INSP-Final Inspection | 6/28/2019 | 7/1/2019 | 7/1/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Jim Page
|
|
|
Could not final, fire alarms not ready, this request is cancelled.
Gabe Garduno is the contact. Thank you for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test witnessed with no visible loss of pressure.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | FAIL |
Troy Cobbley
|
|
|
Underground hydro test failed due to visible loss on the guage.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PASS |
Troy Cobbley
|
|
|
Supply line re-flush witnessed
|
INSP-Sprinkler Rough-in | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line had a leak, was repaired and now can be re-covered.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed.
|
INSP-Supply line flush | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Gabe Garduno is the contact. Stacey with Suez will be at this building as well as 11783 at 10:00 AM to do this underground flush. This inspection is to be at the same time as above ground hydros for both buildings as well. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | CANC |
Troy Cobbley
|
|
|
Underground supply line piping and the breeze way underground piping is ok for cover.
Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus//
cancel inspection per Troy Cobbley 3-27-19 j.a
|