.
General Inspection1/16/20181/16/20181/16/2018PPART
DetailsMichael Zawacki
Lots nof dirt on road and sidewalks. Nothing getting onto hill road. Dirty water flowing in gutters, DI is protected.
Aging Inspection1/3/20181/3/20181/3/2018 PASS
DetailsMichael Zawacki
Work on multiple homes. Some track out inside neighborhood. Washout in use. Neighborhood needs a trash pickup soon for construction waste at homes being framed.
General Inspection11/3/201711/3/201711/7/2017PPEND
DetailsMichael Zawacki
Landscapers and foundation workers onsite. Trackout everywhere within neighborhood, not being tracked onto hill. Concrete washout now in use. No sign of dirt in creek/canal.
Random Inspection10/19/201710/19/201710/19/2017PPEND
DetailsMichael Zawacki
Doing sidewalk and curb along hill. Dumping washout onto empty lot. Called RP, said he would get it taken care of.
General Inspection8/23/20178/28/20178/31/2017PCANC
DetailsAndy J. Long
rescheduled
General Inspection8/23/20178/23/20178/23/2017 CANC
DetailsAndy J. Long
General Inspection5/9/20175/23/20175/24/2017PPASS
DetailsAndy J. Long
No activity at time of inspection. No discharges, trackout or fugitve dust observed. Permit sign and SWPPP info posted. Approved.
General Inspection5/9/20175/9/20175/9/2017PPASS
DetailsAndy J. Long
No new activity. Undergound sewer and utlitiy work is complete but no roads or gutters yet. Permit and SWPPP info posted at rock construction entrance. Perimeter control wattle installed along contruction limits in between canal. There are some large unprotected stockpiles on site that should be stabilized/ flattened to prevent fugitive dust issues. Will check on status in 2 weeks.
General Inspection2/28/20172/28/20172/28/2017PPASS
DetailsMelissa Jannusch
No site preparation walk through. Construction entrance is installed. Sign is posted. Vegetated buffer is on perimeter surrounding perimeter. No corrections requested.
Site Preparation2/28/20172/28/20172/28/2017PFAIL
DetailsMelissa Jannusch
Did not call in site preparation. Did not have a site prep walk through.
General Inspection8/31/20179/7/2017 P 
DetailsAndy J. Long