Site Final | 4/29/2019 | 4/30/2019 | 5/2/2019 | A | PASS |
Andy J. Long
|
|
|
Construction complete. Distrubed area below pool has revegetated. No further ESC inspections.
|
General Inspection | 4/29/2019 | 4/29/2019 | 4/29/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/28/2019 | 3/28/2019 | 3/29/2019 | | PASS |
Andy J. Long
|
|
|
Last section of slope revegetating. Construction is complete. Should be ready for final in April/May
|
General Inspection | 3/13/2019 | 3/13/2019 | 3/13/2019 | | PASS |
Michael Zawacki
|
|
|
Some grass starting to grow.
|
General Inspection | 2/26/2019 | 2/26/2019 | 2/26/2019 | | PASS |
Michael Zawacki
|
|
|
Work completed, hillside not stable.
|
General Inspection | 2/11/2019 | 2/11/2019 | 2/11/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/25/2019 | 1/25/2019 | 1/25/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/10/2019 | 1/10/2019 | 1/10/2019 | | PASS |
Michael Zawacki
|
|
|
Currently working on stabalization.
|
General Inspection | 12/26/2018 | 12/26/2018 | 12/26/2018 | | PASS |
Michael Zawacki
|
|
|
Stabalization in progress.
|
General Inspection | 12/11/2018 | 12/11/2018 | 12/11/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/26/2018 | 11/26/2018 | 11/26/2018 | | PASS |
Michael Zawacki
|
|
|
BMPs removed. Hillside has been hydroseeded, no growth yet.
|
General Inspection | 11/9/2018 | 11/9/2018 | 11/9/2018 | | PASS |
Michael Zawacki
|
|
|
Neighboring lot cleaned, hillside in process of stabalization.
|
General Inspection | 10/25/2018 | 10/25/2018 | 10/26/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/10/2018 | 10/10/2018 | 10/10/2018 | | PASS |
Michael Zawacki
|
|
|
Area was tackified. Rain caused no rilling or erosion.
|
General Inspection | 9/21/2018 | 9/21/2018 | 9/21/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/6/2018 | 9/6/2018 | 9/6/2018 | | PASS |
Michael Zawacki
|
|
|
Hillside has been hydroseeded.
|
General Inspection | 8/22/2018 | 8/22/2018 | 8/22/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/17/2018 | 8/7/2018 | 8/8/2018 | A | PASS |
Michael Zawacki
|
|
|
Lot still needs landscaping below pool. Old silt fence still at site. Material storage has been removed from neighboring parcel.
|
General Inspection | 7/17/2018 | 7/17/2018 | 7/17/2018 | | PART |
Andy J. Long
|
|
|
No activity or crew onsite at time of inspection. Pool is installed but not yet complete. All permits open.
WIP installing wrought iron fence around yard which is not yet landscaped.
Silt fence below project will require maintenance/ re-installation if yard is not stabilized as part of the project.
No corrections requested at this time, no violations observed. Will check back in 3 weeks.
|
General Inspection | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | PASS |
Michael Zawacki
|
|
|
Pool looks complete. Hillside still needs landscaping. Silt fence under work area is starting to fall over. Materials are still stored on lot next door.
|
General Inspection | 6/28/2018 | 6/28/2018 | 6/29/2018 | | CANC |
Andy J. Long
|
|
|
|
Random Inspection | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Michael Zawacki
|
|
|
WIP. Using vacant lot next door for storage and access.
|