Information based on query as of Saturday, May 11, 2024.
Permit Information
Permit NumberFIR18-00804
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 6001 W CASSIA ST
Project NameBorah HS Dry Pipe Sprinkler
Customer Number 
ePlanReviewYes
Description
In the three classroom wings, remove the sprinkler system from the top of dry pipe valve. Replace with new material. The existing underground, riser, FDC, bulk main and dry pipe valves with trim to remain as is. Shilo to install a nitro generator to supply the the three dry systems.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/29/20204/30/20204/30/2020PPASS
DetailsTroy Cobbley
permit finaled

Jon Beazer is the contact. Thanks! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection11/15/201911/15/201911/15/2019PCANC
DetailsJim Page
Reference notes entered on 01APR2019, address still has FIR permits in issued status for dry systems (FIR18-00719) as well as AES communicator that failed last inspection (FIR18-00161). Point of contact has been informed of related FIR permits that need to be followed up on before this permit can be finaled.

on is the field contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/1/20194/1/20194/1/2019PPASS
DetailsJim Page
Rough to cover inspection for wing C complete. All rough in inspection for this project complete.
INSP-Final Inspection3/29/20194/1/20194/1/2019PPART
DetailsJim Page
Final trip test for wing C complete at 50 seconds. Final inspection for wing C complete, auto purge devices need to be relocated out of the attic space, temperature for auto purges per installation requirements specifies that purge unit needs to be in temperature controlled environment between -4 degrees farenheit to 122 degrees farenheit, the attic space has the ability to exceed these limits. FIR permit for fire sprinkler will not be finaled until address related fire alarm and AES permits are inspected and finaled.

Richard Clark is the contact. This final inspection is for wing C. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/1/20194/1/20194/1/2019PDONE
DetailsJim Page
24 hour air test complete per conversation with Troy Cobbley.
INSP-Conference3/28/20193/28/20193/28/2019PDONE
DetailsTroy Cobbley
24 hour air test for C wing started at 1:30 with 48psi on the guage.

Richard Clark is the contact. He would like a 24-hour air test for wing C, we just weren''t sure which option to put it under. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection3/26/20193/27/20193/27/2019PPART
DetailsJim Page
Trip tests for wings A & B were met with satisfactory trip times, wing a time was 45 seconds, wing B was 48 seconds.

Richard Clark is the contact. This final is for wings A ; B. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro3/26/20193/27/20193/27/2019PDONE
DetailsJim Page
Hydrostatic test for wing C witnessed, system gained 3 pounds during test.

Richard Clark is the contact. This hydro only is for wing C. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Alarm Testing3/25/20193/26/20193/26/2019PFAIL
DetailsJim Page
Too much water in piping during trip test, time was not met on system A, took 1 minute and 56 seconds for water to reach inspectors test.

Richard Clark is the contact. He requests a Trip Test for wings A ; B after school. Thank you for your hard work!
Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Alarm Testing3/25/20193/26/20193/25/2019PCANC
DetailsTroy Cobbley
Richard Clark is the contact. He requests a Trip Test and wants it to take place after school. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro3/22/20193/22/20193/22/2019PPASS
DetailsTroy Cobbley
The 24 hour air test of wings A and B witnesses
INSP-Sprinkler Rough-in/Hydro3/21/20193/21/20193/21/2019PPART
DetailsTroy Cobbley
24 hour air test started at 2:30 with 42psi on both guages for wings A and B.
INSP-Sprinkler Rough-in/Hydro3/21/20193/21/20193/21/2019PPART
DetailsJim Page
Rough in inspection for wings A & B complete.

This Rough-in/hydro is for wings A ; B. The contact is Richard Clark. Thank your for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro3/21/20193/21/20193/21/2019PPASS
DetailsTroy Cobbley
This Rough-in/hydro for wings A ; B was witnessed with no visible loss at the guages.
INSP-Sprinkler Rough-in/Hydro3/20/20193/20/20193/20/2019PCANC
DetailsTroy Cobbley
To be rescheduled for tomorrow. This Rough-in/Hydro is for wings A ; B. The contact is Richard Clark. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in2/18/20192/19/20192/19/2019APART
DetailsJim Page
Inspection turned into a conference, vic couplings on verticals will need to be changed to flexible vices.

Richard Clark is the contact. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus