Site Final | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Andy J. Long
|
|
|
Townhomes complete and landscaped. Remaining ESC inspecitons conducted under main site permit ESC16-00945.
|
General Inspection | 6/13/2018 | 6/13/2018 | 6/15/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/29/2018 | 5/29/2018 | 5/30/2018 | | PASS |
Michael Zawacki
|
|
|
Rear lot is now paved. Hill in rear is covered with mulch, fence line has wattle for entire length of project. Landscaping in process. All work is scheduled to be complete by June 10th.
|
General Inspection | 5/14/2018 | 5/14/2018 | 5/14/2018 | | PASS |
Michael Zawacki
|
|
|
Work is interior. Outside is exposed but contained, nothing leaving site.
|
General Inspection | 4/27/2018 | 4/27/2018 | 4/30/2018 | | PASS |
Michael Zawacki
|
|
|
No dirt leaving site. Site is still all exposed, large puddle on drive heading towards back of units. Will need to monitor as a cause of trackout.
|
General Inspection | 4/12/2018 | 4/12/2018 | 4/13/2018 | | PASS |
Michael Zawacki
|
|
|
Front area cleaned up. Forms being put in place for sidewalk to front doors.
|
General Inspection | 3/28/2018 | 3/28/2018 | 3/28/2018 | | PART |
Michael Zawacki
|
|
|
Site is dirty, needs a good cleanup. No dirt is leaving site.
|
General Inspection | 3/13/2018 | 3/13/2018 | 3/14/2018 | | PASS |
Michael Zawacki
|
|
|
No mud leaving site today.
|
General Inspection | 2/26/2018 | 2/26/2018 | 2/26/2018 | | PASS |
Andy J. Long
|
|
|
Minimal work occuring during wet winter weather this morning. Workers parking across the street to avoid trackout from site. No offsite discharges or trackout observed. No loose trash next to road.
|
Conference | 2/9/2018 | 2/9/2018 | 2/9/2018 | P | DONE |
Andy J. Long
|
|
|
new project manager, Matteo E. 777.304.5459
Notified he will be new RP and is working on corrections at site.
|
Tracking Control | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Michael Zawacki
|
|
|
Trackout onto Warm Springs. Area looks cleaned. Still some hard packed dirt in places. Site will be monitored more frequently.
|
Complaint Inspection | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | FAIL |
Michael Zawacki
|
|
|
Lots of trackout onto Warm Springs. Talked to Preston and said he would get it clean. Scheduled follow up for the morning.
|
General Inspection | 1/25/2018 | 1/25/2018 | 1/26/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/10/2018 | 1/10/2018 | 1/10/2018 | | PASS |
Michael Zawacki
|
|
|
WIP on buildings. Back is muddy but not leaving site. No vehicles on property, no trackout.
|
General Inspection | 12/21/2017 | 12/21/2017 | 12/21/2017 | | PASS |
Michael Zawacki
|
|
|
WIP. Some excavation for sewer lines. Lots of dirt on sidewalk, people also parking on sidewalk.
|
General Inspection | 12/1/2017 | 12/1/2017 | 12/1/2017 | | PASS |
Michael Zawacki
|
|
|
WIP. Site clean and maintained. New supervisor on site.
|
General Inspection | 11/15/2017 | 11/15/2017 | 11/15/2017 | | PASS |
Michael Zawacki
|
|
|
WIP. Asked to provide washout for when stucco begins. Site is contained and clean, some dirt on sidewalk I asked for them to clean.
|