General Inspection | 8/3/2020 | 8/3/2020 | 8/4/2020 | | PASS |
Michael Zawacki
|
|
|
WIP on vertical. Site is fenced and contained. No issues.
|
General Inspection | 6/16/2020 | 6/16/2020 | 6/16/2020 | | PASS |
Andy J. Long
|
|
|
WIP on interior. Most of perimeter is stablized except on small section of 6th and 5th. No signiifcant trackout or discharges.
|
General Inspection | 5/1/2020 | 5/1/2020 | 5/1/2020 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/16/2020 | 3/16/2020 | 3/17/2020 | | PASS |
Michael Zawacki
|
|
|
Current activity with risk is masonary. Mixer is in secondary containment, washout on site. Scaffolding is also fenced so minimal amounts of mud falling. Will need to watch tracking from deliveries. At time of inspection there was an unattended hose turned on and running onto front street, water was starting to back up and will pick any pollutants in gutter.
|
General Inspection | 1/28/2020 | 1/29/2020 | 1/31/2020 | A | PASS |
Andy J. Long
|
|
|
check 5th street staging area - observed muddy stormwater
New curb and gutter being placed, street being swept , concrete drying. Washouts onsite.
Will follow up next week. No discharges, storm drain has sediment bag
|
General Inspection | 1/10/2020 | 1/10/2020 | 1/10/2020 | | PASS |
Michael Zawacki
|
|
|
Talkjed with Adam. Had a spill moving ecopan and are on it getting cleaned. No issues at site besides washout.
|
General Inspection | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | PART |
Andy J. Long
|
|
|
No signficant trackout, no discharges. Permit posted on 6th street. Site using Ecopan for concrete washout.
Corrections requested to RP Adam: - sweep gutter on 5th street - fix DI bag installed on storm drain on 5th at Front (west side of street)
Follow up scheduled.
|
General Inspection | 11/11/2019 | 11/11/2019 | 11/12/2019 | | PASS |
Andy J. Long
|
|
|
Perimter BMPs installed, permit posted. No trackout. Concrete washout bins are onsite. No corrections requested at this time
|
General Inspection | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | FAIL |
Andy J. Long
|
|
|
Concrete pump trucks are leaking oils and other materials onto 5th street and do not have drip pans or spill kits.
Notified RP Adam with ESI and called Parnell w/ Brundage Bone. He stated his mechanic will be focusing on the two trucks that are going to the site and will make sure they have drip pans/spill absorbent.
Follow up scheduled.
|
Tracking Control | 9/13/2019 | 9/13/2019 | 9/16/2019 | P | PASS |
Michael Zawacki
|
|
|
Follow up on concrete spill and completion of cleanup. Some staining, no large amounts on road.
|
Conference | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | DONE |
Michael Zawacki
|
|
|
Concrete delivery reversed drum on road. Concrete was dumped on 6th heading towards front. ITD, ACHD, EPA, & Boise City ESC were all notified. Curtis clean sweep on site. Concrete contractor is responsible for getting roads cleaned completely. ESI will install inlet protection in areas to prevent dust and debris from getting into drains. ACHD inspector determined cleanup was ok to get traffic moving but not an acceptable final cleanup.
|
General Inspection | 9/9/2019 | 9/9/2019 | 9/10/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 7/22/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/18/2019 | 7/18/2019 | 7/22/2019 | | CANC |
Andy J. Long
|
|
|
|