Site Final | 10/25/2018 | 10/25/2018 | 10/26/2018 | P | PASS |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Michael Zawacki
|
|
|
|
Site Final | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | NR |
Michael Zawacki
|
|
|
Rescheduled for 10/26. Need to see if public works wants witches hats removed from their project on fort st.
|
General Inspection | 10/11/2018 | 10/11/2018 | 10/11/2018 | | PASS |
Michael Zawacki
|
|
|
Field house is only remaining activity on site. Parking lot is paved and all landscaping complete.
|
General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 | | PASS |
Michael Zawacki
|
|
|
Parking lot complete, crews are now installing sod. Area is expected to have coverage in a week. Field house is nearing completion. No ESC issues at site.
|
General Inspection | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PASS |
Michael Zawacki
|
|
|
Only observed issue is washout is nearly full. Jan will get it cleaned or new one in before the next sidewalk pour. Water truck on site keeping dust down, no trackout reaching road.
|
General Inspection | 7/23/2018 | 7/23/2018 | 7/23/2018 | | PASS |
Michael Zawacki
|
|
|
Site is watered and free from dust. Guide line is up for curbing. Construction entrance in place, no tracking to fort. Second approach estimated to begin in the next week.
|
Tracking Control | 6/21/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Andy J. Long
|
|
|
No muddy trackout to street. Apron needs frequent sweeping or water to keep down dust at entrance. Stockpile is almost hauled off.
Approved.
|
General Inspection | 6/21/2018 | 6/21/2018 | 6/21/2018 | | FAIL |
Andy J. Long
|
|
|
Trackout to Fort Street. Dump trucks hauling off dirt do have a tracking pad to cross over.
Observed water truck rinsing street without a sweeper, potential for turbid non-stormwater discharge. MS4 inlets have sediment filter bags installed.
Correction request: - sweep apron, minimize rinsing to be acompanied by sweeping to prevent runoff.
Project manager Jan with Beniton notified of corrections. Stated stockpile hauloff will be completed tomorrow and sweeping and clean will increase instead of installing new rock entrance for this operation.
Follow up tomorrow PM
|
General Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 | | PASS |
Michael Zawacki
|
|
|
Met with project manager on site. Site is in good condition. Only correction request was to turn and freshen rock on entrance and to make sure drivers are not going around it.
|
General Inspection | 4/20/2018 | 4/20/2018 | 4/20/2018 | | PASS |
Michael Zawacki
|
|
|
Phase 2 under way. Pop up classrooms have been removed. Currently grading area and stockpiling, water truck on site. Natural buffer and wattle protecting fort street.
|
General Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 | | PASS |
Michael Zawacki
|
|
|
Talked with foreman on site. Phase 1 is complete. Phase two is scheduled to begin in a few weeks, as soon as plans are finalized. BMPs still in place, let them know we will be back when they start to check BMPs.
|
General Inspection | 2/15/2018 | 2/15/2018 | 2/20/2018 | | PASS |
Michael Zawacki
|
|
|
Area around half complete. Area aroung Cunningham St still exposed.
|
Site Final | 12/20/2017 | 12/20/2017 | 12/22/2017 | P | NR |
Andy J. Long
|
|
|
NR- not ready for site final
WIP. Two soccer/football fields complete and have turf, one softball/baseball field. Frontage along Fort still in progress. No trackout or discharges, no loose trash or materials exposed.
Permit is open. No corrections requested.
|
General Inspection | 8/28/2017 | 8/28/2017 | 8/28/2017 | A | PASS |
Andy J. Long
|
|
|
Grading and foundation construction in progress No trackout to Fort Street, water truck and tower on site for dust control, perimeter sediment controls and DI bags installed.
|
General Inspection | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Andy J. Long
|
|
|
No fugitive dust observed. Water truck and onsite filling station in use. No trackout to Fort Street. Site perimeter is clean. Approved.
|