Information based on query as of Saturday, May 4, 2024.
Permit Information
Permit NumberFIR19-00126
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 2675 W MAIN ST
Project NameRev 22 Church
Customer Number 
ePlanReviewYes
Description
Add new sprinkler system to existing Bldg. Underground permit FIR19-00094
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/15/20197/15/20197/15/2019PPASS
DetailsJim Page
Final inspection complete.

Phone #: ###-#### Inspection requested via web by Scott Carter II
INSP-Sprinkler Rough-in/Hydro7/2/20197/3/20197/3/2019ADONE
DetailsJim Page
Hydrostatic test for basement level witnessed, no pressure loss observed.

Contact Noemi Carrero ###-#### 30 min prior to Hydro Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro7/1/20197/2/20197/2/2019PPART
DetailsJim Page
Hydrostatic test for level 1 witnessed, no pressure loss observed.

Contact Noemi Carrero ###-#### 30 min Prior to OH Hydro Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro7/2/20197/2/20197/2/2019PFAIL
DetailsJim Page
Basement level lost 4PSI during hydro, visible leak in corridor.
INSP-Sprinkler Rough-in6/19/20196/19/20196/19/2019PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in basement level complete, approved for cover, notated city approved drawings 3 areas that has exposed combustibles above ceiling grid, sprinkler protection will be required for mentioned areas, will verify coverage is in place during a follow up inspection. Level 1 sprinkler rough in complete.

Contact Ken Orahood ###-#### 30 min prior to RTC Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in5/7/20195/8/20195/8/2019APART
DetailsMark Stumbaugh
***OK to cover the pipe chase. Heads added on both side of the spiral duct as requested. Still waiting on heads to be installed in stairwell ceilings.**MAS**
Contact Ken Orahood ###-#### 30 min prior to RTC insp start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in5/6/20195/6/20195/6/2019PFAIL
DetailsTroy Cobbley
** Head needs to be added on other side of duct. If sheetrock doen't go all the way to the deck a head outside the chase on both sides of the duct would be acceptable.***MAS***
Contact Ken Orahood - ###-#### 30 min prior to RTC Insp start please

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in4/29/20194/29/20194/29/2019PDONE
DetailsTroy Cobbley
OK to cover hard ceilings only. Pipe chase needs to stay open. Need to add heads for 24" spiral duct. Area above ceiling in back stairwell needs to stay open till heads are installed. *MAS* Contact Ken Orahood - ###-#### 30 Min Prior to RTC insp start please

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank