Permit Information
Permit NumberMEC18-03406
StatusFinaled
Name AMERICAN MECHANICAL
Site Address 367 N ANCESTOR PL
Project Name 
Customer Number 
ePlanReviewNo
Description
New: Furnish and Install labor, materials as per subcontract agreement for HVAC Mechanical System
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final12/14/201812/17/201812/17/2018APASS
DetailsBrian Scoles
Please contact Rich Beckstead (###-####) if you have any questions. Phone #: ###-#### Inspection requested via web by Beka Hereau- final ok- card signed
Final11/1/201811/2/201811/2/2018APART
DetailsBrian Scoles
Final Inspection - Contact Rich ###-#### Phone #: ###-#### Inspection requested via web by Beka Hereau- temp occupancy ok- need uv protection on lineset on roof- need clarification on missing R/A 2nd floor not there is engineer ok without it- rest is good
Rough-in10/9/201810/9/201810/9/2018APASS
DetailsBrian Scoles
look at R/A in wall- R/I ok- ok to install all R/A registers in plenum walls
Rough-in9/27/20189/27/20189/27/2018ACANC
DetailsBrian Scoles
wrong permit was scheduled
Rough-in9/26/20189/27/20189/27/2018APASS
DetailsBrian Scoles
2nd floor for cover Phone #: ###-#### Inspection requested via web by Beka Hereau- 2nd floor ok- ok for ceiling tiles- 1st floor whole building ok for ceiling tiles- roof good just need 1 exhaust installed 3 feet above economizers and uv protection on all linesets and clamped to supports- call in R/I when exhaust duct is installed to grid guess dishwasher hood is omitted per general
Rough-in9/24/20189/25/20189/25/2018APART
DetailsBrian Scoles
1st floor ceiling for cover Phone #: ###-#### Inspection requested via web by Beka Hereau- R/I ok 1st floor only excluding plenum area needs plenum rated insulation on all piping- ok for ceiling tiles first floor area discussed with contractor
Rough-in8/27/20188/27/20188/27/2018PPASS
DetailsBrian Scoles
look at wall R/A- 13 R/A ducts east exterior wall ok- ok to cover pending other inspections- NW corner room needs plenum rated insulation on all piping by final
Rough-in8/24/20188/27/20188/27/2018APART
DetailsBrian Scoles
Contact Rich Beckstead ###-####. Inspection for Cover Phone #: ###-#### Inspection requested via web by Beka Hereau- still installing last one- all ducting needs sealed with mastic
Rough-in8/8/20188/9/20188/9/2018PPART
DetailsBrian Scoles
Request for cover upstairs and downstairs bathroom Phone #: ###-#### Inspection requested via web by Beka Hereau- 1st and 2nd floor bathrooms seal ok- ok to cover- recall in r/i when insulation, all taps and mini split lineset are install
Rough-in8/8/20188/8/20188/8/2018PFAIL
DetailsBrian Scoles
Request for cover upstairs and downstairs bathroom Phone #: ###-#### Inspection requested via web by Beka Hereau- need to finish exhaust duct thru roof and seal- need to seal oval to round off fan and seal both first and second floors and attach with screws- need tranfers first floor thats missing and register installed- talked with installer onsite- recall in when ready
Rough-in8/6/20188/6/20188/6/2018PPASS
DetailsTroy James
Met general on site to discuss plenum wall. Approve rfi design by mechanical engineer.
Rough-in7/31/20188/1/20188/1/2018APART
DetailsBrian Scoles
Rough in in office area - Duct Sealing
Contact Rich Beckstead ###-#### Phone #: ###-#### Inspection requested via web by Beka Hereau- seal on first and second floor ok- ok to insulate- still need RFI issued on plenum walls- do not cover any plenum walls at this time- plenums must use plenum rated materials
Rough-in7/25/20187/26/20187/26/2018APEND
DetailsBrian Scoles
Wall Inspection Phone #: ###-#### Inspection requested via web by Beka Hereau- need to be in loop of emails on whats going on with walls- general contractor forwarded me emails and we will take a look at them- ok to cover walls that do not have plenum in them- all others need to hold off until later date and we have time to look into this
Conference7/17/20187/17/20187/17/2018PDONE
DetailsTroy James
Meet brian at 3:00
Contractor to verify material in wall is plenum rated or redesign system by mechanical engineer.

Conference7/17/20187/17/20187/17/2018PDONE
DetailsBrian Scoles
meet troy 3 pm- engineer is looking into alternative routing in walls- will submit drawings when figured out
Rough-in7/16/20187/17/20187/17/2018APART
DetailsBrian Scoles
Partial Rough In Phone #: ###-#### Inspection requested via web by Beka Hereau- seal on rtu 2, 3, 4, 5 and 6 main lines only ok- need to verify SMACNA for hanger supports on duct