INSP-Final Inspection | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
Gerardo Arce is the contact. This inspection has already been done, reach out to the contact for more information. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/26/2019 | 3/26/2019 | 3/26/2019 | P | DONE |
Jim Page
|
|
|
Hydrstatic test for underground supply witnessed, no pressure loss observed.
Gerardo Arce is the contact. This inspection is for a Hydro only. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 3/18/2019 | 3/20/2019 | 3/20/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed by Mark Scharfen on 3/22/2019-building D was witnessed by Troy Cobbley and Mark Scharfen but wrong permit was signed off.
Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 1/24/2019 | 1/29/2019 | 1/29/2019 | A | FAIL |
Jim Page
|
|
|
Point of contact could not be reached.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 | P | CANC |
Troy Cobbley
|
|
|
Problem with hydro pump.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Underground Rough to Cover Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/17/2018 | 8/17/2018 | 8/17/2018 | P | CANC |
Jim Page
|
|
|
Undergound not ready for inspection, this request is cancelled and a new inspection will be rescheduled for when the underground supply is complete.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for undergorund supply, stub up and approximately 12 feet of pipie approved for cover, remaining underground to be inspected at a later date.
Underground rough to cover Phone #: ###-#### Inspection requested via web by Stan Beus
|