Permit Information
Permit NumberFIR18-00913
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 12251 W FRANKLIN RD
Project NameCJD Investment
Customer Number 
ePlanReviewYes
Description
Underground Submittal only - Phoenix Fire Point of connection to be Approx 50 FT from Bldg after tee and Valve by others.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/17/20196/17/20196/17/2019PPASS
DetailsTroy Cobbley
Permit finaled

Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection6/15/20196/17/20196/17/2019ACANC
DetailsTroy Cobbley
Contractor was not ready for inspection when I wasContact Andrew Larson 208###-#### 30 min prior to UG Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro6/13/20196/14/20196/14/2019APASS
DetailsTroy Cobbley
The underground hydro test was witnessed.
INSP-Sprinkler Rough-in/Hydro6/11/20196/11/20196/11/2019PCANC
DetailsTroy Cobbley
Point of Contact is Andrew Larson ###-#### please call him 30 min prior to UG Hydro insp start time.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Conference6/10/20196/10/20196/10/2019PDONE
DetailsTroy Cobbley
I let Andrew know that if they need to repair the underground piping a new flush and hydro would be required.
INSP-Sprinkler Rough-in/Hydro6/6/20196/7/20196/7/2019ACANC
DetailsTroy Cobbley
The underground supply piping is still losing pressure. Was not able to start a test.

Contact Andrew Larson ###-#### 30 min prior to UG Hydro start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection6/5/20196/6/20196/6/2019AFAIL
DetailsTroy Cobbley
The underground hydro failed due to visible loss on the guage.

Contact Andrew Larson ###-#### 30 Min Prior to UG Final start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Supply line flush5/22/20195/22/20195/22/2019APASS
DetailsTroy Cobbley
.The underground supply line flush was witnessed and a verified flow of over 1500 gpm

Contact Andrew Larson ###-#### 30 min prior to Flush Insp start pelase

Thank YOU,
Teri Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in1/22/20191/23/20191/22/2019APASS
DetailsTroy Cobbley
The remaining underground supply piping is ok for cover. Mechanical restraint was used and four additional 45 fittings have been used which will need to be included in the overhead hydraulic calculations.

Contact Leroy Anderson - ###-#### 30 min prior to UG RTC Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in1/18/20191/22/20191/18/2019ACANC
DetailsTroy Cobbley
Contact Leroy Anderson ###-#### 30 Min prior ot UG RTC insp. start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in12/27/201812/28/201812/28/2018APASS
DetailsTroy Cobbley
Underground stub out is ok for cover.

rough to cover // Leroy Phone #: ###-####
INSP-Sprinkler Rough-in12/19/201812/20/201812/20/2018PFAIL
DetailsTroy Cobbley
No underground supply piping has even been installed yet per the general contractor


Contact Keith Orahood ###-#### 30 Min prior to UG RTC Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in12/19/201812/19/201812/19/2018PCANC
DetailsTroy Cobbley
Contact Keith Orahood - ###-#### 30 min prior to UG RTC Insp start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank