INSP-Final Inspection | 5/18/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Todd Ketterling is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PART |
Jim Page
|
|
|
Partial final inspection is complete, fire sprinkler riser monitoring is complete, intial walkthrough is complete, permit will remian in issued status until BLD permit gets close to final life fire safety inspection. Sprinkler riser monitoring is to remain active. Furniture storage inside the building is authorized provided sprinklers remain active and monitored.
Todd Ketterling is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/6/2020 | 4/6/2020 | 4/6/2020 | P | PART |
Troy Cobbley
|
|
|
Forward flush passed. The interconnection with the fire alarm system was not ready for inspection.
Todd Ketterling is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/6/2020 | 4/6/2020 | 4/6/2020 | P | CANC |
Jim Page
|
|
|
Todd Ketterling is the contact Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/2/2020 | 4/3/2020 | 4/3/2020 | A | DONE |
Jim Page
|
|
|
Hydrostaic test for overhead fire sprinkler piping, levels 1 and 2 witnessed, no pressure loss observed.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/2/2020 | 4/3/2020 | 4/3/2020 | A | CANC |
Jim Page
|
|
|
Rescheduled for 06APR2020 per conversation with the GC and point of contact, sprinklers are ready to be made active but ceiling tiles missing in numerous areas. Per conversation with GC ceiling tiles should be in by the coordinated date, this requestb is cancelled.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | CANC |
Jim Page
|
|
|
Hydrostatic test to be rescheduled, did not get pumped up in the alotted time, this request is cancelled.
Todd Ketterling is the contact. Thanks(: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for remaining overhead fire sprinkler piping in cafeteria complete, approved for cover.
Todd Ketterling is the contact. Thanks for all your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/17/2020 | 3/17/2020 | 3/17/2020 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Aron Foster is the contact. Thanks! Have a great day Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PART |
Jim Page
|
|
|
Overhead fire sprinkler piping in kitchen area approved for cover.
Aron Foster is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for level 1 areas A and B complete, level 1 areas A and B approved for cover.
Aron Foster is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/21/2020 | 2/21/2020 | 2/21/2020 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Aron Foster is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Cole Bierman is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/19/2020 | 2/20/2020 | 2/19/2020 | P | CANC |
Jim Page
|
|
|
Cole Bierman is the contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Aron Foster is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/27/2020 | 1/28/2020 | 1/28/2020 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping above hardlids complete, city approved plans have been notated areas approved for cover.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | A | FAIL |
Jim Page
|
|
|
Numerous upright heads have been painted in the classroom closets, sprinkler heads will need to be replaced per 2016 NFPA13, section 6.2.6.2.2, sprinkler heads cannot be cleaned.
|
INSP-Sprinkler Rough-in | 1/16/2020 | 1/17/2020 | 1/17/2020 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Todd Ketterling is the contact for this RTC inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | CANC |
Jim Page
|
|
|
Rescheduled for 17JAN2020, this request is cancelled.
Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/3/2020 | 1/6/2020 | 1/6/2020 | P | PART |
Jim Page
|
|
|
Onsite city approved plans have been marked with red ink hardlids that are approved for cover.
Todd Ketterling is the contact for this RTC inspection. We appreciate your help. Thank you Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping above hardlids complete, notated city approved drawings with red ink areas approved for cover.
Todd is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 12/19/2019 | 12/20/2019 | 12/19/2019 | A | CANC |
Jim Page
|
|
|
Todd Ketterling is the contact. I have scheduled this with the water department for 10:30 AM. Thank you for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PART |
Jim Page
|
|
|
Initial walk through for rough in inspection for overhead fire sprinkler piping complete, a seperate inspection will need to be requested for a cover inspection after finsh heads are cut in.
Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|