Permit Information
Permit NumberBLD17-03128
StatusFinaled
Name CM COMPANY
Site Address 11255 W FAIRVIEW AVE
Project NameICCU Fairvew Branch
Customer Number 
ePlanReviewYes
Description
(IDAHO CENTRAL CREDIT UNION) **Permit for the construction of a new 9,300 sq. ft. building with work to include a 6,500 sq. ft. main structure, a 2,850 sq. f.t covered drive thru, and related site improvements. This building is not Fire Sprinklered. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/16/201811/6/2018 DONE
mailed 11-12
Second Notice 9/20/201810/11/2018 DONE
mailed 10-12-18
First Notice 9/9/20189/10/2018 DONE
mailed 9-11-18
Permanent Occupancy  8/30/2018 DONE
PubWorks Occupancy Approval8/21/20188/21/20188/21/2018 DONE
DetailsTiffany Lowery
BLD-Final8/20/20188/20/20188/20/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Darrell Gogert. Ok for temp occ. Will be ok for perm occ. once plumbing and electrical sign perm.
Zoning Approval8/20/20188/20/20188/20/2018 PASS
DetailsKatelyn Menuge
Permanent Occupancy Pass
Routing - Addressing8/20/2018 8/20/2018 PASS
DetailsLaura Hunter
Corrected parcel and address number to 11255 W Fairview Ave. Spoke with Darrell at CM 8/20/18
FIRE-Final Inspection8/16/20188/17/20188/17/2018APASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguishers are place with current inspection tags, building does have a knox box installed by main entry, addressing on permit needs to be changed to the correct property address before BLD final. Final life fire safety inspection complete.

Daryl Phone #: ###-####
BLD-Other8/14/20188/15/20188/15/2018PCANC
DetailsMike Jordan
We are in need of a Zoning inspection. all landscape is complete. Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Ceiling Grid Inspection8/14/20188/14/20188/14/2018PPASS
DetailsMike Jordan
Grid inspection for drive through. Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Ceiling Grid Inspection7/23/20187/24/20187/25/2018PPASS
DetailsBrandon Shaw
Good to cover perimeter
OK to cover grid, pending Mech approval
BLD-Other6/19/20186/19/20186/19/2018APASS
DetailsMike Jordan
wall cover and check the framing in the ATM and mechanical room. Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Framing/Rough-in6/14/20186/15/20186/15/2018APASS
DetailsMike Jordan
ceiling in the front entry vestibule. Phone #: ###-#### Inspection requested via web by Darrell Gogert..HArdlid at main entry, Sofit framing around skylight.
BLD-Framing/Rough-in6/13/20186/13/20186/13/2018PNR
DetailsMike Jordan
rough framing remainder Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Framing/Rough-in6/8/20186/8/20186/8/2018PPASS
DetailsMike Jordan
Soffits Phone #: ###-#### Inspection requested via web by Darrell Gogert. Interior soffits ok.
BLD-Framing/Rough-in5/31/20186/4/20186/4/2018ANR
DetailsMike Jordan
interior and soffits. will call when trade inspections are complete Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Framing/Rough-in6/1/20186/1/20186/1/2018PPART
DetailsMike Jordan
Interior walls excluding the plumbing wall at restrooms. Phone #: ###-#### Inspection requested via web by Darrell Gogert. Interior framed walls only ok, pending plumbing rough in inspection
BLD-Framing/Rough-in5/31/20185/31/20185/31/2018PNR
DetailsMike Jordan
Interior walls and soffits. Phone #: ###-#### Inspection requested via web by Darrell Gogert. Needs plumbing and electrical rough in inspections first.
BLD-Energy code compliance5/29/20185/30/20185/30/2018APASS
DetailsMike Jordan
Exterior walls Phone #: ###-#### Inspection requested via web by Darrell Gogert. Exterior walls only.
BLD-Framing/Rough-in5/21/20185/22/20185/22/2018APART
DetailsMike Jordan
interior framing before insulation Phone #: ###-#### Inspection requested via web by Darrell Gogert. Upper framing only ok for insulation.
BLD-Framing/Rough-in5/21/20185/21/20185/21/2018PPASS
DetailsMike Jordan
soffit framing Phone #: ###-#### Inspection requested via web by Darrell Gogert. Steel studs for soffits ok.
BLD-Wall Bracing5/15/20185/15/20185/15/2018PPASS
DetailsMike Jordan
Shear wall inspection for drive through. Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Framing/Rough-in5/9/20185/9/20185/9/2018APASS
DetailsMike Jordan
Inspection needed on shear wall rough framing at drive through. Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Wall Bracing5/3/20185/3/20185/3/2018APASS
DetailsJim Sly
Shear wall screw inspection Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Framing/Rough-in4/27/20184/30/20184/30/2018APASS
DetailsMike Jordan
Jimmy Phone #: ###-####. Exterior sheathing attachment ok.
BLD-Framing/Rough-in4/18/20184/19/20184/19/2018PPASS
DetailsMike Jordan
Exterior framing/structural steel Phone #: ###-#### Inspection requested via web by Darrell Gogert. Exterior steel stud framing only.
