Final | 12/14/2018 | 12/17/2018 | 12/17/2018 | A | PASS |
Brian Scoles
|
|
|
Please contact Rich Beckstead (###-####) if you have any questions. Phone #: ###-#### Inspection requested via web by Beka Hereau- final ok- card signed
|
Final | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | PART |
Brian Scoles
|
|
|
Final Inspection - Contact Rich ###-#### Phone #: ###-#### Inspection requested via web by Beka Hereau- temp occupancy ok- need uv protection on lineset on roof- need clarification on missing R/A 2nd floor not there is engineer ok without it- rest is good
|
Rough-in | 10/9/2018 | 10/9/2018 | 10/9/2018 | A | PASS |
Brian Scoles
|
|
|
look at R/A in wall- R/I ok- ok to install all R/A registers in plenum walls
|
Rough-in | 9/27/2018 | 9/27/2018 | 9/27/2018 | A | CANC |
Brian Scoles
|
|
|
wrong permit was scheduled
|
Rough-in | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Brian Scoles
|
|
|
2nd floor for cover Phone #: ###-#### Inspection requested via web by Beka Hereau- 2nd floor ok- ok for ceiling tiles- 1st floor whole building ok for ceiling tiles- roof good just need 1 exhaust installed 3 feet above economizers and uv protection on all linesets and clamped to supports- call in R/I when exhaust duct is installed to grid guess dishwasher hood is omitted per general
|
Rough-in | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PART |
Brian Scoles
|
|
|
1st floor ceiling for cover Phone #: ###-#### Inspection requested via web by Beka Hereau- R/I ok 1st floor only excluding plenum area needs plenum rated insulation on all piping- ok for ceiling tiles first floor area discussed with contractor
|
Rough-in | 8/27/2018 | 8/27/2018 | 8/27/2018 | P | PASS |
Brian Scoles
|
|
|
look at wall R/A- 13 R/A ducts east exterior wall ok- ok to cover pending other inspections- NW corner room needs plenum rated insulation on all piping by final
|
Rough-in | 8/24/2018 | 8/27/2018 | 8/27/2018 | A | PART |
Brian Scoles
|
|
|
Contact Rich Beckstead ###-####. Inspection for Cover Phone #: ###-#### Inspection requested via web by Beka Hereau- still installing last one- all ducting needs sealed with mastic
|
Rough-in | 8/8/2018 | 8/9/2018 | 8/9/2018 | P | PART |
Brian Scoles
|
|
|
Request for cover upstairs and downstairs bathroom Phone #: ###-#### Inspection requested via web by Beka Hereau- 1st and 2nd floor bathrooms seal ok- ok to cover- recall in r/i when insulation, all taps and mini split lineset are install
|
Rough-in | 8/8/2018 | 8/8/2018 | 8/8/2018 | P | FAIL |
Brian Scoles
|
|
|
Request for cover upstairs and downstairs bathroom Phone #: ###-#### Inspection requested via web by Beka Hereau- need to finish exhaust duct thru roof and seal- need to seal oval to round off fan and seal both first and second floors and attach with screws- need tranfers first floor thats missing and register installed- talked with installer onsite- recall in when ready
|
Rough-in | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Troy James
|
|
|
Met general on site to discuss plenum wall. Approve rfi design by mechanical engineer.
|
Rough-in | 7/31/2018 | 8/1/2018 | 8/1/2018 | A | PART |
Brian Scoles
|
|
|
Rough in in office area - Duct Sealing Contact Rich Beckstead ###-#### Phone #: ###-#### Inspection requested via web by Beka Hereau- seal on first and second floor ok- ok to insulate- still need RFI issued on plenum walls- do not cover any plenum walls at this time- plenums must use plenum rated materials
|
Rough-in | 7/25/2018 | 7/26/2018 | 7/26/2018 | A | PEND |
Brian Scoles
|
|
|
Wall Inspection Phone #: ###-#### Inspection requested via web by Beka Hereau- need to be in loop of emails on whats going on with walls- general contractor forwarded me emails and we will take a look at them- ok to cover walls that do not have plenum in them- all others need to hold off until later date and we have time to look into this
|
Conference | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | DONE |
Troy James
|
|
|
Meet brian at 3:00 Contractor to verify material in wall is plenum rated or redesign system by mechanical engineer.
|
Conference | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | DONE |
Brian Scoles
|
|
|
meet troy 3 pm- engineer is looking into alternative routing in walls- will submit drawings when figured out
|
Rough-in | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PART |
Brian Scoles
|
|
|
Partial Rough In Phone #: ###-#### Inspection requested via web by Beka Hereau- seal on rtu 2, 3, 4, 5 and 6 main lines only ok- need to verify SMACNA for hanger supports on duct
|