BLD-Framing/Rough-in4/17/20184/17/20184/17/2018PNH
DetailsMike Jordan
Exterior framing/structural steel Phone #: ###-#### Inspection requested via web by Darrell Gogert
BLD-Wall Bracing4/2/20184/2/20184/2/2018PPART
DetailsMike Jordan
Shear wall at the vault. Phone #: ###-#### Inspection requested via web by Darrell Gogert. Interior wall on gridline D by bank vault only ok. Need to verifiy holdowns at this location.
BLD-Foundation3/7/20183/7/20183/7/2018APASS
DetailsMike Jordan
I need an inspection on foundation rebar. we will be placing concrete at 12:00 Phone #: ###-#### Inspection requested via web by Darrell Gogert. North retaining wall ok.
BLD-Footing2/20/20182/21/20182/21/2018ADEFR
DetailsMike Jordan
Daryl Phone #: ###-####. Pending speciial innspection.
BLD-Energy code compliance2/15/20182/16/20182/15/2018APASS
DetailsMike Jordan
Foundation insulation - Daryl Phone #: ###-####
BLD-Footing2/15/20182/15/20182/15/2018PPART
DetailsMike Jordan
Late afternoon - Daryl Phone #: ###-####. INterior footing for shear wall, exterior column pad footings for canopy at drivethrough.
BLD-Foundation2/7/20182/9/20182/9/2018APASS
DetailsDave Hannah
Darrell Phone #: ###-####
BLD-Foundation2/1/20182/2/20182/2/2018ACANC
DetailsMike Jordan
DARYL - THEY ARE PLANNING ON POURING AT NOON SO THE EARLIER THE BETTER - PLEASE Phone #: ###-####
BLD-Footing2/2/20182/2/20182/2/2018APART
DetailsMike Jordan
DARYL - THEY ARE PLANNING ON POURING AT NOON SO THE EARLIER THE BETTER - PLEASE Phone #: ###-####. Perimeter footings, work in progress, almost complete. Ok to place conc. pending ok from special inspection agency.
Issue PAID IN FULL permit  1/17/2018 DONE
Print Occupancy Form  1/17/2018 DONE
Telephone call  1/16/2018 DONE
we received a check in the mail but the amount was not for the total due-i called Annie at CM Co-she contacted Id. Central and they wanted us to post the check we have now and they'll send another check for the difference
Telephone call  1/5/2018 DONE
Dave Moe with CM Company called- i told him we needed the ACHD letter before we could give him the total due
OVERRIDE  12/18/2017  
Plan assigned to (JAR)10/23/201710/23/201712/18/2017 DONE
DetailsJulie Romig
**1st Rev Comp - 2nd Rec'd 12/12 - 502 Idaho Central Credit Union
Routing Off Site - STRUCTURAL12/12/2017 12/18/2017 PASS
DetailsJulie Romig
2nd Review
Routing - PLAN CHECK12/12/2017 12/18/2017 PASS
DetailsJulie Romig
2nd Review
PLANS/APPL TAKEN TO FRONT DESK  12/18/2017 DONE
Permit Ready to Issue  12/18/2017 DONE
MET-NEED ACHD
RP - met
ACHD-MET
GC FORM-MET
REVISED CERT-MET
Route to Impact Fee Review11/29/201712/2/201712/4/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  11/29/2017 FAIL
DetailsJulie Romig
Routing - PLAN CHECK10/23/2017 11/29/2017 FAIL
DetailsJulie Romig
See plan review report for required corrections.
Routing PW Drainage10/23/2017 11/7/2017 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL10/23/2017 11/2/2017 PASS
DetailsJulie Romig
Routing PW Sewer Design10/23/2017 10/31/2017 PASS
DetailsKyle S. Rosenmeyer
Routing - FIRE10/23/201710/23/201710/26/2017 PASS
DetailsScott Arellano
Attached review comments to case
Routing PW Solid Waste10/23/2017 10/25/2017 PASS
DetailsEvan Carpenter
Intake Approval  10/23/2017 PASS
Routing PW Street Lights10/23/2017 10/23/2017 PASS
DetailsTom Marshall
Routing - Design Review10/23/2017 10/23/2017 PASS
DetailsAndrea Tuning
Routing - MECHANICAL10/23/2017 10/23/2017 PASS
DetailsTroy James
Routing - PLUMBING10/23/2017 10/23/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing - PLANNING10/23/2017 10/23/2017 PASS
DetailsBrent Moore
Routing - PLANNING Land Div10/23/2017 10/23/2017 PASS
DetailsTodd Tucker
Routing - Addressing10/23/2017 10/23/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/23/2017 10/23/2017 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment10/23/2017 10/23/2017 PASS
DetailsMichael Zawacki
Needs RP
Intake Approval  10/5/2017 FAIL
DetailsRob Patrick
Steve, Please provide the following:
1. Verification of Legal Lot or Parcel document needs signed & dated. Contact Todd Tucker (TTucker@cityofboise.org) for the Verification of Legal Lot or Parcel signed approval.
2. Provide a completed form #310 - Statement of Special Inspections.
3. Provide dwg FP2.1 for Smoke Alarms and Carbon Monoxide detectors denoted in the Architectural/Life Safety Plans area of the checklist.
4. Please sign and date the checklist form #502.
Thank you
Rob Patrick
Application received  8/31/2017 DONE
Application submitted via PDS Online on Aug 31 2017 9:20AM